Flared end sections are either concrete or metal as required. These items will be inspected by the Division of Construction and Materials and an inspection report will be issued. These items should be installed and backfilled in the same manner required for the pipe. These items are paid for on a per each basis and the inspector should record in a field book when they were installed. A record should be made as to which type of toe wall was used. These entries should be signed by the inspector making them.