Difference between revisions of "104.7 Scoping Estimates"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (Per Bidding and TP, estimate guidance was clarified to reflect current practice in estimating.)
(Per Bidding and Estimates, estimating guidance updated to add optional spreadsheets to assist the districts with scoping and estimating processes. The Resurfacing Per Mile Scoping Form and the Project Scoping Form were made available.)
Line 1: Line 1:
 
[[image:104.7 Cost.jpg|left|475px]]
 
[[image:104.7 Cost.jpg|left|475px]]
  
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="240px" align="right"  
+
Estimates based on cost per mile shall in no case be considered to contain sufficient detail to allow their inclusion in the STIP.
 +
 +
The scoping estimate is used to determine solutions for a project.  There may be multiple scoping estimates for a project since there are multiple solutions for a project.  The district determines which solution best fits the purpose and need of the project and begins preliminary plans stage during which the [[121.7 Program Estimates|Program Estimate]] is complete.  The Program Estimate shall not use the cost per mile pricing because there are too many unknowns and assumptions made during the scoping stage of a project to produce an accurate Program Estimate.  The Program Estimate shall be at the preliminary plans stage after 30% of the plans are completed.
 +
{|style="padding: 0.3em; margin-left:15px; border:1px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="280px" align="right"  
 
|-
 
|-
|'''Figure'''
+
|'''Resources'''
 
|-
 
|-
 
|[[media:Fig 104.7.docx|Cost Estimate Guide for Scoping]]  
 
|[[media:Fig 104.7.docx|Cost Estimate Guide for Scoping]]  
 +
|-
 +
|[[media:121.7 Project Scoping Form.xlsx|Project Scoping Form]]
 +
|-
 +
|[[media:104.7 Resurfacing.xlsx|Resurfacing Per Mile Scoping Form]]
 
|}
 
|}
 +
The [[media:121.7 Project Scoping Form.xlsx|Project Scoping Form]] is available for detailed documentation of various project design elements of the project in order to assist the project estimator in covering all applicable project elements while establishing the conceptual estimate. Although not required, the Project Scoping Form can be used to establish a detailed project overview of all likely applicable costs, and while the tool itself does not yield an estimate, it does serve to clearly define and document the various project elements which combine to impact the project cost. This documentation will be beneficial as the project moves forward into preliminary design and programming.
  
Estimates based on cost per mile shall in no case be considered to contain sufficient detail to allow their inclusion in the STIP.
+
For preventative maintenance treatments, the [[media:104.7 Resurfacing.xlsx|Resurfacing Per Mile Scoping Form]] spreadsheet has basic inputs for average unit prices and the applicable work types. The spreadsheet generates a per mile cost for most resurfacing projects based upon the intended project elements to be includedWhen combined with BidTabs.net, this tool allows the user to quickly compare alternative treatments with costs based upon the specific unit costs for the project specific areaBy comparing the specific costs for each alternative, the project staff can select the best overall treatment in terms of cost and benefits for each project.
 
The scoping estimate is used to determine solutions for a project. There may be multiple scoping estimates for a project since there are multiple solutions for a project.  The district determines which solution best fits the purpose and need of the project and begins preliminary plans stage during which the [[121.7 Program Estimates|Program Estimate]] is completeThe Program Estimate shall not use the cost per mile pricing because there are too many unknowns and assumptions made during the scoping stage of a project to produce an accurate Program Estimate.  The Program Estimate shall be at the preliminary plans stage after 30% of the plans are completed.
 
  
 
The cost per mile assumption used to develop the scoping estimate should be derived using data from similar, recently-awarded, projects in the region.
 
The cost per mile assumption used to develop the scoping estimate should be derived using data from similar, recently-awarded, projects in the region.

Revision as of 10:25, 21 October 2019

Estimates based on cost per mile shall in no case be considered to contain sufficient detail to allow their inclusion in the STIP.

The scoping estimate is used to determine solutions for a project. There may be multiple scoping estimates for a project since there are multiple solutions for a project. The district determines which solution best fits the purpose and need of the project and begins preliminary plans stage during which the Program Estimate is complete. The Program Estimate shall not use the cost per mile pricing because there are too many unknowns and assumptions made during the scoping stage of a project to produce an accurate Program Estimate. The Program Estimate shall be at the preliminary plans stage after 30% of the plans are completed.

Resources
Cost Estimate Guide for Scoping
Project Scoping Form
Resurfacing Per Mile Scoping Form

The Project Scoping Form is available for detailed documentation of various project design elements of the project in order to assist the project estimator in covering all applicable project elements while establishing the conceptual estimate. Although not required, the Project Scoping Form can be used to establish a detailed project overview of all likely applicable costs, and while the tool itself does not yield an estimate, it does serve to clearly define and document the various project elements which combine to impact the project cost. This documentation will be beneficial as the project moves forward into preliminary design and programming.

For preventative maintenance treatments, the Resurfacing Per Mile Scoping Form spreadsheet has basic inputs for average unit prices and the applicable work types. The spreadsheet generates a per mile cost for most resurfacing projects based upon the intended project elements to be included. When combined with BidTabs.net, this tool allows the user to quickly compare alternative treatments with costs based upon the specific unit costs for the project specific area. By comparing the specific costs for each alternative, the project staff can select the best overall treatment in terms of cost and benefits for each project.

The cost per mile assumption used to develop the scoping estimate should be derived using data from similar, recently-awarded, projects in the region.

Where similar projects are not found, the Cost Estimate Guide for Scoping may be used. The Cost Estimate Guide for Scoping includes cost per mile factors derived from similar projects as well as the generic factors. These factors typically are for the major items of work and do not include other anticipated work that would be required to construct the project. All other anticipated construction costs should be included in the scoping estimate which is typically assumed at 20% but may be more or less depending on the project.