A [[#748.9.6 Acronyms|list of acronyms]] is provided at the end of this article.
 
 
[[Image:748.9 Clarksville Sandbagging.jpg|right|465px]]
 
[[Image:748.9 Clarksville Sandbagging.jpg|right|465px]]
  
==748.9.1 Floodplain Development Permit==
+
Acting as the Federal Highway Administration’s (FHWA’s) agent, MoDOT must evaluate every project to determine whether it could have a negative impact on the base (1% or 100-year) floodplain and/or regulatory floodway. 23 CFR 650A requires that hydraulic conditions created by a project be consistent with Federal Emergency Management Agency (FEMA) standards established for the NFIP.
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="160px" align="right"  
+
 
|- 
+
The Federal Emergency Management Agency (FEMA) through the National Flood Insurance Program (NFIP) requires the management of development within regulated floodplains. FEMA defines development as: Any man-made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials.
|'''Forms'''
+
 
 +
For NFIP requirements and Floodplain Development Permit information, see [[127.9 Floodplain Management|EPG 127.9 Floodplain Management]].
 +
{|style="padding: 0.3em; margin-left:7px; border:2px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="285px" align="right"  
 
|-
 
|-
|[[:Category:101 Standard Forms#Floodplain Development Permit/Application|Floodplain Development Permit]]
+
|[[:Category:101 Standard Forms#Floodplain Development Permit/Application|'''Floodplain Development Permit''']]
 
|-
 
|-
|[[:Category:101 Standard Forms|No-Rise Certification]]  
+
|[[:Category:101 Standard Forms#No-Rise Certificate|'''“No-Rise” Certification''']]
 
|}
 
|}
Communities (cities, counties or states) participating in the National Flood Insurance Program (NFIP) are required to regulate construction in the floodplain. Communities accomplish this by requiring permits for development in special flood hazard areas. The State Emergency Management Agency (SEMA) has been granted authority ([http://www.sos.mo.gov/library/reference/orders/1998/eo98_003.asp Executive Order No. 98-03]) to regulate floodplain development by state agencies and to issue floodplain development permits for state projects. SEMA requires a floodplain development permit for any development in special flood hazard areas, regardless of whether the community is participating in the NFIP.
+
==748.8.1 Floodplain Management Tools==
 +
 
 +
===748.8.1.1 Floodplain and Special Flood Hazard Area===
 +
A floodplain is defined by the Federal Emergency Management Agency (FEMA) as any land area susceptible to being inundated by water. The 100-year flood, or a flood with a one percent annual chance of being equaled or exceeded in a given year, has been adopted by FEMA as the Base (regulatory) Flood for the National Flood Insurance Program (NFIP). The water surface elevation of the Base Flood is known as the Base Flood Elevation (BFE).
 +
 
 +
A Special Flood Hazard Area (SFHA) is land in the floodplain inundated by the Base Flood and is commonly referred to as the "100-year floodplain." Special Flood Hazard Areas are typically shown as "Zone A, (A1-A30), or AE" on flood insurance maps. A floodplain development permit is typically required for any construction in a Special Flood Hazard Area.
 +
 
 +
===748.8.1.2 Floodway===
 +
Encroachment in the floodplain, such as roadway fill, can reduce the flood-carrying capacity, increase the flood elevations in streams and increase flood hazards in areas beyond the encroachment itself. One aspect of floodplain management involves balancing the economic gain from floodplain development against the resulting increase in flood hazard. For the purposes of the NFIP, the floodway concept is used as a tool to assist in this aspect of floodplain management.
 +
 
 +
The 100-year floodplain is divided into a floodway and a floodway fringe. The floodway is the channel of the stream plus the portions of the adjacent overbanks which must be kept free of encroachment in order to pass the Base Flood without cumulatively increasing the water surface elevations by more than a designated height. The floodway fringe is the area between the floodway and floodplain boundaries.
 +
 
 +
[[Image:748.9 Floodplain.jpg|center|800px|thumb|<center>'''Floodplain Encroachment and Floodway'''</center>]]
 +
 
 +
==748.8.2 FEMA Floodplain Products==
 +
 
 +
The Federal Emergency Management Agency (FEMA) conducts studies to determine floodplain boundaries, floodway boundaries and Base Flood Elevations.  Products produced from these studies include:
 +
 
 +
:* Flood Insurance Study (FIS) report
 +
:* Flood Insurance Maps
 +
:* Hydraulic Models
 +
:* Hydrologic Models.
 +
 
 +
The FIS report and flood insurance maps are typically not updated until a revised FIS is conducted. Changes or corrections made after the FIS report is published are accomplished through a Letter of Map Changes (LOMC).
 +
 
 +
===748.8.2.1 Community Status Book===
 +
A current list of communities for which flood insurance studies have been performed is available in FEMA’s [http://www.fema.gov/cis/MO.pdf Community Status Book (CSB)].  
 +
 
 +
This list may be consulted to determine if a flood insurance study has been performed for any community within the project limits. The CSB list is divided into two parts: communities participating in the NFIP and communities that are not participating. Both parts of the list must be reviewed, as permits are required by SEMA for projects in a special flood hazard area when a flood insurance study has been performed, regardless of whether the community participates in the NFIP.
 +
 
 +
The CSB also includes the effective date of the current flood insurance study for the community. It is important to compare this date with the effective date of the FIS and maps used; if the CSB shows a later date, a revised study report and maps is available.
 +
 
 +
===748.8.2.2 Flood Insurance Study (FIS) Report===
 +
FIS reports are produced on a county wide basis for all communities within the county (city wide for the City of St. Louis). Cities within the county that participate in the NFIP are considered communities. FEMA considers the county to be the community in unincorporated areas and in cities that do not participate in the NFIP.  Some older studies produced separate FIS reports for each community in the county.
  
The [http://wwwi/design/EnvironmentalStudies.htm Design Division's environmental section] reviews projects to determine if there will be any encroachment into the floodplain or regulatory floodway and provides the results of these reviews to the districts in RES responses. If a permit is necessary, the [http://wwwi/intranet/br/default.htm Bridge Division] will obtain floodplain development permit(s) from SEMA for projects which include structures in a regulated floodplain, and the district will obtain permits for other [[127.9 Floodplain Management and the Regulatory Floodway|projects involving roadway fill in a regulated floodplain]]Bridge Division or district Design will be responsible for determining whether a floodplain development permit is required on the project, and for providing SEMA with any project information necessary to obtain the permit, including any required "no rise" certifications for work in a regulated floodway.
+
The FIS report is used to record the methods used to conduct the flood insurance study. Depending on the degree of flood hazard posed, a particular stream may have been analyzed by approximate methods or by detailed hydrologic and hydraulic methods. The level of information presented in the study can vary greatly depending on whether the stream in question was studied by detailed or approximate methodsInformation for a studied stream may include:
  
==748.9.2 Floodplain and Special Flood Hazard Area==
+
:* stream discharges,
A floodplain is defined by the Federal Emergency Management Agency (FEMA) as any land area susceptible to being inundated by water. The 100-year flood, or a flood with a one percent annual chance of being equaled or exceeded in a given year, has been adopted by FEMA as the base flood for the NFIP. The water surface elevation of the base flood is known as the base flood elevation (BFE). A special flood hazard area is land in the floodplain inundated by the 100-year flood and is commonly referred to as the "100-year floodplain." A floodplain development permit is required for any construction in a special flood hazard area. Special flood hazard areas are typically shown as "A zones" on flood insurance maps.
+
:* floodway widths,
 +
:* water surface elevations,
 +
:* hydrologic modeling method,
 +
:* hydraulic modeling method,
 +
:* method used to determine the beginning water surface elevation,
 +
:* flood profiles for streams with detailed studies,
 +
:* elevation datum of the FIS.  
  
==748.9.3 Floodway==
+
The FIS report for any communities within the project limits should be carefully reviewed.  
Encroachment on the floodplain, such as roadway fill, reduces the flood-carrying capacity, increases the flood heights of streams and increases flood hazards in areas beyond the encroachment itself. One aspect of floodplain management involves balancing the economic gain from floodplain development against the resulting increase in flood hazard. For the purposes of the NFIP, the floodway concept is used as a tool to assist in this aspect of floodplain management. The 100-year floodplain is divided into a floodway and a floodway fringe. The floodway is the channel of the stream plus the portions of the adjacent overbanks which must be kept free of encroachment in order to pass the base flood without cumulatively increasing the water surface elevations by more than a designated height. The floodway fringe is the area between the floodway and floodplain boundaries.
 
  
[[Image:748.9 Flookplain Encroachment and Floodway.gif|800px]]
+
The FIS report is typically not updated until a revised FIS is conducted. Changes or corrections made after the FIS report is published are accomplished through a Letter of Map Correction (LOMC).
  
===748.9.3.1 Construction within a Floodway===
+
FIS reports are available through the [https://msc.fema.gov/portal/search?AddressQuery=washington%20dc#searchresultsanchor FEMA Map Service Center].
Construction in the floodway that causes any increase in the BFE is prohibited. In order to issue a floodplain development permit for construction in the floodway, a "No-Rise Certification" must be provided by a registered professional engineer, which certifies that the proposed construction will cause no increase in the BFE.
 
  
Several methods can be used to demonstrate that a construction project within a floodway will not cause an increase in the BFE. The simplest method is to model both the existing conditions and the proposed conditions. Comparison of the water surface elevations from these two models will show any increase caused by the construction; generally, if the project as a whole causes no increase in the BFE, that portion within the floodway will also cause no increase. 
+
===748.8.2.3 Flood Insurance Maps===
 +
Flood insurance maps may be one of three types:
  
Another method is to include only that portion of the project within the floodway in a "proposed conditions" model. Comparison of these water surface elevations to the existing conditions water surface elevations will directly show the impact of the proposed construction in the floodway.
+
:* Flood Insurance Rate Maps (FIRMs),
 +
:* Flood Boundary and Floodway Maps (FBFMs),
 +
:* or Flood Hazard Boundary Maps (FHBMs).  
  
It is generally not difficult to show no increase in BFE's for bridge replacements where the existing bridge is on or near the existing alignment; new bridges are usually longer and cause less obstruction to the 100-year discharge than existing bridges. For bridges on new alignment, additional steps must sometimes be taken to cause no increase in BFE's. Possibilities include modification of the roughness coefficients through the structure or excavation of material from the overbanks for some distance upstream and downstream of the structure. All such modifications must be justifiable.
+
Originally, FBFMs were used to delineate the floodway and FIRMs or FHBMs were used to delineate the various insurance rating zones. The map types have been combined, and now only the FIRM is published. Newer FIRMs delineate both rating zones and floodways. Depending on the publication date of the flood insurance study, it may be necessary to look at either a FBFM or a FIRM to determine whether the project lies within a regulatory floodway.  
  
===748.9.3.2 Temporary Bridges===
+
FHBMs and FIRMs are used when detailed studies have not been performed, no floodway has been developed, and floodplain boundaries are approximate.
Temporary bridges designed to pass the 10-year discharge with 1.0 ft. of backwater will typically result in an increase in base flood elevations. Permits for temporary bridges in floodways will be handled by SEMA on a case-by-case basis. The floodplain development permit application for temporary bridges must include the following:
+
 
 +
FIRMs and FBFMs are used when a detailed study has been performed and a floodway has been developed, and show the boundaries of both the floodplain and the floodway. Special flood hazard areas are typically shown as Zone A on FHBMs and as Zone A, Zone AE, or Zones A1 through A30 on FIRMs and FBFMs.
 +
 +
For all communities for which a flood insurance study has been performed, the maps that include a portion of the project should be checked to determine if the project is within a special flood hazard area. If so, a floodplain development permit may be required.
 +
 
 +
If a floodplain development permit is required and any portion of the project is to be constructed within a regulatory floodway, the portion of the construction within the floodway cannot cause an increase in the BFE and a No-Rise Certification will be required by SEMA.
 +
 
 +
Flood insurance map panels are available through the [https://msc.fema.gov/portal/search?AddressQuery=washington%20dc#searchresultsanchor FEMA Map Service Center]. The [https://hazards-fema.maps.arcgis.com/apps/webappviewer/index.html?id=8b0adb51996444d4879338b5529aa9cd National Flood Hazard Layer (NFHL)] shows all digital map data, FIRM panels for counties with digital maps may be printed from the NFHL. The NFHL is also available as a kmz file for use in Google Earth.
 +
 
 +
===748.8.2.4 Hydraulic Models===
 +
Hydraulic models used to develop the data for a flood insurance study may be available from FEMA.  The most common models are HEC-2 and HEC-RAS. 
 +
 
 +
FEMA HEC-RAS models for streams with detailed studies typically can be used as the base model for the existing conditions model. On streams studied using unsteady state flow, or 2D analysis, the FEMA model should be used as the base model due to the difficulty in reproducing the discharge hydrographs used in the model.
 +
 
 +
FEMA HEC-RAS models for streams with approximate studies typically are not used as base models. Approximate models do not include manmade structures or floodplain encroachments; typically the valley sections are not at appropriate locations for modeling structures and encroachments.
 +
 
 +
FEMA HEC-2 (predecessor of HEC-RAS) models are sometimes available, but often only the input and output data is available. Due to the age of these models it is typically not recommended that HEC-2 Models be used as the base model for the existing conditions model.
 +
 
 +
===748.8.2.5 Hydrologic Models===
 +
Hydrologic models used to develop stream discharges for a flood insurance study may be available from FEMA.
 +
 
 +
===748.8.2.6 Letters of Map Changes===
 +
Letters of Map Changes (LOMC) are documents issued by FEMA that revise or amend the flood hazard information shown on the FIRM without requiring the FIRM to be physically revised and re-published. LOMCs can be one of the following types:
 +
 
 +
:* Letter of Map Revision (LOMR)
 +
:* Letter of Map Revision Based on Fill (LOMR-F)
 +
:* Letter of Map Amendment (LOMA).
 +
 
 +
A LOMR is a modification to an effective Flood Insurance Map. LOMRs are generally based on physical changes in the floodplain that affect the hydrologic or hydraulic characteristics of a flooding source and thus result in the modification of the existing regulatory floodway, the effective Base Flood Elevations (BFE), or boundary of the Special Flood Hazard Area (SFHA). The LOMR officially revises the Flood Insurance Rate Map (FIRM) or Flood Boundary and Floodway Map (FBFM), and sometimes the Flood Insurance Study (FIS) report, and when appropriate, includes a description of the modifications. The LOMR is generally accompanied by an annotated copy of the affected portions of the FIRM, FBFM, and FIS report.
 +
 
 +
A LOMR-F is a modification of the Special Flood Hazard Area (SFHA) shown on the Flood Insurance Map based on the placement of fill outside an existing regulatory floodway.
 +
 
 +
A LOMA is an official amendment, by letter, to an effective National Flood Insurance Map. A LOMA establishes a property's location in relation to the Special Flood Hazard Area (SFHA). A LOMA is usually issued because a property has inadvertently been mapped as being in the floodplain, but is actually on natural high ground above the base flood elevation.
 +
 
 +
LOMRs should be reviewed to determine if any changes were made to the BFE, SFHA  limits or floodway limits within the project area.  LOMR-Fs and LOMAs do not apply to transportation infrastructure and typically do not need to be reviewed.  
 +
 
 +
===748.8.2.7 Review of FEMA Floodplain Products===
 +
'''Encroachments.''' To determine whether a project encroaches into a regulated floodplain or floodway on the current effective Flood Insurance Map or pending Flood Insurance Map, the following sources should be consulted:
 +
:* [https://hazards-fema.maps.arcgis.com/apps/webappviewer/index.html?id=8b0adb51996444d4879338b5529aa9cd National Flood Hazard Layer]
 +
::• Current Effective FIRMs
 +
::• Digital Maps only (not all counties have digital maps available)
 +
:* [https://msc.fema.gov/portal/search?AddressQuery=washington%20dc#searchresultsanchor FEMA Map Service Center]
 +
::• Historical, Current Effective, Pending and Prelim. Flood Insurance Maps
 +
::• Digital and scanned paper (non-digital) maps
 +
:* [https://fema.maps.arcgis.com/apps/webappviewer/index.html?id=e7a7dc3ebd7f4ad39bb8e485bb64ce44 FEMA Map Change Viewer]
 +
::• Current Effective, Pending and Prelim. Flood Insurance Maps
 +
::• Digital Maps only.
 +
 
 +
To determine if a Floodplain Development Permit Application or “No-Rise” Certificate is needed, see [[127.9 Floodplain Management#127.9.2 Floodplain Development Permits|EPG 127.9.2 Floodplain Development Permits]].
 +
 
 +
For information on how a Pending or Preliminary FIRM may impact an upcoming project, review the Pending or Preliminary Flood Insurance Study report or contact the Structural Hydraulics Engineer in Bridge Division.
  
*hydraulic analysis of the effect of the temporary bridge on base flood elevations
+
'''Design.''' The flood insurance maps noted above should be used to determine the Flood Hazard Zone(s) the project encroaches into and if a floodway is involved. The Current Effective Flood Insurance Study (FIS) report (Pending and Preliminary FIS report if applicable) should also be reviewed.  The following data in the FIS report will aid in the project’s design and may be required to meet FEMA requirements (some FIS reports do not contain some of the items listed below):
*determination of the effect of any increased flooding resulting from the temporary bridge on any upstream improvements
 
*estimate of length of time temporary bridge will be in place
 
  
===748.9.3.3 Culvert Extensions===
+
:* Flooding Sources Included in the Report
Culvert extensions in floodways can pose a particularly challenging problem depending on whether they operate under inlet control or outlet control.
+
:* Study type (approximate or detailed) of the flooding source
 +
:* Principle Flood Problems
 +
:* Flooding sources with accredited levees
 +
:* Hydrologic methods used to determine peak discharges
 +
:* Summary of peak discharges for flooding sources
 +
:* Stream gage information
 +
:* Hydraulic Models used for analysis
 +
:* Roughness Coefficients used for each flooding source
 +
:* Starting water surface determination method
 +
:* Vertical Datum information
 +
:* Floodway Data Tables
 +
:* Flood Profiles.
  
Culverts operating under inlet control can generally be lengthened without increasing water surface elevations. In some cases, an improvement to the inlet may be required to compensate for increases in culvert length.
+
==748.8.3 Design of Encroachments==
  
Culverts operating under outlet control generally can not be lengthened without increasing water surface elevations upstream.
+
===748.8.3.1 Construction Within a Floodplain===
 +
Construction in the floodplain that causes an increase of more than 1 foot over the natural condition in the BFE is prohibited, except when the hydraulic performance of an existing structure is being matched, see [[748.4 Headwater and Backwater#748.4.3 Existing Structures|EPG 748.4.3 Existing Structures]].
 +
 +
If it is not practical to limit the increase in BFE to 1 foot a Conditional Letter of Map Revision (CLOMR) can be submitted to FEMA to modify the FIS and Flood Insurance Maps, See [[#748.8.4 Letters of Map Revision|EPG 748.8.4 Letters of Map Revision]].  
  
===748.9.3.4 Floodway Revisions===
+
===748.8.3.2 Construction within a Floodway===
Where construction in an existing floodway is absolutely necessary, and such construction will cause an increase in the BFE, the flood insurance study or floodway must be revised so that the proposed construction no longer causes an increase in the BFE or is no longer in the floodway.  Flood insurance study revisions are obtained from FEMA through the community or communities with jurisdiction. The revision process requires a detailed hydraulic analysis and the cooperation and approval of all communities involved.
+
Construction within a floodway that causes any increase in the BFE is prohibited. In order to issue a floodplain development permit for construction in the floodway, a "No-Rise Certification" must be provided by a registered professional engineer, which certifies that the proposed construction will cause no increase in the BFE.  
  
In general, obtaining a revision is a difficult and time-consuming process and should be avoided if at all possible. However, revising the floodway can be particularly cost-effective in one situation. Floodway widths are determined precisely only at the locations of cross-sections in the hydraulic model used to create the FIS.  At all other locations along the stream, floodway widths are determined by interpolation along topographic maps. When a stream crossing is located between cross-sections, at a significant distance from both the upstream and downstream cross-section, it may be beneficial to review the hydraulic model used in the FIS. In some cases, adding an additional cross-section to the model at the location of the proposed structure will allow the floodway width to be reduced at that location, especially if the floodway appears unusually wide at the structure location.
+
Several methods can be used to demonstrate that a construction project within a floodway will not cause an increase in the BFE. The simplest method is to model both the existing conditions and the proposed conditions. Comparison of the water surface elevations from these two models will show any increase caused by the construction; generally, if the project as a whole causes no increase in the BFE, that portion within the floodway will also cause no increase.  
  
==748.9.4 Review of Flood Insurance Study and Maps==
+
Another method is to model the existing and proposed conditions using a floodway analysis. Comparison of these water surface elevations will directly show the impact of the proposed construction in the floodway.  
Since paper copies are no longer provided to MoDOT, the [http://msc.fema.gov/webapp/wcs/stores/servlet/FemaWelcomeView?storeId=10001&catalogId=10001&langId=-1 FEMA Map Service Center] or SEMA office may be consulted for Flood Insurance reports, maps and related material.
 
  
===748.9.4.1 Community Status Book===
+
It is generally not difficult to show no increase in BFEs for bridge replacements where the existing bridge is on or near the existing alignment and there is little or no roadway overtopping. For bridges on new alignment, or with significant roadway overtopping, additional steps can sometimes be taken to limit the length of the new bridge and to cause no increase in BFEs. Possibilities include modification of the roughness coefficients through the structure or excavation of material from the overbanks for some distance upstream and downstream of the structure. All such modifications must be justifiable.  
A current list of communities for which flood insurance studies have been performed is available in the [http://www.fema.gov/cis/MO.pdf Community Status Book (CSB).]
 
  
This list should be consulted to determine if a flood insurance study has been performed for any community within the project limits. The CSB list is divided into two parts: communities participating in the NFIP and communities that are not participating. Both parts of the list must be reviewed, as permits are required by SEMA for projects in a special flood hazard area when a flood insurance study has been performed, regardless of whether the community participates in the NFIP.
+
If it is not practical to cause no increase to the BFEs a Conditional Letter of Map Revision (CLOMR) can be submitted to FEMA to modify the FIS and Flood Insurance Maps, See [[#748.8.4 Letters of Map Revision|EPG 748.8.4 Letters of Map Revision]].  
  
The CSB also includes the effective date of the current flood insurance study for the community. It is important to compare this date with the effective date of the FIS and maps used; if the CSB shows a later date, a revised study report and maps must be obtained.
+
====748.8.3.2.1 Temporary Bridges====
 +
Temporary bridges designed to pass the 10-year discharge with 1.0 ft. of backwater will typically result in an increase in base flood elevations. Permits for temporary bridges in floodways will be handled by SEMA on a case-by-case basis. The floodplain development permit application for temporary bridges must include the following:
 +
 +
:* Hydraulic analysis of the effect of the temporary bridge on base flood elevations
 +
:* Determination of the effect of any increased flooding resulting from the temporary bridge on any upstream improvements
 +
:* Estimate of length of time temporary bridge will be in place.
  
===748.9.4.2 Flood Insurance Study===
+
For additional information, see Section 4.4 of FEMA Bulletin P-993, [https://www.fema.gov/media-library-data/1415994328968-8a331cb33b4b5aeb3ab26f9d382a7f68/FEMA_P_993_FPM_Bulletin_Variance.pdf Variances and the National Flood Insurance Program], or consult the Structural Hydraulics Engineer in Bridge Division.
The study report contains valuable information regarding discharges, floodway widths, water surface elevations, and other items that may be pertinent to hydraulic design. Depending on the degree of flood hazard posed, a particular stream may have been analyzed by approximate methods or by detailed hydrologic and hydraulic methods. The level of information presented in the study can vary greatly depending on whether the stream in question was studied by detailed or approximate methods. The report for any communities within the project limits should be carefully reviewed.
 
  
===748.9.4.3 Flood Insurance Maps===
+
====748.8.3.2.2 Culvert Extensions====
The FIS maps may be one of three types: Flood Insurance Rate Maps (FIRMs), Flood Boundary and Floodway Maps (FBFMs), or Flood Hazard Boundary Maps (FHBMs). FHBMs are used when detailed studies have not been performed, no floodway has been developed, and floodplain boundaries are approximate. FIRMs and FBFMs are used when a detailed study has been performed and a floodway has been developed and show the boundaries of both the floodplain and the floodway. Special flood hazard areas are typically shown as Zone A on FHBMs and as Zone A, Zone AE, or Zones A1 through A30 on FIRMs and FBFMs.
+
Culvert extensions in floodways can pose a particularly challenging problem depending on whether they operate under inlet control or outlet control.  
  
Originally, FBFMs were used to delineate the floodway and FIRMs were used to delineate the various insurance rating zones. Recently, however, the two were combined, and now only the FIRM is published. The newer FIRMs delineate both rating zones and floodways. Depending on the publication date of the flood insurance study, it may be necessary to look at either a FBFM or a FIRM to determine whether the project lies within a regulatory floodway.
+
Culverts operating under inlet control can generally be lengthened without increasing water surface elevations. In some cases, an improvement to the inlet may be required to compensate for increases in culvert length.  
  
For all communities for which a flood insurance study has been performed, the maps that include a portion of the project should be checked to determine if the project is within a special flood hazard area. If so, a floodplain development permit is required. 
+
Culverts operating under outlet control generally cannot be lengthened without increasing water surface elevations upstream.  
  
If any portion of the project is to be constructed within a regulatory floodway, the portion of the construction within the floodway can not cause an increase in the BFE and a No-Rise Certification will be required by SEMA.
+
If it is not practical to cause no increase to the BFEs a Conditional Letter of Map Revision (CLOMR) can be submitted to FEMA to modify the FIS and Flood Insurance Maps. See EPG 748.8.4 Letters of Map Revision.  
  
===748.9.4.4 Summary of FIS Review Process===
+
==748.8.4 Letters of Map Revision==
The process for reviewing floodway maps is summarized below:
 
*Check all communities within project limits to see if a flood insurance study has been performed.
 
*If study exists, check maps (FIRMs, FBFMs, FHBMs).
 
*If in special flood hazard area, floodplain development permit is required.
 
*If in regulatory floodway, can cause no increase in BFE. No-Rise Certification is required. 
 
*If it is not possible to achieve no increase in BFE, a flood insurance study or floodway revision may be required.
 
  
==748.9.5 Floodplain Development Permit Application and No-Rise Certification==
+
Where the proposed construction in an absolutely necessary, and such construction will cause an increase in the BFE, or increase in floodway width, of an existing floodway, or increase the BFE of a SFHA by more than 1 foot, the Flood Insurance Study (FIS) or floodway must be revised so that the proposed construction no longer causes an increase, greater than the amount allowed, in the BFE. Flood insurance study revisions for construction related revisions require the submission of a detailed hydraulic analysis, annotated FIRM panel(s) and FIS report be submitted to FEMA in the form of a Conditional Letter of Map Revision (CLOMR). Upon approval of FEMA’s review of the CLOMR and with concurrence of all communities involved, SEMA will approve a floodplain development permit for the project. One the project is complete the hydraulic model and annotated FIRM(s) and FIS are updated and submitted to FEMA. Once FEMA has reviewed and accepted the changes to the FIRM(s) and FIS they will issue a Letter of Map Revision (LOMR).
The SEMA [[:Category:101 Standard Forms|Floodplain Development Permit]] and [[:Category:101 Standard Forms|No-Rise Certification]] (when required) are to be completed with care, particularly:
 
*Property Owner shall be listed as: Missouri Highways and Transportation Commission; 105 West Capitol Avenue, Jefferson City, Missouri 65101.  Community and County information should be provided for the actual location of the bridge.
 
*determination of the quarter-quarter section, township and range
 
*floodway/floodway fringe designation
 
*100-year flood elevation and datum – the FIS base flood elevation should be given if available
 
*current map date – check the community status book
 
*project description - must include all aspects of the proposed construction, including grading, fill, and pavement in addition to the proposed bridge
 
  
The application for permit shall include a photocopy or [http://msc.fema.gov/webapp/wcs/stores/servlet/info?storeId=10001&catalogId=10001&langId=-1&content=firmetteHelp_A&title=FIRMettes Firmette] of the section of the relevant flood map.
+
In general, obtaining a CLOMR/LOMR is a difficult and time-consuming process and should be avoided if at all possible. However, revising the floodway can be cost-effective in one situation. Floodway widths are determined precisely only at the locations of cross-sections in the hydraulic model used to create the FIS. At all other locations along the stream, floodway widths are determined by interpolation along topographic maps. When a stream crossing is located between cross-sections, at a significant distance from both the upstream and downstream cross-section, it may be beneficial to review the hydraulic model used in the FIS. In some cases, adding an additional cross-section to the model at the location of the proposed structure will allow the floodway width to be reduced at that location, especially if the floodway appears unusually wide at the structure location.
  
==748.9.6 Levee Attachments==
+
==748.8.5 Levees==
 +
 
 +
Information concerning levees on MHTC right of way and roadway embankments versus levees is located in [[:Category:203 Roadway and Drainage Excavation, Embankment and Compaction#203.2.5 Levee Attachments|EPG 203.2.5 Levee Attachments]].  Information on freeboard of FEMA accredited levees can be found in [[748.3 Freeboard#748.3.4 Levees|EPG 748.3.4 Levees]].
  
Information concerning levees on MHTC right of way and roadway embankments versus levees is located in [[:Category:203 Roadway and Drainage Excavation, Embankment and Compaction#203.2.5 Levee Attachments|EPG 203 Roadway and Drainage Excavation, Embankment and Compaction]].
 
  
==748.9.7 Acronyms==
 
{|
 
|BFE || || Base Flood Elevation
 
|-
 
|CSB || || Community Status Book
 
|-
 
|FBFM || || Flood Boundary and Floodway Map
 
|-
 
|FEMA || || Federal Emergency Management Agency
 
|-
 
|FHBM || || Flood Hazard Boundary Map
 
|-
 
|FIRM || || Flood Insurance Rate Map
 
|-
 
|FIS || || Flood Insurance Study
 
|-
 
|NFIP || || National Flood Insurance Program
 
|-
 
|SEMA || || State Emergency Management Agency
 
|}
 
  
 
[[Category:748 Hydraulics and Drainage|748.09]]
 
[[Category:748 Hydraulics and Drainage|748.09]]

Latest revision as of 08:26, 3 September 2019

Acting as the Federal Highway Administration’s (FHWA’s) agent, MoDOT must evaluate every project to determine whether it could have a negative impact on the base (1% or 100-year) floodplain and/or regulatory floodway. 23 CFR 650A requires that hydraulic conditions created by a project be consistent with Federal Emergency Management Agency (FEMA) standards established for the NFIP.

The Federal Emergency Management Agency (FEMA) through the National Flood Insurance Program (NFIP) requires the management of development within regulated floodplains. FEMA defines development as: Any man-made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials.

For NFIP requirements and Floodplain Development Permit information, see EPG 127.9 Floodplain Management.

Floodplain Development Permit
“No-Rise” Certification

748.8.1 Floodplain Management Tools

748.8.1.1 Floodplain and Special Flood Hazard Area

A floodplain is defined by the Federal Emergency Management Agency (FEMA) as any land area susceptible to being inundated by water. The 100-year flood, or a flood with a one percent annual chance of being equaled or exceeded in a given year, has been adopted by FEMA as the Base (regulatory) Flood for the National Flood Insurance Program (NFIP). The water surface elevation of the Base Flood is known as the Base Flood Elevation (BFE).

A Special Flood Hazard Area (SFHA) is land in the floodplain inundated by the Base Flood and is commonly referred to as the "100-year floodplain." Special Flood Hazard Areas are typically shown as "Zone A, (A1-A30), or AE" on flood insurance maps. A floodplain development permit is typically required for any construction in a Special Flood Hazard Area.

748.8.1.2 Floodway

Encroachment in the floodplain, such as roadway fill, can reduce the flood-carrying capacity, increase the flood elevations in streams and increase flood hazards in areas beyond the encroachment itself. One aspect of floodplain management involves balancing the economic gain from floodplain development against the resulting increase in flood hazard. For the purposes of the NFIP, the floodway concept is used as a tool to assist in this aspect of floodplain management.

The 100-year floodplain is divided into a floodway and a floodway fringe. The floodway is the channel of the stream plus the portions of the adjacent overbanks which must be kept free of encroachment in order to pass the Base Flood without cumulatively increasing the water surface elevations by more than a designated height. The floodway fringe is the area between the floodway and floodplain boundaries.

Floodplain Encroachment and Floodway

748.8.2 FEMA Floodplain Products

The Federal Emergency Management Agency (FEMA) conducts studies to determine floodplain boundaries, floodway boundaries and Base Flood Elevations. Products produced from these studies include:

  • Flood Insurance Study (FIS) report
  • Flood Insurance Maps
  • Hydraulic Models
  • Hydrologic Models.

The FIS report and flood insurance maps are typically not updated until a revised FIS is conducted. Changes or corrections made after the FIS report is published are accomplished through a Letter of Map Changes (LOMC).

748.8.2.1 Community Status Book

A current list of communities for which flood insurance studies have been performed is available in FEMA’s Community Status Book (CSB).

This list may be consulted to determine if a flood insurance study has been performed for any community within the project limits. The CSB list is divided into two parts: communities participating in the NFIP and communities that are not participating. Both parts of the list must be reviewed, as permits are required by SEMA for projects in a special flood hazard area when a flood insurance study has been performed, regardless of whether the community participates in the NFIP.

The CSB also includes the effective date of the current flood insurance study for the community. It is important to compare this date with the effective date of the FIS and maps used; if the CSB shows a later date, a revised study report and maps is available.

748.8.2.2 Flood Insurance Study (FIS) Report

FIS reports are produced on a county wide basis for all communities within the county (city wide for the City of St. Louis). Cities within the county that participate in the NFIP are considered communities. FEMA considers the county to be the community in unincorporated areas and in cities that do not participate in the NFIP. Some older studies produced separate FIS reports for each community in the county.

The FIS report is used to record the methods used to conduct the flood insurance study. Depending on the degree of flood hazard posed, a particular stream may have been analyzed by approximate methods or by detailed hydrologic and hydraulic methods. The level of information presented in the study can vary greatly depending on whether the stream in question was studied by detailed or approximate methods. Information for a studied stream may include:

  • stream discharges,
  • floodway widths,
  • water surface elevations,
  • hydrologic modeling method,
  • hydraulic modeling method,
  • method used to determine the beginning water surface elevation,
  • flood profiles for streams with detailed studies,
  • elevation datum of the FIS.

The FIS report for any communities within the project limits should be carefully reviewed.

The FIS report is typically not updated until a revised FIS is conducted. Changes or corrections made after the FIS report is published are accomplished through a Letter of Map Correction (LOMC).

FIS reports are available through the FEMA Map Service Center.

748.8.2.3 Flood Insurance Maps

Flood insurance maps may be one of three types:

  • Flood Insurance Rate Maps (FIRMs),
  • Flood Boundary and Floodway Maps (FBFMs),
  • or Flood Hazard Boundary Maps (FHBMs).

Originally, FBFMs were used to delineate the floodway and FIRMs or FHBMs were used to delineate the various insurance rating zones. The map types have been combined, and now only the FIRM is published. Newer FIRMs delineate both rating zones and floodways. Depending on the publication date of the flood insurance study, it may be necessary to look at either a FBFM or a FIRM to determine whether the project lies within a regulatory floodway.

FHBMs and FIRMs are used when detailed studies have not been performed, no floodway has been developed, and floodplain boundaries are approximate.

FIRMs and FBFMs are used when a detailed study has been performed and a floodway has been developed, and show the boundaries of both the floodplain and the floodway. Special flood hazard areas are typically shown as Zone A on FHBMs and as Zone A, Zone AE, or Zones A1 through A30 on FIRMs and FBFMs.

For all communities for which a flood insurance study has been performed, the maps that include a portion of the project should be checked to determine if the project is within a special flood hazard area. If so, a floodplain development permit may be required.

If a floodplain development permit is required and any portion of the project is to be constructed within a regulatory floodway, the portion of the construction within the floodway cannot cause an increase in the BFE and a No-Rise Certification will be required by SEMA.

Flood insurance map panels are available through the FEMA Map Service Center. The National Flood Hazard Layer (NFHL) shows all digital map data, FIRM panels for counties with digital maps may be printed from the NFHL. The NFHL is also available as a kmz file for use in Google Earth.

748.8.2.4 Hydraulic Models

Hydraulic models used to develop the data for a flood insurance study may be available from FEMA. The most common models are HEC-2 and HEC-RAS.

FEMA HEC-RAS models for streams with detailed studies typically can be used as the base model for the existing conditions model. On streams studied using unsteady state flow, or 2D analysis, the FEMA model should be used as the base model due to the difficulty in reproducing the discharge hydrographs used in the model.

FEMA HEC-RAS models for streams with approximate studies typically are not used as base models. Approximate models do not include manmade structures or floodplain encroachments; typically the valley sections are not at appropriate locations for modeling structures and encroachments.

FEMA HEC-2 (predecessor of HEC-RAS) models are sometimes available, but often only the input and output data is available. Due to the age of these models it is typically not recommended that HEC-2 Models be used as the base model for the existing conditions model.

748.8.2.5 Hydrologic Models

Hydrologic models used to develop stream discharges for a flood insurance study may be available from FEMA.

748.8.2.6 Letters of Map Changes

Letters of Map Changes (LOMC) are documents issued by FEMA that revise or amend the flood hazard information shown on the FIRM without requiring the FIRM to be physically revised and re-published. LOMCs can be one of the following types:

  • Letter of Map Revision (LOMR)
  • Letter of Map Revision Based on Fill (LOMR-F)
  • Letter of Map Amendment (LOMA).

A LOMR is a modification to an effective Flood Insurance Map. LOMRs are generally based on physical changes in the floodplain that affect the hydrologic or hydraulic characteristics of a flooding source and thus result in the modification of the existing regulatory floodway, the effective Base Flood Elevations (BFE), or boundary of the Special Flood Hazard Area (SFHA). The LOMR officially revises the Flood Insurance Rate Map (FIRM) or Flood Boundary and Floodway Map (FBFM), and sometimes the Flood Insurance Study (FIS) report, and when appropriate, includes a description of the modifications. The LOMR is generally accompanied by an annotated copy of the affected portions of the FIRM, FBFM, and FIS report.

A LOMR-F is a modification of the Special Flood Hazard Area (SFHA) shown on the Flood Insurance Map based on the placement of fill outside an existing regulatory floodway.

A LOMA is an official amendment, by letter, to an effective National Flood Insurance Map. A LOMA establishes a property's location in relation to the Special Flood Hazard Area (SFHA). A LOMA is usually issued because a property has inadvertently been mapped as being in the floodplain, but is actually on natural high ground above the base flood elevation.

LOMRs should be reviewed to determine if any changes were made to the BFE, SFHA limits or floodway limits within the project area. LOMR-Fs and LOMAs do not apply to transportation infrastructure and typically do not need to be reviewed.

748.8.2.7 Review of FEMA Floodplain Products

Encroachments. To determine whether a project encroaches into a regulated floodplain or floodway on the current effective Flood Insurance Map or pending Flood Insurance Map, the following sources should be consulted:

• Current Effective FIRMs
• Digital Maps only (not all counties have digital maps available)
• Historical, Current Effective, Pending and Prelim. Flood Insurance Maps
• Digital and scanned paper (non-digital) maps
• Current Effective, Pending and Prelim. Flood Insurance Maps
• Digital Maps only.

To determine if a Floodplain Development Permit Application or “No-Rise” Certificate is needed, see EPG 127.9.2 Floodplain Development Permits.

For information on how a Pending or Preliminary FIRM may impact an upcoming project, review the Pending or Preliminary Flood Insurance Study report or contact the Structural Hydraulics Engineer in Bridge Division.

Design. The flood insurance maps noted above should be used to determine the Flood Hazard Zone(s) the project encroaches into and if a floodway is involved. The Current Effective Flood Insurance Study (FIS) report (Pending and Preliminary FIS report if applicable) should also be reviewed. The following data in the FIS report will aid in the project’s design and may be required to meet FEMA requirements (some FIS reports do not contain some of the items listed below):

  • Flooding Sources Included in the Report
  • Study type (approximate or detailed) of the flooding source
  • Principle Flood Problems
  • Flooding sources with accredited levees
  • Hydrologic methods used to determine peak discharges
  • Summary of peak discharges for flooding sources
  • Stream gage information
  • Hydraulic Models used for analysis
  • Roughness Coefficients used for each flooding source
  • Starting water surface determination method
  • Vertical Datum information
  • Floodway Data Tables
  • Flood Profiles.

748.8.3 Design of Encroachments

748.8.3.1 Construction Within a Floodplain

Construction in the floodplain that causes an increase of more than 1 foot over the natural condition in the BFE is prohibited, except when the hydraulic performance of an existing structure is being matched, see EPG 748.4.3 Existing Structures.

If it is not practical to limit the increase in BFE to 1 foot a Conditional Letter of Map Revision (CLOMR) can be submitted to FEMA to modify the FIS and Flood Insurance Maps, See EPG 748.8.4 Letters of Map Revision.

748.8.3.2 Construction within a Floodway

Construction within a floodway that causes any increase in the BFE is prohibited. In order to issue a floodplain development permit for construction in the floodway, a "No-Rise Certification" must be provided by a registered professional engineer, which certifies that the proposed construction will cause no increase in the BFE.

Several methods can be used to demonstrate that a construction project within a floodway will not cause an increase in the BFE. The simplest method is to model both the existing conditions and the proposed conditions. Comparison of the water surface elevations from these two models will show any increase caused by the construction; generally, if the project as a whole causes no increase in the BFE, that portion within the floodway will also cause no increase.

Another method is to model the existing and proposed conditions using a floodway analysis. Comparison of these water surface elevations will directly show the impact of the proposed construction in the floodway.

It is generally not difficult to show no increase in BFEs for bridge replacements where the existing bridge is on or near the existing alignment and there is little or no roadway overtopping. For bridges on new alignment, or with significant roadway overtopping, additional steps can sometimes be taken to limit the length of the new bridge and to cause no increase in BFEs. Possibilities include modification of the roughness coefficients through the structure or excavation of material from the overbanks for some distance upstream and downstream of the structure. All such modifications must be justifiable.

If it is not practical to cause no increase to the BFEs a Conditional Letter of Map Revision (CLOMR) can be submitted to FEMA to modify the FIS and Flood Insurance Maps, See EPG 748.8.4 Letters of Map Revision.

748.8.3.2.1 Temporary Bridges

Temporary bridges designed to pass the 10-year discharge with 1.0 ft. of backwater will typically result in an increase in base flood elevations. Permits for temporary bridges in floodways will be handled by SEMA on a case-by-case basis. The floodplain development permit application for temporary bridges must include the following:

  • Hydraulic analysis of the effect of the temporary bridge on base flood elevations
  • Determination of the effect of any increased flooding resulting from the temporary bridge on any upstream improvements
  • Estimate of length of time temporary bridge will be in place.

For additional information, see Section 4.4 of FEMA Bulletin P-993, Variances and the National Flood Insurance Program, or consult the Structural Hydraulics Engineer in Bridge Division.

748.8.3.2.2 Culvert Extensions

Culvert extensions in floodways can pose a particularly challenging problem depending on whether they operate under inlet control or outlet control.

Culverts operating under inlet control can generally be lengthened without increasing water surface elevations. In some cases, an improvement to the inlet may be required to compensate for increases in culvert length.

Culverts operating under outlet control generally cannot be lengthened without increasing water surface elevations upstream.

If it is not practical to cause no increase to the BFEs a Conditional Letter of Map Revision (CLOMR) can be submitted to FEMA to modify the FIS and Flood Insurance Maps. See EPG 748.8.4 Letters of Map Revision.

748.8.4 Letters of Map Revision

Where the proposed construction in an absolutely necessary, and such construction will cause an increase in the BFE, or increase in floodway width, of an existing floodway, or increase the BFE of a SFHA by more than 1 foot, the Flood Insurance Study (FIS) or floodway must be revised so that the proposed construction no longer causes an increase, greater than the amount allowed, in the BFE. Flood insurance study revisions for construction related revisions require the submission of a detailed hydraulic analysis, annotated FIRM panel(s) and FIS report be submitted to FEMA in the form of a Conditional Letter of Map Revision (CLOMR). Upon approval of FEMA’s review of the CLOMR and with concurrence of all communities involved, SEMA will approve a floodplain development permit for the project. One the project is complete the hydraulic model and annotated FIRM(s) and FIS are updated and submitted to FEMA. Once FEMA has reviewed and accepted the changes to the FIRM(s) and FIS they will issue a Letter of Map Revision (LOMR).

In general, obtaining a CLOMR/LOMR is a difficult and time-consuming process and should be avoided if at all possible. However, revising the floodway can be cost-effective in one situation. Floodway widths are determined precisely only at the locations of cross-sections in the hydraulic model used to create the FIS. At all other locations along the stream, floodway widths are determined by interpolation along topographic maps. When a stream crossing is located between cross-sections, at a significant distance from both the upstream and downstream cross-section, it may be beneficial to review the hydraulic model used in the FIS. In some cases, adding an additional cross-section to the model at the location of the proposed structure will allow the floodway width to be reduced at that location, especially if the floodway appears unusually wide at the structure location.

748.8.5 Levees

Information concerning levees on MHTC right of way and roadway embankments versus levees is located in EPG 203.2.5 Levee Attachments. Information on freeboard of FEMA accredited levees can be found in EPG 748.3.4 Levees.