643.4 Railroads: Difference between revisions
| (32 intermediate revisions by 6 users not shown) | |||
| Line 1: | Line 1: | ||
==643.4.1 Introduction and Overview for Highway Construction Projects | [[image:643.4.jpg|right|275px]] | ||
==643.4.1 Introduction and Overview for Highway Construction Projects Impacting Railroads== | |||
{|style="padding: 0.3em; margin-right:7px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="210px" align="left" | {|style="padding: 0.3em; margin-right:7px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="210px" align="left" | ||
|- | |- | ||
| Line 6: | Line 8: | ||
|[http://library.modot.mo.gov/RDT/reports/Ri05053/or08001.pdf Report 2007] | |[http://library.modot.mo.gov/RDT/reports/Ri05053/or08001.pdf Report 2007] | ||
|} | |} | ||
Railroad projects involve a variety of issues, including crossing signals, stop and yield signs, surfacing, traffic signal preemption and grade separations. Some of these may be funded by the Multimodal Division, by MoDOT districts, by both or by other entities. Projects involving work on or over railroad right of way or involving adjustment of railroad facilities require the timely submittal of plans to the Central Office in order to avoid delays in the monthly bid opening. The district is responsible for providing the necessary plans and details to [http:// | Railroad projects involve a variety of issues, including crossing signals, stop and yield signs, surfacing, traffic signal preemption and grade separations. Some of these may be funded by the Multimodal Division, by MoDOT districts, by both or by other entities. Projects involving work on or over railroad right of way or involving adjustment of railroad facilities require the timely submittal of plans to the Central Office in order to avoid delays in the monthly bid opening. The district is responsible for providing the necessary plans, typical sections and details to [http://sharepoint/systemdelivery/MO/rail/default.aspx Multimodal Operations - Railroads (MO-RR)] where negotiations with railroads are conducted. | ||
{|style="padding: 0.3em; margin-left:7px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right" | {|style="padding: 0.3em; margin-left:7px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right" | ||
|- | |- | ||
|'''Forms''' | |'''Forms''' | ||
|- | |- | ||
|[ | |[https://epg.modot.org/forms/CM/C9_Daily_Utility_Report.pdf Daily Utility Report (C-9)] | ||
|- | |- | ||
|[[media:643.4.2 Railroad Crossing Inspection - Form C - 10.doc|Railroad Crossing Inspection (C-10)]] | |[[media:643.4.2 Railroad Crossing Inspection - Form C - 10.doc|Railroad Crossing Inspection (C-10)]] | ||
|- | |- | ||
|[ | |[https://epg.modot.org/forms/CM/C13_Final_Utility_Report.pdf Final Utility Report (C-13)] | ||
|- | |- | ||
|[[Media:643.4 Highway -Railroad Crossing Data (M-D-20).doc|Form D-20, Highway-Railroad Crossing Data]] | |[[Media:643.4 Highway -Railroad Crossing Data (M-D-20).doc|Form D-20, Highway-Railroad Crossing Data]] | ||
| Line 26: | Line 28: | ||
|} | |} | ||
===643.4.1.1 | ===643.4.1.1 Highway Construction Projects With Railroad Involvement=== | ||
Projects that include the construction or modification of a highway bridge over a railroad are called overhead grade separation projects. Projects that include the construction of a bridge that takes the tracks over the highway are called underpass projects because the road passes under the railroad. Parallel projects include the construction of roadways, slopes and ditches parallel to and on the railroad right of way, but not across the track. Other projects with railroad involvement include the construction of a new railroad crossing, the widening of an existing crossing, or the resurfacing of highways approaches to a crossing. These are called at-grade projects. Agreements with railroads are secured whenever MoDOT constructs a roadway over, under or across a railroad’s track. A new agreement is also secured whenever a bridge is replaced or widened over a railroad track or whenever an at-grade crossing is widened or relocated. However, a new agreement is not needed for the rehabilitation or the maintenance of an existing overhead bridge or the resurfacing of an existing at-grade crossing. The agreements with railroads are sent to the RE’s office only if the railroad is required to [[#643.4.2.4 Adjustment of Railroad Facilities|adjust their facilities]]. Railroad agreements for highway construction projects are always actual cost agreements. | |||
===643.4.1.2 Contract Job Special Provisions Detailing Railroad Requirements=== | |||
A highway construction project that includes work on or over railroad right of way is one of the few occasions where MoDOT’s contractor is working on property not controlled by the Commission. Railroads have the authority to operate trains on their tracks and to maintain a safe environment throughout the construction of any highway project. Contractors and inspectors are required to obey the railroad’s safety procedures and policies as described in the railroad Job Special Provision (JSP). To establish good lines of communication, it is recommended the RE’s office invite the railroad’s representatives listed in the JSP to the preconstruction meetings or set up a separate meeting between the contractor and the railroad. All contracts for construction projects with railroad involvement contain a section in the JSP’s that details the authority of the railroads. This JSP specifies the conditions placed upon the department and our contractor when working on and over railroad right of way (ROW). The railroad JSP defines the requirements for locating utilities on railroad right of way, for railroad flaggers, for contractor’s insurance coverage requirements, for safety training and other safety related precautions and conditions, and the authority of the railroad to review and approve shoring plans and demolition plans. For example the contractor’s insurance policies must be approved by the railroad and arrangements for the flagger must be established before any work can be done on or over the railroad’s ROW. | |||
===643.4.1. | ===643.4.1.3 Highway-Railroad Crossing Data=== | ||
Once a project with railroad impacts is added to the Statewide Transportation Improvement Plans (STIP), Form D-20, Highway-Railroad Crossing Data Sheet must be completed and submitted to MO-RR. This form includes information such as railroad ownership, type of crossing, and expected railroad impacts. | |||
===643.4.1.4 Preliminary Roadway Plans=== | |||
{|style="padding: 0.3em; margin-right:7px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#ffddcc" width="210px" align="left" | |||
===643.4.1 | |||
{|style="padding: 0.3em; margin- | |||
|- | |- | ||
| | |'''Economic, Freight, Railways''' | ||
|- | |- | ||
| | |[https://spexternal.modot.mo.gov/sites/cm/CORDT/RI08022_Impacts.pdf Summary 2008] | ||
|- | |- | ||
| | |[https://spexternal.modot.mo.gov/sites/cm/CORDT/RI08022_Siding.pdf Summary 2008] | ||
|- | |- | ||
| | |'''Public Policy Impact on Rail Development''' | ||
|- | |- | ||
| | |[https://spexternal.modot.mo.gov/sites/cm/CORDT/or10010.pdf Report 2009] | ||
|- | |- | ||
|'''See also:''' [https://www.modot.org/research-publications Research Publications] | |||
|''' | |||
|} | |} | ||
Electronic Plans for any portion of the preliminary roadway plans affecting a railroad including title sheet, plan-profile sheet, cross section sheets, typical sections, and any special sheets are submitted to MO-RR. | |||
Electronic plans and the [https://epg.modot.org/files/f/f7/643.4_Highway_-Railroad_Crossing_Data_%28M-D-20%29.doc Form D-20], Highway-Railroad Crossing Data, must be submitted to MO-RR at least fourteen months prior to the scheduled bid opening date for projects which require major involvement with railroads, such as modification or construction of grade separation structures. Projects with minor railroad involvement, such as rehabilitation or painting of bridges over railroads and resurfacing of approaches to at-grade crossings, require less time for negotiation. Plans and D-20 for these projects are to be submitted six months before the date of the scheduled bid opening. | |||
A review of the number and condition of railroad crossing signs ("crossbucks"), whether they are reflectorized, the condition of the track crossing material and the location and condition of any flashing light signals or gates in relation to the new centerline of roadway will also be made. Form D-20 is used to record these field conditions. This form is to be emailed to MO as soon as the proposed improvement is added to the STIP. | |||
MO-RR will provide this information to the railroad on all projects affecting railroad operating right of way or facilities. If more than one railroad company is involved, the right of way and facilities of each company are to be identified separately. Highway construction plans will show: | |||
:1) All existing railroad facilities within 500 ft. of the crossing, such as switch points, signals, drainage structures, right of way lines, pole lines, restrictions to sight distance, intersection of centerlines equated to railroad stationing (or mile post) and highway stationing, angle of intersection and a land tie to the nearest corner, as well as adjustments that are required. | |||
:2) Highlighting these features in yellow on the plans emphasizes all notes pertinent to work on railroad property, especially those on the proposed handling of drainage. | |||
:3) Railroad right of way lines and the excavation limits on railroad property are outlined in red on the cross section sheets. | |||
:4) Culvert sections are to be furnished at this time for any culverts proposed on railroad right of way. | |||
:5) When roadway excavation must be hauled across a railroad track, the district is to furnish the location and width of the required crossing and the quantity of material to be hauled. In all cases, existing public crossings should be used for this purpose, if at all possible. | |||
[[Image:643.4 Photo1 Flashing Light Signal.jpg|right|400px]] | |||
===643.4.1.5 Grade Separation Structures / Closing of Existing Crossings=== | |||
The design of railroad-highway grade separations is coordinated with Bridge and district Design. [[:Category:747_Bridge_Reports_and_Layouts|EPG 747 Bridge Reports and Layouts]] provides information for creating a grade separation report. | |||
= | A minimum lateral clearance and vertical clearance from the railroad track to the structure is required. (For additional information see [https://epg.modot.org/index.php?title=Category:760_General_Construction_Inspection_for_Structures#760.4.4_Railroad_Vertical_and_Horizontal_Clearances EPG 760.4.4 Railroads Vertical and Horizontal Clearances].) The right angle section must extend entirely across the railroad's right of way. | ||
At an early stage in the design process, the district will coordinate efforts with MO-RR to explore the feasibility of closing adjacent at-grade crossings that may or may not be located on the state highway system. Should this be the case, the closing of the other crossings will be a part of the grade separation project. | |||
[http://www.up.com/real_estate/roadxing/industry/index.htm BNSF Railway-Union Pacific Railroad Guidelines for Railroad Grade Separation Projects] provides specific guidelines as required by these railroads when constructing over or under railroad property. | |||
[ | |||
===643.4.1.6 Property Rights from Railroads=== | |||
Acquisitions of railroad right of way is a difficult and time-consuming process. Central Office Right of Way (COROW) and MO-RR are responsible for all acquisitions with railroads regardless of whether they are operating, non-operating, or abandoned railroad right of way. The COROW and District Right of Way Managers will handle all acquisitions with the affected railroad entity. Acquisitions from railroads should adhere to the procedures established in [https://epg.modot.org/index.php?title=236.7_Negotiation#236.7.5_Railroad.2C_State_and_Federal_Acquisitions EPG 236.7.5 Railroad, State and Federal Acquisitions]. | |||
Property rights granted by a railroad may be defined and described using one or more document types. Temporary and permanent easements are used where construction and maintenance of highway facilities encroach on operating right of way and may be included in one document. A Warranty Deed (Form 4-7.1A (CCO RW3)), a Quit Claim Deed (Form 4-7.2 (CCO RW2)), or an Easement for Highway Purposes (Form 4-7.5 (CCO RW23)) is desirable where permanent rights are sought on railroad right of way. Coordination with MO-RR and Central Office Right of Way is important when determining the document form due to the fact that all railroads utilize their own Public Projects Manual for details associated with acquisitions. | |||
The district right of way Manager at the request of COROW will prepare the negotiation packet which contains the conveyance documents using a metes and bounds legal description. The District Right of Way staff will prepare an appraisal for each parcel in accordance with standard procedures discussed in [[236.6 Appraisal and Appraisal Review|EPG 236.6 Appraisal and Appraisal Review]]. After the appraisal is complete, the district right of way Manager will provide COROW with the appraisal, railroad’s tract map, roadway plan sheets, conveyance documents, a Written Notice of Intended Acquisition Letter and an undated Written Offer Letter that reflects the approved just compensation. It is likely that an administrative settlement will be necessary to cover the railroad’s processing fee. | |||
In the event when highway right of way runs parallel with abutting railroad right of way and limited access rights are being acquired from the railroad, an electronic set of right of way plans must be sent as soon as available to MO-RR. MO-RR will provide the plans to the railroad to determine if access points need to be reserved for the railroad's use along with the consideration of potentially closing the public/private grade crossings. Quit claim deeds are used to acquire access rights when other easement rights are not involved. | |||
The brief description for railroad easements is referenced to a land tie shown on the railroad's track map. (Example: reference the land tie, provide the distance along the section or quarter section line to the centerline of the railroad right of way, tied to the railroads equation station; refer to track map). A metes and bounds description completed by a Professional Land Surveyor describing the easement and included as Exhibit A to the conveyance document must be provided to Right of Way Manager or COROW. | |||
One copy of the railroad's track map, electronic copies of the roadway plan sheet with the parcels highlighted, and electronic copies of the property document form are submitted by District Right of Way Manager to COROW negotiations with the railroad entity. | |||
===643.4.1.7 Railroad Operating Right of Way=== | |||
Railroads usually consider a 100 ft. width of right of way centered about their main track centerline as the minimum on which they can effectively operate. Any encroachment within this limit, even if it is only for ditch cleanout or erosion control, is not welcomed by the railroad and therefore is to be avoided. When encroachment on railroad operating property is absolutely necessary, the roadway plans and other information noted above, including cross sections sheets showing the work on railroad operating right of way throughout the encroachment, are submitted to MO-RR. | |||
===643.4. | ===643.4.1.8 Railroad Non-Operating Right of Way=== | ||
Property outside the typical 100 ft. wide corridor is usually considered as non-operating right of way. Abandoned depots, warehouses, and watering ponds are also examples of non-operating right of way. As with all railroad easements, railroads typically grant only quitclaim deeds for acquisition of non-operating right of way. | |||
===643.4. | ===643.4.1.9 Rehabilitation, Resurfacing and Painting of Structures Over, On, or Under Railroads=== | ||
All projects over, on, or under railroad property constructed by MoDOT's contractors require notification of the railroad no matter how minor the work may be. The contractor is almost always required to have railroad protective liability insurance before performing any work involving railroad property even where no trains are currently operated. Rehabilitation of structures such as full-depth repair or removal of railings and curbs will require the contractor to engage railroad personnel (known as “flaggers”) to protect the railroad's property and operation. MO-RR is to be notified of these projects as soon as these projects have been added to the [[121.3 The Statewide Transportation Improvement Program (STIP)|State Transportation Improvement Program (STIP)]]. | |||
===643.4. | ===643.4.1.10 Resurfacing Projects=== | ||
When railroad grade crossings are within the limits of a roadway resurfacing project, MO-RR can request the railroad to make any necessary repairs or replacement of the track crossings, warning devices, and adjustment of high or low tracks to provide for a better grade crossing. | |||
Resurfacing projects will typically mill to match the existing roadway elevation at the railroad crossig. If for some reason this cannot be done, the district will review all railroad crossings within the project limits and determine if a track adjustment is necessary and can be justified. If an adjustment appears beneficial, a profile of top of rail (both rails if the track is on a curve) for 500 ft. in each direction from the crossing will be obtained. This information will be submitted to MO-RR together with a recommended adjustment height. | |||
The district | The district initiates a review of all railroad grade crossings within the limits of or affected by a project by submitting [https://epg.modot.org/files/f/f7/643.4_Highway_-Railroad_Crossing_Data_%28M-D-20%29.doc Form D-20] as soon as a project is added to the STIP. | ||
A review of [[903.20 Signing for Rail and Light Rail Transit Grade Crossings|advance warning signs]] should also be done at the same time to ensure they are correctly placed on either side of the crossing. | |||
Resurfacing projects with paving limits up to the crossing surface or within 25 ft. of the tracks will require a JSP that includes railroad protective liability insurance and flagging. Seal coat projects, with limits stopping 50 ft. before the tracks, may require a No Railroad Involvement JSP. MO-RR will coordinate the necessary provisions with the impacted railroad, as soon as the required information is submitted in the Form D-20. | |||
===643.4.1.11 Railroad Crossing Maintenance Responsibility=== | |||
Unless otherwise agreed to, the railroad company shall maintain the highway surface over the length of the ties at single-track crossings and between tracks where adjacent track centers are less than 15 ft. apart. | |||
[[image:643.4.1.11 2019.jpg|center|850px|thumb|<center>''' Highway/Railroad Crossing<br/>Maintenance Responsibilities at Multiple Track Crossings'''</center>]] | |||
Unless otherwise agreed to, the railroad company shall maintain the highway surface over the length of the ties at single-track crossings and between tracks where adjacent track centers are less than 15 ft. apart. | |||
Unless otherwise agreed to, all railroad crossing warning devices, except the advance pavement marking and the advance warning signs, shall be maintained by the railroad company. | |||
MoDOT shall install and maintain the advance pavement marking and the advance warning signs at railroad crossings on MoDOT roadways. MoDOT will maintain the approaches at single-track crossings on state highways up to the end of the ties or to the edge of the crossing material, and will maintain the pavement between multiple track crossings where adjacent track centers are 15 ft. or more apart. | |||
MoDOT should also monitor the crossing location on MoDOT roadways for any vegetation or other sight distance obstructions that may obscure railroad crossing signals. | MoDOT should also monitor the crossing location on MoDOT roadways for any vegetation or other sight distance obstructions that may obscure railroad crossing signals. | ||
===643.4.1.12 Crossing Surfaces=== | |||
Railroads are responsible for the installation and maintenance of all public railroad-highway grade crossing surfaces. If a district desires to pay for a crossing surface or a portion of a crossing surface, they will work with MO-RR before entering into any oral agreement or arrangement to pay for the crossing, which is strictly voluntary. | |||
Agreements for installation of high type crossing surfaces are prepared by MO-RR and submitted to the railroad for execution. These high type surfaces are composed of rubber or concrete. MO-RR will transmit the agreement to the district for execution by the local agency, if applicable, after execution by the railroad. Once it has been executed by the local agency, MO-RR will notify the railroad to proceed with the installation. District construction personnel will inspect the work. The District Construction and Materials engineer responsible for Construction will notify MO-RR when the installation is completed. | |||
===643.4.1.13 Railroad Grade Crossing Warning Systems=== | |||
The determination of appropriate warning devices at railroad grade crossings is the responsibility of MO-RR with concurrence of the railroad(s) involved. The district initiates a review of all railroad grade crossings within the limits of or affected by a project by submitting [[Media:643.4 Highway -Railroad Crossing Data (M-D-20).doc|Form D-20]] as soon as possible after a project is added to the STIP. | |||
If the district is unsure whether an existing grade crossing warning system is affected by a project (even if the crossing warning system is actually located outside the project limits), they need to contact MO-RR for clarification. | |||
==643.4. | ===643.4.1.14 Railroad Crossing Median Islands=== | ||
<div style="float: right; margin-top: 5px; margin-left: 5px; width:425px; background-color: #f5f5f5; padding: 0.3em; border: 2px solid #cccccc; text-align:left;"> | |||
'''<u><center>Quiet Zone</center></u>''' | |||
* Quiet zones are federally-designated areas at least a half mile in length of railroad tracks in which the locomotive engineer is allowed to not blow the train's horn at public crossings. Development of quiet zones falls to the community requesting the quiet zone, (usually a city) the state agency that regulates crossing safety devices (in Missouri, MoDOT) and the railroad involved. | |||
'''<u><center>Requirements</center></u>''' | |||
*The creation of a new quiet zone requires, at a minimum, that each grade crossing be equipped with medians on both sides of the crossing, flashing lights and gates and "constant warning time" circuitry. Additional safety measures may be required to compensate for the absence of the horn as a warning device in some cases. | |||
'''<u><center>Hours</center></u>''' | |||
*New quiet zones can be in effect 24 hours a day, or only between 10 p.m. and 7 a.m. | |||
'''<u><center>Emergencies</center></u>''' | |||
*Train engineers are still permitted to blow horns in quiet zones in emergency situations where safety devices are not working, or to warn railroad or other workers on or near tracks. | |||
</div> | |||
[[image:643.4.1.14.jpg|left|400px|thumb|'''<center>For roadway approaches with posted speed limits that are 45 MPH or greater, delineators or delineator curb system may be considered to discourage motorists from driving around the gates.</center>''']] | |||
Collisions at railroad crossings equipped with automated warning signals and gates can occur if the vehicle operator drives around the gates while in the lowered position. To help mitigate this, in areas with a Posted Speed Limit of 40 MPH or less, a median island with barrier type (non-mountable) curbs is constructed on the roadway approaches. Typically, the island must be at least 100 ft. long to be effective. (The island is also typically required for the establishment of a "Quiet Zone", see box to the right). In some cases, where access would be severely affected, an island of at least 60 ft. can be considered. A detailed drawing is available for use. If a barrier type (non-mountable) curb on a divisional median island is used, lighting of the island ends is required. | |||
For roadway approaches where the posted speed limit is 45 MPH or greater, delineators or delineator curb system may be considered to discourage motorists from driving around the gates. Delineators or delineator curb system may also be considered at locations with posted speed limits of 40 MPH or less if deemed more feasible than the median island with barrier type (non-mountable) curbs described above. | |||
Maintenance staff should be involved in the development of Quiet Zone details prior to the selection, design and construction of any island or delineation option at the crossing. | |||
</br> | |||
</br> | |||
</br> | |||
===643.4.1.15 Final Plans=== | |||
Electronic copies of the title sheet, plan and profile sheet(s), bridge title sheet (if applicable), and any special sheet(s) showing details of the crossing or of the roadway in the vicinity of the crossing (including any structures) are submitted to MO-RR. | |||
If a crossing on a non-state route is to be closed as part of the project, MO-RR must approve the closure or the local road authority must provide a resolution, ordinance, or official letter supporting the closure to MO-RR which will then approve it. The district will secure this approval. | |||
When the roadway improvement project includes a new grade crossing of the railroad, a [[Media:643.4 Questionaire for New Grade Crossing.doc|questionnaire for a new grade crossing]] is submitted to MO-RR with the roadway plan sheets. If the project includes a [[Media:643.4 Questionnaire for Grade Separation.doc|new, widened or replacement grade separation]] structure a different questionnaire is submitted with the roadway plan sheets. | |||
This information is submitted to MO-RR at least six months prior to the scheduled bid opening date for the project. | |||
4. | ===643.4.1.16 Final Quantities=== | ||
Plans submitted to the Central Office that include any proposed work on railroad operating right of way will contain a breakdown of [http://www.modot.mo.gov/business/contractor_resources/biditemslisting.htm bid item] quantities (using forms DE 301 and 302) which occur within the limits of the railroad right of way. The contractor will use this information to obtain railroad protective liability insurance. | |||
==643.4.2 Construction Inspection Guidelines for Railroads== | |||
[[image:643.4.2.jpg|right|275px]] | |||
There are two basic types of railroad projects that require oversight and inspection by MoDOT construction inspectors: | |||
:* Highway construction projects built by MoDOT contractors over, on, or under railroads. The work on these projects use traditional job numbers (JXXXXX). MoDOT’s Railroad Projects Manager (RPM)is the Central Office contact for any questions concerning this type of railroad work. Refer to [[#643.4.1.1 Highway Construction Projects With Railroad Involvement|EPG 643.4.1.1 Highway Construction Projects With Railroad Involvement]] and [[#643.4.1.2 Contract Job Special Provisions Detailing Railroad Requirements|EPG 643.4.1.2 Contract Job Special Provisions Detailing Railroad Requirements]]. | |||
:* Railroad crossing safety improvement projects built by the railroad or their contractor. Railroad crossing safety improvement projects typically use the following style of job number: RRP-000S(XXX). MoDOT’s Railroad Safety Specialists (RSS) are the Central Office contact for any questions concerning this type of railroad work. | |||
Highway construction projects usually involve state routes only, whereas the railroad crossing safety improvement projects can be located on any public crossing, including but not limited to crossings located on city streets, county roadways or highways. | |||
===643.4.2.1 Railroad Flagging=== | |||
A railroad flagger is a railroad employee designated to communicate with our contractor. A flagger is required whenever the contractor’s work could endanger or interfere with the railroad’s operations such as the movement of trains through the project site. A general rule is a flagger is required whenever the contractor will have workers or equipment within 25 feet of the centerline of an active track. One of the primary duties of the flagger is to advise the contractor when trains are expected so that the contractor can pull back personnel and equipment to secure the construction area for the safe movement of trains. The department’s contractor shall contact the railroad to hire a flagger under the conditions specified in the JSP; however, if the contractor proceeds without a flagger when one is needed, the railroad may choose to station a flagger at the site full time throughout the project duration. Under most circumstances a flagger cannot be hired on an hourly basis. Typically the flagger is hired for a minimum of one eight-hour day. Some railroads require as much as 30 days advance notice to hire a flagger and as much as one week’s notice to discharge a flagger, so the contractor is economically inclined to consolidate all work that requires flagging service. Flagging costs are deducted from the contractor’s progress payments. There is no bid item for flagging service. The contractor’s costs for flagging must be in other bid items. The project office shall review all flagging invoices for accuracy, thus inspectors should keep an independent record of the flagging service provided. | |||
Since flagging costs can quickly become extremely expensive, MoDOT districts are urged to strictly monitor the charges and ask MO-RR for assistance should they appear unreasonable. | |||
===643.4.2.2 Adjustment of Railroad Facilities=== | |||
Railroad facilities may need to be modified or adjusted to clear the construction area. For example overhead communication lines frequently need to be relocated prior to the construction or demolition of a highway bridge over a railroad. Sometimes the railroad tracks need to be moved to make space for a new bridge pier. Railroad employees perform these adjustments at MoDOT expense. Ideally this type of work is performed prior to the start of the project construction. The project office inspects these adjustments and makes recommendation for payment when the railroad invoices are received. | |||
===643.4.2.3 Field Inspection of Railroad Work=== | |||
Inspection of work performed by railroads during highway construction projects is similar to the inspection of work performed by [[643.2 Local Utility Adjustments - Public and Private#643.2.2.6 Field Inspection|utility companies]]. The railroad is responsible for the work that will be reimbursed by MoDOT, but the work is performed on their facilities in accordance with their own standards. The RE’s office or MO-RR staff will keep detailed records of the work performed so the [[643.2 Local Utility Adjustments - Public and Private#643.2.2.8 Maintaining Construction Records|railroad invoices]] can be verified in the following situations. | |||
===643.4.2.4 Railroad Invoices - Highway Construction Projects=== | |||
On MoDOT construction projects in which, for example, a bridge is built over a railroad, MoDOT’s Railroad Projects Manager (RPM) receives the progressive and final invoices from the railroads. The RPM will forward all invoices to the RE. The RE’s office is responsible for reviewing and making recommendation for the payment for all railroad work performed for highway construction projects. Railroads may send progressive invoices for facility adjustments and for flagging services on a monthly basis. The project office shall determine the amount of flagging costs that need to be deducted from the contactor’s payments. The project office should process the invoices within one month of receipt when possible. Progress invoices are handled in the same manner as the [[643.2 Local Utility Adjustments - Public and Private#643.2.2.9.2 Partial Payment Invoices|utility partial payment invoices]]. Therefore, the RE sends progress payment memos directly to the Controller’s Office (copy memo to Division Construction and the RPM (not the DUE)). Final invoices are processed in the same manner as [[643.2 Local Utility Adjustments - Public and Private#643.2.2.9.3 Final Invoice|Utility Final Invoices]]. However, the RE will forward the following items to the Construction Division with a memo: | |||
:* [https://epg.modot.org/forms/CM/C9_Daily_Utility_Report.pdf Daily Utility Reports (C-9)] and the | |||
:* [https://epg.modot.org/forms/CM/C13_Final_Utility_Report.pdf Final Utility Report (C-13)] | |||
The district construction office and the RPM also receive copy of the memo and attachments. If disputes are encountered between the contractor and the railroad representatives that cannot be resolved by the RE, or if questions arise regarding the intention of construction and maintenance agreements or railroad special provisions, the project office can contact the RPM. | |||
==643.4.3 Railroad Crossing Safety Improvements== | |||
MoDOT administers federal funds specifically intended to reduce the hazards of highway/railroad crossings. Typically this involves the installation of active warning devices, such as flashing light signals and gates, at rural crossings on non-state routes. Railroad forces or a construction contractor hired by the railroad usually performs the work. Railroad companies occasionally participate in the cost, but the majority is usually paid using the federal and state funds administered (by the RSS) through the Missouri Highway/Rail Crossing Safety Program. | |||
MO-RR will initiate individual grade crossing improvements not associated with a roadway improvement project by using a priority rating system developed from the data available on the crossing inventory or by using cost share agreements with the railroads, local governments or private agencies. The district, together with the railroad, local officials and MO-RR personnel annually inspect a number of these crossings in the field to determine the appropriate improvement. A diagnostic field review will be conducted with all affected parties to determine the appropriate improvements. | |||
MO-RR prepares all agreements for improvements at railroad crossings after the proposed work has been approved by the FHWA. Crossing improvements on state routes are processed by MO-RR without involving local agencies. | |||
===643.4.3.1 Railroad Crossing Improvement Project Coordination=== | |||
The District Railroad (RR) Contacts are to be notified of rail-highway grade crossing improvement projects as soon as a project is initiated by MO-RR. | |||
MO-RR will coordinate a diagnostic field review at the railroad crossing with the Railroad, District RR Contact(s), Area Engineers and local road authority representatives. At the diagnostic field review, all involved parties shall investigate the crossing and discuss the potential safety improvements. The attending District RR Contact is responsible for signing the diagnostic review documentation as the District representative. | |||
The district is responsible for providing approaching roadway recommendations, signage modifications, etc. | |||
MO-RR distributes all project paperwork to the local road authority, district RR Contact(s) and Railroad, as necessary. | |||
The Supplemental Agreement between MoDOT, the railroad and local road authority is drafted, reviewed, finalized and dispersed for signatures by MO-RR, railroad and local road authority. This agreement details the planned improvements and responsibility of each involved party. | |||
The Administrative Order is drafted and issued by MO-RR, at which time the railroad is typically granted 1 year to construct improvements. Financial Service, district contact and Motor Carriers are advised at this time that the project is scheduled for construction. | |||
===643.4.3.2 Field Inspection of Railroad Work – Crossing Safety Improvements=== | |||
The district will be notified of project involving at-grade crossing improvements. The district should monitor projects on the state system for adequate traffic control. For complex projects, MO-RR will coordinate any additional inspection assistance required from the District Construction office prior to the start of construction. For most routine projects, district inspection will not be required. | |||
===643.4. | ===643.4.3.3 Railroad Invoices for Crossing Safety Improvements - MoDOT and Non-MoDOT Projects=== | ||
The Railroad Safety Section (RSS) receives the progressive and final invoices from the railroads throughout construction of the project. This type of railroad work is progressed and final billed very differently than railroad invoices for highway construction projects. The RSS submits all progress bills directly to the Controllers Office. | |||
After the RSS receives the proper documentation and final invoice, RSS will determine whether to withhold or recommend payment. MO-RR will complete the final inspection. | |||
==643.4.4 Maintenance Activities== | |||
===643.4.4.1 Railroad Crossing Safety=== | |||
Prior to conducting any work over or within 25 horizontal feet of the centerline of an active track, that could interfere with the movement of any train, MoDOT shall contact the railroad company responsible for the track at least 48 hours in advance of performing the work. The railroad company shall be notified of the nature, length and location of the work that is to be performed. For work that will interfere with the movement of any train or pose a safety hazard to the workers within these space limitations on the active track, a railroad company flagger paid for by the department must be present unless the railroad company has indicated that a flagger is not required at the work site during the time the work is to be done. | |||
The [http://sharepoint/systemdelivery/MO/rail/projects/Documents/Rail_Frieight-Track_Managers/rail_freight_track_managers_2015.pdf Statewide Railroad Track Manager Map] should be referenced to determine the railroad company representative responsible for a particular railroad track or crossing, contact the MO Railroad Section at (573) 526-2169. In order to identify the railroad company representative responsible for maintaining a particular railroad track or crossing, department personnel should provide the name of the railroad company and either the crossing number (also called the DOT Number) or the railroad milepost and subdivision identification to the Railroad Section. | |||
MoDOT employees are required to wear [http://sharepoint/safety/csp/SitePages/PPE.aspx personal protective equipment], as described in the department’s Safety Policies, Rules & Regulations Employee Handbook, appropriate for each task when working near or over an active railroad track. | |||
===643.4.4.2 Cooperation with Railroads=== | |||
District personnel should notify MO-RR or the railroad company representative (roadmaster) when a crossing is in need of repair. If it is unclear which railroad company is responsible for a particular crossing, district personnel should contact the Railroad Section for assistance in determining ownership responsibility for the crossing. If the crossing repairs are not made by the railroad company within a reasonable period of time, the district should request assistance from the Railroad Section to set a firm timeline by which the railroad must make the repairs. | |||
MoDOT may furnish asphaltic material for patching crossings when requested by the railroad company. If possible, MoDOT and the railroad company should schedule any needed maintenance to the roadway in the vicinity of the crossing at the same time. | |||
If department personnel are patching the roadway at a multiple track crossing and there are potholes in the roadway surface between the tracks (not rails), department personnel should patch the holes with department forces even if the centerlines of the tracks are less than 15 ft. apart. MoDOT does not assume the responsibility for maintenance of the crossing and under no circumstances are department personnel to replace any portion of a timber or other type of crossing material. MoDOT forces are not to work between the rails, but can furnish asphaltic material to the railroad company for use in this area. | |||
When replacing or making major repairs to a crossing it may be necessary for the railroad company to temporarily close the crossing to both rail and highway traffic. The District Engineer may authorize the highway closure, however, the closure should be held to as short a period of time as possible. If a detour is available the railroad company may set-up the detour around the crossing, however, MoDOT will not be involved in providing the detour nor will the department assume any responsibility for the maintenance of the detour route. MoDOT may furnish (not install) detour signing as well as the warning signs necessary to adequately warn motorists of the closure and detour. The railroad company is responsible for the placement and maintenance of the signing as well as notifying all local officials and local media of the closure. The railroad company shall obtain a permit for the placement of any detour or workzone signs on MHTC Right-of-way. | |||
===643.4.4.3 Roadway Taper at Railroad Crossings=== | |||
A rough riding railroad crossing is sometimes caused by the buildup of the asphalt approach pavement to the crossing. On overlay projects, depth transitions should be constructed approaching the railroad crossing to meet the elevation of the tracks. Modified coldmilling should be used to create a taper of 1” to 100’ (1:1200) and the overlay placed at the intended thickness. As some flexibility exists, the district will need to review the route and any exceptions to determine the appropriate adjustments for each location within the project. | |||
==643.4.5 Traffic Control for Railroad and Light Rail Transit Grade Crossings== | |||
[[ | Refer to [[:Category:913 Traffic Control for Railroad and Light Rail Transit Grade Crossings (MUTCD Part 8)|EPG 913]]. | ||
Latest revision as of 09:19, 26 November 2025

643.4.1 Introduction and Overview for Highway Construction Projects Impacting Railroads
| Freight and Passenger Rail Capacity Analysis |
| Report 2007 |
Railroad projects involve a variety of issues, including crossing signals, stop and yield signs, surfacing, traffic signal preemption and grade separations. Some of these may be funded by the Multimodal Division, by MoDOT districts, by both or by other entities. Projects involving work on or over railroad right of way or involving adjustment of railroad facilities require the timely submittal of plans to the Central Office in order to avoid delays in the monthly bid opening. The district is responsible for providing the necessary plans, typical sections and details to Multimodal Operations - Railroads (MO-RR) where negotiations with railroads are conducted.
643.4.1.1 Highway Construction Projects With Railroad Involvement
Projects that include the construction or modification of a highway bridge over a railroad are called overhead grade separation projects. Projects that include the construction of a bridge that takes the tracks over the highway are called underpass projects because the road passes under the railroad. Parallel projects include the construction of roadways, slopes and ditches parallel to and on the railroad right of way, but not across the track. Other projects with railroad involvement include the construction of a new railroad crossing, the widening of an existing crossing, or the resurfacing of highways approaches to a crossing. These are called at-grade projects. Agreements with railroads are secured whenever MoDOT constructs a roadway over, under or across a railroad’s track. A new agreement is also secured whenever a bridge is replaced or widened over a railroad track or whenever an at-grade crossing is widened or relocated. However, a new agreement is not needed for the rehabilitation or the maintenance of an existing overhead bridge or the resurfacing of an existing at-grade crossing. The agreements with railroads are sent to the RE’s office only if the railroad is required to adjust their facilities. Railroad agreements for highway construction projects are always actual cost agreements.
643.4.1.2 Contract Job Special Provisions Detailing Railroad Requirements
A highway construction project that includes work on or over railroad right of way is one of the few occasions where MoDOT’s contractor is working on property not controlled by the Commission. Railroads have the authority to operate trains on their tracks and to maintain a safe environment throughout the construction of any highway project. Contractors and inspectors are required to obey the railroad’s safety procedures and policies as described in the railroad Job Special Provision (JSP). To establish good lines of communication, it is recommended the RE’s office invite the railroad’s representatives listed in the JSP to the preconstruction meetings or set up a separate meeting between the contractor and the railroad. All contracts for construction projects with railroad involvement contain a section in the JSP’s that details the authority of the railroads. This JSP specifies the conditions placed upon the department and our contractor when working on and over railroad right of way (ROW). The railroad JSP defines the requirements for locating utilities on railroad right of way, for railroad flaggers, for contractor’s insurance coverage requirements, for safety training and other safety related precautions and conditions, and the authority of the railroad to review and approve shoring plans and demolition plans. For example the contractor’s insurance policies must be approved by the railroad and arrangements for the flagger must be established before any work can be done on or over the railroad’s ROW.
643.4.1.3 Highway-Railroad Crossing Data
Once a project with railroad impacts is added to the Statewide Transportation Improvement Plans (STIP), Form D-20, Highway-Railroad Crossing Data Sheet must be completed and submitted to MO-RR. This form includes information such as railroad ownership, type of crossing, and expected railroad impacts.
643.4.1.4 Preliminary Roadway Plans
| Economic, Freight, Railways |
| Summary 2008 |
| Summary 2008 |
| Public Policy Impact on Rail Development |
| Report 2009 |
| See also: Research Publications |
Electronic Plans for any portion of the preliminary roadway plans affecting a railroad including title sheet, plan-profile sheet, cross section sheets, typical sections, and any special sheets are submitted to MO-RR.
Electronic plans and the Form D-20, Highway-Railroad Crossing Data, must be submitted to MO-RR at least fourteen months prior to the scheduled bid opening date for projects which require major involvement with railroads, such as modification or construction of grade separation structures. Projects with minor railroad involvement, such as rehabilitation or painting of bridges over railroads and resurfacing of approaches to at-grade crossings, require less time for negotiation. Plans and D-20 for these projects are to be submitted six months before the date of the scheduled bid opening.
A review of the number and condition of railroad crossing signs ("crossbucks"), whether they are reflectorized, the condition of the track crossing material and the location and condition of any flashing light signals or gates in relation to the new centerline of roadway will also be made. Form D-20 is used to record these field conditions. This form is to be emailed to MO as soon as the proposed improvement is added to the STIP.
MO-RR will provide this information to the railroad on all projects affecting railroad operating right of way or facilities. If more than one railroad company is involved, the right of way and facilities of each company are to be identified separately. Highway construction plans will show:
- 1) All existing railroad facilities within 500 ft. of the crossing, such as switch points, signals, drainage structures, right of way lines, pole lines, restrictions to sight distance, intersection of centerlines equated to railroad stationing (or mile post) and highway stationing, angle of intersection and a land tie to the nearest corner, as well as adjustments that are required.
- 2) Highlighting these features in yellow on the plans emphasizes all notes pertinent to work on railroad property, especially those on the proposed handling of drainage.
- 3) Railroad right of way lines and the excavation limits on railroad property are outlined in red on the cross section sheets.
- 4) Culvert sections are to be furnished at this time for any culverts proposed on railroad right of way.
- 5) When roadway excavation must be hauled across a railroad track, the district is to furnish the location and width of the required crossing and the quantity of material to be hauled. In all cases, existing public crossings should be used for this purpose, if at all possible.

643.4.1.5 Grade Separation Structures / Closing of Existing Crossings
The design of railroad-highway grade separations is coordinated with Bridge and district Design. EPG 747 Bridge Reports and Layouts provides information for creating a grade separation report.
A minimum lateral clearance and vertical clearance from the railroad track to the structure is required. (For additional information see EPG 760.4.4 Railroads Vertical and Horizontal Clearances.) The right angle section must extend entirely across the railroad's right of way.
At an early stage in the design process, the district will coordinate efforts with MO-RR to explore the feasibility of closing adjacent at-grade crossings that may or may not be located on the state highway system. Should this be the case, the closing of the other crossings will be a part of the grade separation project.
BNSF Railway-Union Pacific Railroad Guidelines for Railroad Grade Separation Projects provides specific guidelines as required by these railroads when constructing over or under railroad property.
643.4.1.6 Property Rights from Railroads
Acquisitions of railroad right of way is a difficult and time-consuming process. Central Office Right of Way (COROW) and MO-RR are responsible for all acquisitions with railroads regardless of whether they are operating, non-operating, or abandoned railroad right of way. The COROW and District Right of Way Managers will handle all acquisitions with the affected railroad entity. Acquisitions from railroads should adhere to the procedures established in EPG 236.7.5 Railroad, State and Federal Acquisitions.
Property rights granted by a railroad may be defined and described using one or more document types. Temporary and permanent easements are used where construction and maintenance of highway facilities encroach on operating right of way and may be included in one document. A Warranty Deed (Form 4-7.1A (CCO RW3)), a Quit Claim Deed (Form 4-7.2 (CCO RW2)), or an Easement for Highway Purposes (Form 4-7.5 (CCO RW23)) is desirable where permanent rights are sought on railroad right of way. Coordination with MO-RR and Central Office Right of Way is important when determining the document form due to the fact that all railroads utilize their own Public Projects Manual for details associated with acquisitions.
The district right of way Manager at the request of COROW will prepare the negotiation packet which contains the conveyance documents using a metes and bounds legal description. The District Right of Way staff will prepare an appraisal for each parcel in accordance with standard procedures discussed in EPG 236.6 Appraisal and Appraisal Review. After the appraisal is complete, the district right of way Manager will provide COROW with the appraisal, railroad’s tract map, roadway plan sheets, conveyance documents, a Written Notice of Intended Acquisition Letter and an undated Written Offer Letter that reflects the approved just compensation. It is likely that an administrative settlement will be necessary to cover the railroad’s processing fee.
In the event when highway right of way runs parallel with abutting railroad right of way and limited access rights are being acquired from the railroad, an electronic set of right of way plans must be sent as soon as available to MO-RR. MO-RR will provide the plans to the railroad to determine if access points need to be reserved for the railroad's use along with the consideration of potentially closing the public/private grade crossings. Quit claim deeds are used to acquire access rights when other easement rights are not involved.
The brief description for railroad easements is referenced to a land tie shown on the railroad's track map. (Example: reference the land tie, provide the distance along the section or quarter section line to the centerline of the railroad right of way, tied to the railroads equation station; refer to track map). A metes and bounds description completed by a Professional Land Surveyor describing the easement and included as Exhibit A to the conveyance document must be provided to Right of Way Manager or COROW.
One copy of the railroad's track map, electronic copies of the roadway plan sheet with the parcels highlighted, and electronic copies of the property document form are submitted by District Right of Way Manager to COROW negotiations with the railroad entity.
643.4.1.7 Railroad Operating Right of Way
Railroads usually consider a 100 ft. width of right of way centered about their main track centerline as the minimum on which they can effectively operate. Any encroachment within this limit, even if it is only for ditch cleanout or erosion control, is not welcomed by the railroad and therefore is to be avoided. When encroachment on railroad operating property is absolutely necessary, the roadway plans and other information noted above, including cross sections sheets showing the work on railroad operating right of way throughout the encroachment, are submitted to MO-RR.
643.4.1.8 Railroad Non-Operating Right of Way
Property outside the typical 100 ft. wide corridor is usually considered as non-operating right of way. Abandoned depots, warehouses, and watering ponds are also examples of non-operating right of way. As with all railroad easements, railroads typically grant only quitclaim deeds for acquisition of non-operating right of way.
643.4.1.9 Rehabilitation, Resurfacing and Painting of Structures Over, On, or Under Railroads
All projects over, on, or under railroad property constructed by MoDOT's contractors require notification of the railroad no matter how minor the work may be. The contractor is almost always required to have railroad protective liability insurance before performing any work involving railroad property even where no trains are currently operated. Rehabilitation of structures such as full-depth repair or removal of railings and curbs will require the contractor to engage railroad personnel (known as “flaggers”) to protect the railroad's property and operation. MO-RR is to be notified of these projects as soon as these projects have been added to the State Transportation Improvement Program (STIP).
643.4.1.10 Resurfacing Projects
When railroad grade crossings are within the limits of a roadway resurfacing project, MO-RR can request the railroad to make any necessary repairs or replacement of the track crossings, warning devices, and adjustment of high or low tracks to provide for a better grade crossing.
Resurfacing projects will typically mill to match the existing roadway elevation at the railroad crossig. If for some reason this cannot be done, the district will review all railroad crossings within the project limits and determine if a track adjustment is necessary and can be justified. If an adjustment appears beneficial, a profile of top of rail (both rails if the track is on a curve) for 500 ft. in each direction from the crossing will be obtained. This information will be submitted to MO-RR together with a recommended adjustment height.
The district initiates a review of all railroad grade crossings within the limits of or affected by a project by submitting Form D-20 as soon as a project is added to the STIP.
A review of advance warning signs should also be done at the same time to ensure they are correctly placed on either side of the crossing.
Resurfacing projects with paving limits up to the crossing surface or within 25 ft. of the tracks will require a JSP that includes railroad protective liability insurance and flagging. Seal coat projects, with limits stopping 50 ft. before the tracks, may require a No Railroad Involvement JSP. MO-RR will coordinate the necessary provisions with the impacted railroad, as soon as the required information is submitted in the Form D-20.
643.4.1.11 Railroad Crossing Maintenance Responsibility
Unless otherwise agreed to, the railroad company shall maintain the highway surface over the length of the ties at single-track crossings and between tracks where adjacent track centers are less than 15 ft. apart.

Maintenance Responsibilities at Multiple Track Crossings
Unless otherwise agreed to, all railroad crossing warning devices, except the advance pavement marking and the advance warning signs, shall be maintained by the railroad company.
MoDOT shall install and maintain the advance pavement marking and the advance warning signs at railroad crossings on MoDOT roadways. MoDOT will maintain the approaches at single-track crossings on state highways up to the end of the ties or to the edge of the crossing material, and will maintain the pavement between multiple track crossings where adjacent track centers are 15 ft. or more apart.
MoDOT should also monitor the crossing location on MoDOT roadways for any vegetation or other sight distance obstructions that may obscure railroad crossing signals.
643.4.1.12 Crossing Surfaces
Railroads are responsible for the installation and maintenance of all public railroad-highway grade crossing surfaces. If a district desires to pay for a crossing surface or a portion of a crossing surface, they will work with MO-RR before entering into any oral agreement or arrangement to pay for the crossing, which is strictly voluntary.
Agreements for installation of high type crossing surfaces are prepared by MO-RR and submitted to the railroad for execution. These high type surfaces are composed of rubber or concrete. MO-RR will transmit the agreement to the district for execution by the local agency, if applicable, after execution by the railroad. Once it has been executed by the local agency, MO-RR will notify the railroad to proceed with the installation. District construction personnel will inspect the work. The District Construction and Materials engineer responsible for Construction will notify MO-RR when the installation is completed.
643.4.1.13 Railroad Grade Crossing Warning Systems
The determination of appropriate warning devices at railroad grade crossings is the responsibility of MO-RR with concurrence of the railroad(s) involved. The district initiates a review of all railroad grade crossings within the limits of or affected by a project by submitting Form D-20 as soon as possible after a project is added to the STIP.
If the district is unsure whether an existing grade crossing warning system is affected by a project (even if the crossing warning system is actually located outside the project limits), they need to contact MO-RR for clarification.
643.4.1.14 Railroad Crossing Median Islands
- Quiet zones are federally-designated areas at least a half mile in length of railroad tracks in which the locomotive engineer is allowed to not blow the train's horn at public crossings. Development of quiet zones falls to the community requesting the quiet zone, (usually a city) the state agency that regulates crossing safety devices (in Missouri, MoDOT) and the railroad involved.
- The creation of a new quiet zone requires, at a minimum, that each grade crossing be equipped with medians on both sides of the crossing, flashing lights and gates and "constant warning time" circuitry. Additional safety measures may be required to compensate for the absence of the horn as a warning device in some cases.
- New quiet zones can be in effect 24 hours a day, or only between 10 p.m. and 7 a.m.
- Train engineers are still permitted to blow horns in quiet zones in emergency situations where safety devices are not working, or to warn railroad or other workers on or near tracks.

Collisions at railroad crossings equipped with automated warning signals and gates can occur if the vehicle operator drives around the gates while in the lowered position. To help mitigate this, in areas with a Posted Speed Limit of 40 MPH or less, a median island with barrier type (non-mountable) curbs is constructed on the roadway approaches. Typically, the island must be at least 100 ft. long to be effective. (The island is also typically required for the establishment of a "Quiet Zone", see box to the right). In some cases, where access would be severely affected, an island of at least 60 ft. can be considered. A detailed drawing is available for use. If a barrier type (non-mountable) curb on a divisional median island is used, lighting of the island ends is required.
For roadway approaches where the posted speed limit is 45 MPH or greater, delineators or delineator curb system may be considered to discourage motorists from driving around the gates. Delineators or delineator curb system may also be considered at locations with posted speed limits of 40 MPH or less if deemed more feasible than the median island with barrier type (non-mountable) curbs described above.
Maintenance staff should be involved in the development of Quiet Zone details prior to the selection, design and construction of any island or delineation option at the crossing.
643.4.1.15 Final Plans
Electronic copies of the title sheet, plan and profile sheet(s), bridge title sheet (if applicable), and any special sheet(s) showing details of the crossing or of the roadway in the vicinity of the crossing (including any structures) are submitted to MO-RR.
If a crossing on a non-state route is to be closed as part of the project, MO-RR must approve the closure or the local road authority must provide a resolution, ordinance, or official letter supporting the closure to MO-RR which will then approve it. The district will secure this approval.
When the roadway improvement project includes a new grade crossing of the railroad, a questionnaire for a new grade crossing is submitted to MO-RR with the roadway plan sheets. If the project includes a new, widened or replacement grade separation structure a different questionnaire is submitted with the roadway plan sheets.
This information is submitted to MO-RR at least six months prior to the scheduled bid opening date for the project.
643.4.1.16 Final Quantities
Plans submitted to the Central Office that include any proposed work on railroad operating right of way will contain a breakdown of bid item quantities (using forms DE 301 and 302) which occur within the limits of the railroad right of way. The contractor will use this information to obtain railroad protective liability insurance.
643.4.2 Construction Inspection Guidelines for Railroads

There are two basic types of railroad projects that require oversight and inspection by MoDOT construction inspectors:
- Highway construction projects built by MoDOT contractors over, on, or under railroads. The work on these projects use traditional job numbers (JXXXXX). MoDOT’s Railroad Projects Manager (RPM)is the Central Office contact for any questions concerning this type of railroad work. Refer to EPG 643.4.1.1 Highway Construction Projects With Railroad Involvement and EPG 643.4.1.2 Contract Job Special Provisions Detailing Railroad Requirements.
- Railroad crossing safety improvement projects built by the railroad or their contractor. Railroad crossing safety improvement projects typically use the following style of job number: RRP-000S(XXX). MoDOT’s Railroad Safety Specialists (RSS) are the Central Office contact for any questions concerning this type of railroad work.
Highway construction projects usually involve state routes only, whereas the railroad crossing safety improvement projects can be located on any public crossing, including but not limited to crossings located on city streets, county roadways or highways.
643.4.2.1 Railroad Flagging
A railroad flagger is a railroad employee designated to communicate with our contractor. A flagger is required whenever the contractor’s work could endanger or interfere with the railroad’s operations such as the movement of trains through the project site. A general rule is a flagger is required whenever the contractor will have workers or equipment within 25 feet of the centerline of an active track. One of the primary duties of the flagger is to advise the contractor when trains are expected so that the contractor can pull back personnel and equipment to secure the construction area for the safe movement of trains. The department’s contractor shall contact the railroad to hire a flagger under the conditions specified in the JSP; however, if the contractor proceeds without a flagger when one is needed, the railroad may choose to station a flagger at the site full time throughout the project duration. Under most circumstances a flagger cannot be hired on an hourly basis. Typically the flagger is hired for a minimum of one eight-hour day. Some railroads require as much as 30 days advance notice to hire a flagger and as much as one week’s notice to discharge a flagger, so the contractor is economically inclined to consolidate all work that requires flagging service. Flagging costs are deducted from the contractor’s progress payments. There is no bid item for flagging service. The contractor’s costs for flagging must be in other bid items. The project office shall review all flagging invoices for accuracy, thus inspectors should keep an independent record of the flagging service provided.
Since flagging costs can quickly become extremely expensive, MoDOT districts are urged to strictly monitor the charges and ask MO-RR for assistance should they appear unreasonable.
643.4.2.2 Adjustment of Railroad Facilities
Railroad facilities may need to be modified or adjusted to clear the construction area. For example overhead communication lines frequently need to be relocated prior to the construction or demolition of a highway bridge over a railroad. Sometimes the railroad tracks need to be moved to make space for a new bridge pier. Railroad employees perform these adjustments at MoDOT expense. Ideally this type of work is performed prior to the start of the project construction. The project office inspects these adjustments and makes recommendation for payment when the railroad invoices are received.
643.4.2.3 Field Inspection of Railroad Work
Inspection of work performed by railroads during highway construction projects is similar to the inspection of work performed by utility companies. The railroad is responsible for the work that will be reimbursed by MoDOT, but the work is performed on their facilities in accordance with their own standards. The RE’s office or MO-RR staff will keep detailed records of the work performed so the railroad invoices can be verified in the following situations.
643.4.2.4 Railroad Invoices - Highway Construction Projects
On MoDOT construction projects in which, for example, a bridge is built over a railroad, MoDOT’s Railroad Projects Manager (RPM) receives the progressive and final invoices from the railroads. The RPM will forward all invoices to the RE. The RE’s office is responsible for reviewing and making recommendation for the payment for all railroad work performed for highway construction projects. Railroads may send progressive invoices for facility adjustments and for flagging services on a monthly basis. The project office shall determine the amount of flagging costs that need to be deducted from the contactor’s payments. The project office should process the invoices within one month of receipt when possible. Progress invoices are handled in the same manner as the utility partial payment invoices. Therefore, the RE sends progress payment memos directly to the Controller’s Office (copy memo to Division Construction and the RPM (not the DUE)). Final invoices are processed in the same manner as Utility Final Invoices. However, the RE will forward the following items to the Construction Division with a memo:
The district construction office and the RPM also receive copy of the memo and attachments. If disputes are encountered between the contractor and the railroad representatives that cannot be resolved by the RE, or if questions arise regarding the intention of construction and maintenance agreements or railroad special provisions, the project office can contact the RPM.
643.4.3 Railroad Crossing Safety Improvements
MoDOT administers federal funds specifically intended to reduce the hazards of highway/railroad crossings. Typically this involves the installation of active warning devices, such as flashing light signals and gates, at rural crossings on non-state routes. Railroad forces or a construction contractor hired by the railroad usually performs the work. Railroad companies occasionally participate in the cost, but the majority is usually paid using the federal and state funds administered (by the RSS) through the Missouri Highway/Rail Crossing Safety Program.
MO-RR will initiate individual grade crossing improvements not associated with a roadway improvement project by using a priority rating system developed from the data available on the crossing inventory or by using cost share agreements with the railroads, local governments or private agencies. The district, together with the railroad, local officials and MO-RR personnel annually inspect a number of these crossings in the field to determine the appropriate improvement. A diagnostic field review will be conducted with all affected parties to determine the appropriate improvements.
MO-RR prepares all agreements for improvements at railroad crossings after the proposed work has been approved by the FHWA. Crossing improvements on state routes are processed by MO-RR without involving local agencies.
643.4.3.1 Railroad Crossing Improvement Project Coordination
The District Railroad (RR) Contacts are to be notified of rail-highway grade crossing improvement projects as soon as a project is initiated by MO-RR.
MO-RR will coordinate a diagnostic field review at the railroad crossing with the Railroad, District RR Contact(s), Area Engineers and local road authority representatives. At the diagnostic field review, all involved parties shall investigate the crossing and discuss the potential safety improvements. The attending District RR Contact is responsible for signing the diagnostic review documentation as the District representative.
The district is responsible for providing approaching roadway recommendations, signage modifications, etc.
MO-RR distributes all project paperwork to the local road authority, district RR Contact(s) and Railroad, as necessary.
The Supplemental Agreement between MoDOT, the railroad and local road authority is drafted, reviewed, finalized and dispersed for signatures by MO-RR, railroad and local road authority. This agreement details the planned improvements and responsibility of each involved party.
The Administrative Order is drafted and issued by MO-RR, at which time the railroad is typically granted 1 year to construct improvements. Financial Service, district contact and Motor Carriers are advised at this time that the project is scheduled for construction.
643.4.3.2 Field Inspection of Railroad Work – Crossing Safety Improvements
The district will be notified of project involving at-grade crossing improvements. The district should monitor projects on the state system for adequate traffic control. For complex projects, MO-RR will coordinate any additional inspection assistance required from the District Construction office prior to the start of construction. For most routine projects, district inspection will not be required.
643.4.3.3 Railroad Invoices for Crossing Safety Improvements - MoDOT and Non-MoDOT Projects
The Railroad Safety Section (RSS) receives the progressive and final invoices from the railroads throughout construction of the project. This type of railroad work is progressed and final billed very differently than railroad invoices for highway construction projects. The RSS submits all progress bills directly to the Controllers Office.
After the RSS receives the proper documentation and final invoice, RSS will determine whether to withhold or recommend payment. MO-RR will complete the final inspection.
643.4.4 Maintenance Activities
643.4.4.1 Railroad Crossing Safety
Prior to conducting any work over or within 25 horizontal feet of the centerline of an active track, that could interfere with the movement of any train, MoDOT shall contact the railroad company responsible for the track at least 48 hours in advance of performing the work. The railroad company shall be notified of the nature, length and location of the work that is to be performed. For work that will interfere with the movement of any train or pose a safety hazard to the workers within these space limitations on the active track, a railroad company flagger paid for by the department must be present unless the railroad company has indicated that a flagger is not required at the work site during the time the work is to be done.
The Statewide Railroad Track Manager Map should be referenced to determine the railroad company representative responsible for a particular railroad track or crossing, contact the MO Railroad Section at (573) 526-2169. In order to identify the railroad company representative responsible for maintaining a particular railroad track or crossing, department personnel should provide the name of the railroad company and either the crossing number (also called the DOT Number) or the railroad milepost and subdivision identification to the Railroad Section.
MoDOT employees are required to wear personal protective equipment, as described in the department’s Safety Policies, Rules & Regulations Employee Handbook, appropriate for each task when working near or over an active railroad track.
643.4.4.2 Cooperation with Railroads
District personnel should notify MO-RR or the railroad company representative (roadmaster) when a crossing is in need of repair. If it is unclear which railroad company is responsible for a particular crossing, district personnel should contact the Railroad Section for assistance in determining ownership responsibility for the crossing. If the crossing repairs are not made by the railroad company within a reasonable period of time, the district should request assistance from the Railroad Section to set a firm timeline by which the railroad must make the repairs.
MoDOT may furnish asphaltic material for patching crossings when requested by the railroad company. If possible, MoDOT and the railroad company should schedule any needed maintenance to the roadway in the vicinity of the crossing at the same time.
If department personnel are patching the roadway at a multiple track crossing and there are potholes in the roadway surface between the tracks (not rails), department personnel should patch the holes with department forces even if the centerlines of the tracks are less than 15 ft. apart. MoDOT does not assume the responsibility for maintenance of the crossing and under no circumstances are department personnel to replace any portion of a timber or other type of crossing material. MoDOT forces are not to work between the rails, but can furnish asphaltic material to the railroad company for use in this area.
When replacing or making major repairs to a crossing it may be necessary for the railroad company to temporarily close the crossing to both rail and highway traffic. The District Engineer may authorize the highway closure, however, the closure should be held to as short a period of time as possible. If a detour is available the railroad company may set-up the detour around the crossing, however, MoDOT will not be involved in providing the detour nor will the department assume any responsibility for the maintenance of the detour route. MoDOT may furnish (not install) detour signing as well as the warning signs necessary to adequately warn motorists of the closure and detour. The railroad company is responsible for the placement and maintenance of the signing as well as notifying all local officials and local media of the closure. The railroad company shall obtain a permit for the placement of any detour or workzone signs on MHTC Right-of-way.
643.4.4.3 Roadway Taper at Railroad Crossings
A rough riding railroad crossing is sometimes caused by the buildup of the asphalt approach pavement to the crossing. On overlay projects, depth transitions should be constructed approaching the railroad crossing to meet the elevation of the tracks. Modified coldmilling should be used to create a taper of 1” to 100’ (1:1200) and the overlay placed at the intended thickness. As some flexibility exists, the district will need to review the route and any exceptions to determine the appropriate adjustments for each location within the project.
643.4.5 Traffic Control for Railroad and Light Rail Transit Grade Crossings
Refer to EPG 913.