751.6 General Quantities

From Engineering_Policy_Guide
Jump to navigation Jump to search


751.6.1 Index of Quantities

The following list of pay items shall be used as a guide when preparing the Table of Estimated Quantities to be shown on the bridge plans. The pay items shall be listed on the plans in numerical order according to the Item Number. The Item Number is for information only and is not to be listed in the Table of Estimated Quantities. For pay items not listed, see the Review Section. For more information about pay items, see Pay Items Spreadsheet (For MoDOT Bridge access only).

Accuracy and Rounding

When performing multi-step calculations as in the case of computing the final estimated quantities, keep at least one more significant digit in the intermediate result than needed in the final answer, in this case the final estimated quantity. Hence, the accuracy given in the following indexed table of quantities represents the plan reporting accountability to which the final estimated quantity is subject to for measurement and payment.

Round final calculation to the nearest unit increment given as the plan reporting accuracy and show on plans. Rounding should follow generally accepted rules and be agreeable to those responsible for estimating the final estimated quantities.

Items in the table below can also be found in the Missouri Standard Specifications for Highway Construction

Item Number Plan Reporting Accuracy Units Item Description
Sec 202 – Removal of Roadways and Buildings
202-40.18 1 linear foot Removal of Miscellaneous ACM (Non-Friable)
202-40.43 1 sq. foot Removal of Miscellaneous ACM (Non-Friable)
Sec 206 – Excavation for Structures
206-10.00 5 cu. yard Class 1 Excavation
206-10.03 1 cu. yard Class 1 Excavation in Rock (*)
206-20.00 1 cu. yard Class 2 Excavation
206-20.03 1 cu. yard Class 2 Excavation in Rock (*)
206-33.00 5 cu. yard Class 4 Excavation
206-34.00 1 cu. yard Class 4 Excavation in Rock (*)
* Note: Use when cross-sections indicate rock will be encountered and quantity is more than 10 cu. Yard. If there is less than 10 cu. yards of total excavation in rock, no Excavation in Rock pay items should be listed in the Estimated Quantities. Excavation in rock will be paid in accordance with Sec 109. Check with Project Manager when computing this item.
206-36.00 1 linear foot Supplementary Foundation Test Holes (NX)
206-36.10 1 linear foot Supplementary Cored Holes
206-40.00 1 cu. yard Porous Backfill
206-55.00 1 lump sum Temporary Shoring
206-60.02 to
206-60.12
1 lump sum Cofferdams - Bent xx
Note: Use a separate pay item for each bent. Item numbers established for only Bent 2 thru Bent 12.
206-99.01 1 lump sum Misc.
206-99.02 1 each Misc.
206-99.03 1 linear foot Misc.
206-99.04 1 sq. foot Misc.
206-99.05 1 sq. yard Misc.
206-99.07 0.1 cu. yard Misc.
Sec 216 – Removals for Bridge Structures
216-05.00 1 lump sum Removal of Bridges
216-05.01 1 lump sum Match Marking and Storing Superstructure
216-10.00 1 sq. yard Scarification of Bridge Deck
Note: Do not use with concrete wearing surface removals.
216-10.01 1 sq. yard Total Surface Hydro Demolition
216-15.00 1 sq. foot Removal of Seal Coat or Polymer Wearing Surface
Note: Do not use for unbonded removal.
216-15.01 1 sq. foot Removal of Asphalt Wearing Surface
216-15.02 1 sq. foot Removal of Concrete Wearing Surface
Note: Use for all concrete wearing surfaces.
216-15.03 1 sq. foot Removal of Existing Deck Repair
Note: Use with Hydro demolition when required.
216-20.00 1 linear foot Removal and Storage of Existing Bridge Rail
216-25.00 1 sq. foot Removal of Existing Bridge Deck
216-30.00 1 sq. foot Partial Removal of Existing Bridge Deck
216-35.00 1 lump sum Partial Removal of Culvert Concrete
216-35.01 1 lump sum Partial Removal of Culvert-Bridge Concrete
216-35.02 1 lump sum Partial Removal of Substructure Concrete
216-40.00 1 linear foot Curb Removal
Note: Use for just removal of curbs including for thrie beam installation.
216-45.00 1 linear foot Removal of Existing Expansion Joint & Adjacent Concrete
Note: Also use concrete and reinforcing steel pay items for replacement of expansion joint system.
216-50.00 1 linear foot Removal of Existing Expansion Joint Seal or Sealant
Note: Also use Concrete and Reinforcing Steel pay items for replacement of expansion joint system.
216-55.00 1 lump sum Removal of Cathodic Protection System
216-99.01 1 lump sum Misc.
216-99.02 1 each Misc.
216-99.03 1 linear foot Misc.
216-99.04 1 sq. foot Misc.
216-99.05 1 sq. yard Misc.
Sec 403 – Asphaltic Concrete Pavement
403-10.50 1 sq. yard Optional Asphaltic Concrete Wearing Surface (Bridges)
Sec 407 – Tack Coat
407-10.05 1 gallon Tack Coat
Sec 409 – Seal Coat
409-10.48 1 gallon Emulsified Asphalt, Seal Coat
409-40.01 1 sq. yard Seal Coat Aggregate, Grade A1
409-40.11 1 sq. yard Seal Coat Aggregate, Grade B1
Sec 413 – Surface Treatments
413-33.00 1 sq. yard Optional Ultrathin Bonded Asphalt Wearing Surface (Bridges)
Sec 503 – Bridge Approach Slab
503-10.10A 1 sq. yard Bridge Approach Slab (Major)
503-10.11A 1 sq. yard Bridge Approach Slab (Minor)
Sec 505 – Bridge Deck Concrete Wearing Surface
505-00.01 1 sq. yard Optional Concrete Wearing Surface
505-00.02 1 sq. yard Optional Very Early Strength Concrete Wearing Surface
505-00.03 1 sq. yard Reinforced Concrete Wearing Surface
505-00.04 1 cu. yard Supplementary Wearing Surface Material
Note: Use with total surface hydro demolition to pay for monolithic deck repair.
505-10.00 1 sq. yard Low Slump Concrete Wearing Surface
Note: Use with SPM or SLE approval (typically only allowed as a choice with 505-00.01).
505-20.00 1 sq. yard Latex Modified Concrete Wearing Surface
505-30.00 1 sq. yard Silica Fume Concrete Wearing Surface
505-40.00 1 sq. yard Latex Modified Very Early Strength Concrete Wearing Surface
505-50.00 1 sq. yard CSA Cement Very Early Strength Concrete Wearing Surface
505-60.00 1 sq. yard Steel Fiber Reinforced Concrete Wearing Surface
505-70.00 1 sq. yard Polyester Polymer Concrete Wearing Surface
505-99.05 1 sq. yard Misc.
Sec 605 - Underdrainage
605-20.10A 1 linear foot Structural Underdrain
Sec 607 - Fencing
607-10.50 1 linear foot Chain-Link Fence (Retaining Walls)
607-10.54 1 linear foot (42 in.) Property Fence (Structures)
607-10.55 1 linear foot (60 in.) Property Fence (Structures)
607-10.56 1 linear foot (72 in.) Property Fence (Structures)
607-10.57 1 linear foot (84 in.) Property Fence (Structures)
607-10.58 1 linear foot (96 in.) Property Fence (Structures)
607-10.60 1 linear foot Pedestrian Fence (Structures)
607-10.65 1 linear foot (60 in.) Pedestrian Fence (Structures)
607-10.66 1 linear foot (72 in.) Pedestrian Fence (Structures)
607-10.67 1 linear foot (96 in.) Curved Top Pedestrian Fence (Structures)
607-10.68 1 linear foot (120 in.) Pedestrian Fence (Structures)
607-30.00 1 linear foot (30 in.) Decorative Pedestrian Fence (Structures)
607-30.01 1 linear foot (48 in.) Decorative Pedestrian Fence (Structures)
607-30.02 1 linear foot (60 in.) Decorative Pedestrian Fence (Structures)
607-30.03 1 linear foot (72 in.) Decorative Pedestrian Fence (Structures)
607-30.04 1 linear foot (96 in.) Decorative Pedestrian Fence (Structures)
607-99.03 1 linear foot Misc.
Sec 615 – Office for Engineer
615-10.05 1 lump sum Water Transportation for Engineer
Sec 623 – Polymer Products
623-00.01 1 sq. yard Optional Polymer Wearing Surface
623-30.00 1 sq. yard Epoxy Polymer Wearing Surface
623-40.00 1 cu. foot Polymer Concrete
623-50.00 1 sq. yard MMA Polymer Slurry Wearing Surface
623-99.05 1 sq. yard Misc.
Sec 701 – Drilled Shafts
701-11.00 0.1 linear foot Drilled Shafts (1 ft. 0 in. Dia.)
701-11.01 0.1 linear foot Drilled Shafts (1 ft. 6 in. Dia.)
701-11.02 0.1 linear foot Drilled Shafts (2 ft. 0 in. Dia.)
701-11.03 0.1 linear foot Drilled Shafts (2 ft. 6 in. Dia.)
701-11.04 0.1 linear foot Drilled Shafts (3 ft. 0 in. Dia.)
701-11.05 0.1 linear foot Drilled Shafts (3 ft. 6 in. Dia.)
701-11.06 0.1 linear foot Drilled Shafts (4 ft. 0 in. Dia.)
701-11.07 0.1 linear foot Drilled Shafts (4 ft. 6 in. Dia.)
701-11.08 0.1 linear foot Drilled Shafts (5 ft. 0 in. Dia.)
701-11.09 0.1 linear foot Drilled Shafts (5 ft. 6 in. Dia.)
701-11.10 0.1 linear foot Drilled Shafts (6 ft. 0 in. Dia.)
701-11.11 0.1 linear foot Drilled Shafts (6 ft. 6 in. Dia.)
701-11.12 0.1 linear foot Drilled Shafts (7 ft. 0 in. Dia.)
701-11.13 0.1 linear foot Drilled Shafts (7 ft. 6 in. Dia.)
701-11.14 0.1 linear foot Drilled Shafts (8 ft. 0 in. Dia.)
701-11.15 0.1 linear foot Drilled Shafts (8 ft. 6 in. Dia.)
701-11.16 0.1 linear foot Drilled Shafts (9 ft. 0 in. Dia.)
701-11.17 0.1 linear foot Drilled Shafts (9 ft. 6 in. Dia.)
701-11.18 0.1 linear foot Drilled Shafts (10 ft. 0 in. Dia.)
701-12.00 0.1 linear foot Rock Sockets (1 ft. 0 in. Dia.)
701-12.01 0.1 linear foot Rock Sockets (1 ft. 6 in. Dia.)
701-12.02 0.1 linear foot Rock Sockets (2 ft. 0 in. Dia.)
701-12.03 0.1 linear foot Rock Sockets (2 ft. 6 in. Dia.)
701-12.04 0.1 linear foot Rock Sockets (3 ft. 0 in. Dia.)
701-12.05 0.1 linear foot Rock Sockets (3 ft. 6 in. Dia.)
701-12.06 0.1 linear foot Rock Sockets (4 ft. 0 in. Dia.)
701-12.07 0.1 linear foot Rock Sockets (4 ft. 6 in. Dia.)
701-12.08 0.1 linear foot Rock Sockets (5 ft. 0 in. Dia.)
701-12.09 0.1 linear foot Rock Sockets (5 ft. 6 in. Dia.)
701-12.10 0.1 linear foot Rock Sockets (6 ft. 0 in. Dia.)
701-12.11 0.1 linear foot Rock Sockets (6 ft. 6 in. Dia.)
701-12.12 0.1 linear foot Rock Sockets (7 ft. 0 in. Dia.)
701-12.13 0.1 linear foot Rock Sockets (7 ft. 6 in. Dia.)
701-12.14 0.1 linear foot Rock Sockets (8 ft. 0 in. Dia.)
701-12.15 0.1 linear foot Rock Sockets (8 ft. 6 in. Dia.)
701-12.16 0.1 linear foot Rock Sockets (9 ft. 0 in. Dia.)
701-12.17 0.1 linear foot Rock Sockets (9 ft. 6 in. Dia.)
701-13.00 1 each Video Camera Inspection
701-14.00 0.1 linear foot Foundation Inspection Holes
701-16.00 1 each Sonic Logging Testing
701-17.00 1 each Drilled Shaft Load Tests
701-99.01 1 lump sum Misc.
701-99.02 1 each Misc.
701-99.03 0.1 linear foot Misc.
Sec 702 – Load-Bearing Piles
702-10.10 1 linear foot Structural Steel Piles (10 in.)
702-10.12 1 linear foot Structural Steel Piles (12 in.)
702-10.14 1 linear foot Structural Steel Piles (14 in.)
702-11.14 1 linear foot Cast-In-Place Concrete Piles (14 in.)
702-11.16 1 linear foot Cast-In-Place Concrete Piles (16 in.)
702-11.20 1 linear foot Cast-In-Place Concrete Piles (20 in.)
702-11.24 1 linear foot Cast-In-Place Concrete Piles (24 in.)
702-12.10 1 linear foot Galvanized Structural Steel Piles (10 in.)
702-12.12 1 linear foot Galvanized Structural Steel Piles (12 in.)
702-12.14 1 linear foot Galvanized Structural Steel Piles (14 in.)
702-13.14 1 linear foot Galvanized Cast-In-Place Concrete Piles (14 in.)
702-13.16 1 linear foot Galvanized Cast-In-Place Concrete Piles (16 in.)
702-13.20 1 linear foot Galvanized Cast-In-Place Concrete Piles (20 in.)
702-13.24 1 linear foot Galvanized Cast-In-Place Concrete Piles (24 in.)
702-30.00 1 linear foot Probe Piles
702-40.00 1 each Static Load Test Piles
702-50.01 1 each Dynamic Pile Testing
702-50.02 1 each Pile Wave Analysis
702-50.03 1 linear foot Pilot Hole
702-50.04 1 each Dynamic Pile Restrike Testing
702-60.00 1 linear foot Pre-Bore for Piling
Note: Compute this to nearest foot for each hole.
702-70.00 1 each Pile Point Reinforcement
702-99.02 1 each Misc.
702-99.03 1 linear foot Misc.
Sec 703 – Concrete Masonry Construction
703-10.04 1 sq. yard Diamond Grinding
703-10.05 1 sq. yard Transverse Diamond Grooving
703-20.02 0.1 cu. yard Class B Concrete (Misc)
703-20.03 0.1 cu. yard Class B Concrete (Substructure)
703-20.09 0.1 cu. yard Class B Concrete (Retaining Walls)
703-20.25 1 each Deadman Anchorage Assembly
703-30.01 0.1 cu. yard Seal Concrete
703-30.09 1 lump sum Aesthetic Concrete Stain
703-30.13 1 sq. yard Penetrating Concrete Sealer
703-40.01 0.1 cu. yard Class B-1 Concrete
703-40.02 0.1 cu. yard Class B-1 Concrete (Superstructure on Steel and Concrete)
703-40.03 0.1 cu. yard Class B-1 Concrete (Substructure)
703-40.04 0.1 cu. yard Class B-1 Concrete (Superstructure on Steel)
703-40.05 0.1 cu. yard Class B-1 Concrete (Superstructure Voided Slabs)
703-40.06 0.1 cu. yard Class B-1 Concrete (Superstructure Concrete Box Girder)
703-40.07 0.1 cu. yard Class B-1 Concrete (Superstructure Concrete Tee Girder)
703-40.08 0.1 cu. yard Class B-1 Concrete (Superstructure Solid Slab)
703-40.09 0.1 cu. yard Class B-1 Concrete (Retaining Walls)
703-40.10 0.1 cu. yard Class B-1 Concrete (Superstructure Concrete on I-Girder)
703-40.20 0.1 cu. yard Class B-1 Concrete (Superstructure)
703-40.30 0.1 cu. yard Class B-1 Concrete (Barriers)
703-40.40 0.1 cu. yard Class B-1 Concrete (Culverts-Bridge)
703-40.41 0.1 cu. yard Class B-1 Concrete (Culverts)
703-42.02 0.1 cu. yard Class B-2 Concrete (Superstructure on Steel and Concrete)
703-42.04 0.1 cu. yard Class B-2 Concrete (Superstructure on Steel)
703-42.05 0.1 cu. yard Class B-2 Concrete (Superstructure Voided Slabs)
703-42.06 0.1 cu. yard Class B-2 Concrete (Superstructure Concrete Box Girder)
703-42.07 0.1 cu. yard Class B-2 Concrete (Superstructure Concrete Tee Girder)
703-42.08 0.1 cu. yard Class B-2 Concrete (Superstructure Solid Slab)
703-42.10 0.1 cu. yard Class B-2 Concrete (Superstructure Concrete on I Girder)
703-42.11 0.1 cu. yard Class B-2 Concrete (Superstructure Concrete on Box Girder)
703-42.12 1 sq. yard Slab on Steel
703-42.13 1 sq. yard Slab on Concrete I-Girder
703-42.14 0.1 cu. yard Class B-2 Concrete
703-42.15 1 linear foot Type B Barrier
703-42.16 1 linear foot Type H Barrier
703-42.18 1 sq. yard Slab on Concrete Bulb-Tee Girder
703-42.19A 1 linear foot Type D Barrier
703-42.20 1 sq. yard Slab on Semi-Deep Abutment
703-42.21 1 sq. yard Slab on Concrete NU-Girder
703-42.22 1 sq. yard Slab on Concrete Beam
Note: For spread box beams and spread voided slab beams.
703-42.26 1 sq. yard Slab on Concrete Adjacent Beam
Note: For double-tee girders and when specified on the Design Layout for solid slab beams, adjacent box beams and adjacent voided slab beams.
703-42.30 0.1 cu. yard Class B-2 Concrete (Post-Tensioned Wearing Surface)
703-42.31 1 sq. yard Slab on Steel (with Transparent Forms)
703-42.32 1 sq. yard Slab on Concrete I-Girder (with Transparent Forms)
703-42.33 1 sq. yard Slab on Concrete Bulb-Tee Girder (with Transparent Forms)
703-42.34 1 sq. yard Slab on Concrete NU-Girder (with Transparent Forms)
703-42.35 1 sq. yard Slab on Concrete Beam (with Transparent Forms)
703-44.10 1 linear foot Type A Barrier
703-44.11 1 linear foot Type C Barrier
703-44.12 1 linear foot Type A Barrier Transition
703-44.13 1 linear foot Type C Barrier Transition
703-44.20 1 sq. foot Raised Median Barrier
703-44.30 1 sq. foot Sidewalk (Bridges)
703-45.35 1 linear foot Curb Modification
703-46.00 1 linear foot Curb Blockout
703-46.10 1 linear foot Corral Curb
703-46.20 1 sq. yard Form Liners
703-46.30 1 linear foot Concrete Curb (Bridge Rail)
703-60.00A 0.1 cu. yard Class A-1 Concrete
703-99.01 1 lump sum Misc.
703-99.02 1 each Misc.
703-99.03 1 linear foot Misc.
703-99.04 1 sq. foot Misc.
703-99.05 1 sq. yard Misc.
703-99.07 0.1 cu. yard Misc.
Sec 704 – Concrete Masonry Repair
704-01.01 1 sq. foot Substructure Repair (Formed)
704-01.02 1 sq. foot Substructure Repair (Unformed)
704-01.03 1 sq. foot Superstructure Repair (Unformed)
704-01.04 50* sq. foot Half-Sole Repair
704-01.06 50* sq. foot Full Depth Repair
704-01.07 1 linear foot Slab Edge Repair (Bridges)
704-01.08 50* sq. foot Modified Deck Repair
704-01.10 1 linear foot Epoxy Pressure Injecting
704-01.11 1 each Deck Girder End Repair
704-01.12 50* sq. foot Deck Repair with Void Tube Replacement
704-01.13 1 sq. foot Cleaning and Epoxy Coating
*Note: Round quantity up to nearest multiple of 50 sq. ft.
704-01.63 1 sq. yard Concrete Crack Filler
704-01.64 1 sq. foot Fiber Reinforced Polymer Wrap
704-99.01 1 lump sum Misc.
704-99.02 1 each Misc.
704-99.03 1 linear foot Misc.
704-99.04 1 sq. foot Misc.
704-99.05 1 sq. yard Misc.
704-99.07 0.1 cu. yard Misc.
Sec 705 – Prestressed Concrete Members for Bridges
705-60.00 1 linear foot Type 2 (32 in.), Prestressed Concrete I-Girder
705-60.01 1 linear foot Type 3 (39 in.), Prestressed Concrete I-Girder
705-60.02 1 linear foot Type 4 (45 in.), Prestressed Concrete I-Girder
705-60.03 1 linear foot Type 6 (54 in.), Prestressed Concrete I-Girder
705-60.10 1 linear foot Type 8 (63 in.), Prestressed Concrete Bulb-Tee Girder
705-60.11 1 linear foot Type 7 (72 in.), Prestressed Concrete Bulb-Tee Girder
705-60.21 1 linear foot NU 35, Prestressed Concrete NU-Girder
705-60.22 1 linear foot NU 43, Prestressed Concrete NU-Girder
705-60.23 1 linear foot NU 53, Prestressed Concrete NU-Girder
705-60.24 1 linear foot NU 63, Prestressed Concrete NU-Girder
705-60.25 1 linear foot NU 70, Prestressed Concrete NU-Girder
705-60.26 1 linear foot NU 78, Prestressed Concrete NU-Girder
705-60.30 1 linear foot 11 in., Prestressed Concrete Solid Slab Beam
705-60.40A 1 linear foot 15 in., Prestressed Concrete Spread Voided Slab Beam
705-60.42A 1 linear foot 18 in., Prestressed Concrete Spread Voided Slab Beam
705-60.43A 1 linear foot 21 in., Prestressed Concrete Spread Voided Slab Beam
705-60.45 1 linear foot 15 in., Prestressed Concrete Adjacent Voided Slab Beam
705-60.47 1 linear foot 18 in., Prestressed Concrete Adjacent Voided Slab Beam
705-60.48 1 linear foot 21 in., Prestressed Concrete Adjacent Voided Slab Beam
705-60.49 1 linear foot 21 in., Prestressed Concrete Spread Box Beam
705-60.50A 1 linear foot 27 in., Prestressed Concrete Spread Box Beam
705-60.51A 1 linear foot 33 in., Prestressed Concrete Spread Box Beam
705-60.52A 1 linear foot 39 in., Prestressed Concrete Spread Box Beam
705-60.53A 1 linear foot 42 in., Prestressed Concrete Spread Box Beam
705-60.54 1 linear foot 21 in., Prestressed Concrete Adjacent Box Beam
705-60.55 1 linear foot 27 in., Prestressed Concrete Adjacent Box Beam
705-60.56 1 linear foot 33 in., Prestressed Concrete Adjacent Box Beam
705-60.57 1 linear foot 39 in., Prestressed Concrete Adjacent Box Beam
705-60.58 1 linear foot 42 in., Prestressed Concrete Adjacent Box Beam
705-60.60 1 linear foot 16 in., Prestressed Concrete Double-Tee Girder
705-60.61 1 linear foot 22 in., Prestressed Concrete Double-Tee Girder
705-60.62 1 linear foot 30 in., Prestressed Concrete Double-Tee Girder
705-60.65 1 linear foot 17 in., Prestressed Concrete Spread Box Beam
705-60.66 1 linear foot 17 in., Prestressed Concrete Adjacent Box Beam
705-99.01 1 lump sum Misc.
705-99.02 1 each Misc.
705-99.03 1 linear foot Misc.
705-99.04 1 sq. foot Misc.
705-99.05 1 sq. yard Misc.
Sec 706 – Reinforcing Steel for Concrete Structures
706-10.00 10 pound Reinforcing Steel
706-10.20 10 pound Reinforcing Steel (Culverts-Bridge)
706-10.30 10 pound Reinforcing Steel (Culverts)
706-10.40 10 pound Reinforcing Steel (Retaining Wall)
706-10.60 10 pound Reinforcing Steel (Bridges)
706-10.70 1 each Mechanical Bar Splice
Note: Use when the total number of mechanical bar splices on a set of plans is 50 or greater not including any required in the approach slabs.
706-99.11 10 pound Misc.
Sec 707 – Conduit System on Structure
707-10.00 1 lump sum Conduit System on Structure
707-10.30 1 lump sum Conduit System on Structure (Telephone)
707-10.40 1 lump sum Cathodic Protection System
707-99.01 1 lump sum Misc.
707-99.02 1 each Misc.
Sec 710 – Epoxy Coated Reinforcing Steel
710-10.00 10 pound Reinforcing Steel (Epoxy Coated)
710-99.11 10 pound Misc.
Sec 711 – Protective Coatings for Exposed Concrete Surfaces
711-01.00 1 lump sum Protective Coating – Concrete Bents and Piers (Urethane) Note: Tar appearance
711-02.00 1 lump sum Protective Coating – Concrete Bents and Piers (Epoxy) Note: Clear appearance
711-03.00 1 lump sum Concrete and Masonry Protection System
711-04.00 1 lump sum Sacrificial Graffiti Protection System
711-05.00 1 lump sum Temporary Coating – Concrete Bents and Piers (Weathering Steel)
711-10.00 1 sq. yard Waterproofing
711-10.01 1 sq. yard Waterproofing Membrane
711-99.01 1 lump sum Misc.
711-99.04 1 sq. foot Misc.
711-99.05 1 sq. yard Misc.
Sec 712 – Structural Steel Construction
712-09.00 1 linear foot Expansion Device (Finger Plate)
712-09.15 1 linear foot Expansion Device (Flat Plate)
712-10.00 10 pound Fabricated Structural Carbon Steel (Misc.)
712-10.10 10 pound Fabricated Structural Carbon Steel (I-Beam)
712-10.20 10 pound Fabricated Structural Carbon Steel (Plate Girder)
712-10.30 10 pound Fabricated Structural Carbon Steel (Trusses)
712-10.40 10 pound Fabricated Structural Carbon Steel (Concrete)
712-10.50 10 pound Fabricated Structural Carbon Steel (Box Girder)
712-10.60 1 lump sum Fabricated Sign Support Brackets
712-11.00 10 pound Fabricated Structural Low Alloy Steel (Misc.)
712-11.11 10 pound Fabricated Structural Low Alloy Steel (I-Beam) A709, Grade 50
712-11.13 10 pound Fabricated Structural Low Alloy Steel (I-Beam) A709, Grade 50W
712-11.21 10 pound Fabricated Structural Low Alloy Steel (Plate Girder) A709, Grade 50
712-11.22 10 pound Fabricated Structural Low Alloy Steel (Plate Girder) A709, Grade 50W
712-11.23 10 pound Fabricated Structural Low Alloy Steel (Plate Girder) A709 Grade HPS70W
712-11.24 10 pound Fabricated Structural Low Alloy Steel (Plate Girder) A709 Grade HPS50W
712-11.30 10 pound Fabricated Structural Low Alloy Steel (Trusses)
712-11.40 10 pound Fabricated Structural Low Alloy Steel (Concrete)
712-11.51 10 pound Fabricated Structural Low Alloy Steel (Box Girder) A709, Grade 50
712-11.52 10 pound Fabricated Structural Low Alloy Steel (Box Girder) A709, Grade 50W
712-11.59 1 each Shear Connectors
712-11.60 1 sq. foot Steel Grid Floor (Half Concrete Filled)
712-11.61 1 sq. foot Steel Grid Floor (Concrete Filled)
712-12.50 1 lump sum Strengthening Existing Beams
712-12.51 1 each Hinge Modification
712-13.00 10 pound Fabricated Structural Steel Bearings
712-20.00 10 pound Carbon Steel Castings
712-22.00 10 pound Gray Iron Castings
712-23.00 1 linear foot Bridge Rail (Two Tube Structural Steel)
712-30.00 1 each Steel Bar Dam
712-31.00 1 each Cleaning and Coating Existing Bearings
712-31.10 1 each Bearing Removal for Inspection
712-31.15 1 each Surface Finishing Bearing Rocker
712-31.20 1 each Cleaning, Lubricating and Coating Bearing
712-31.30 1 each Rehabilitate Bearing
712-31.40 10 pound New Bearing Materials
712-31.50 1 each Anchor Bolt Replacement
712-32.00 1 each Removing, Coating and Reinstalling Light Standards (Bridges)
712-32.10 1 each Earthquake Restrainer Assemblies
712-32.50 1 each Rivet Removal and Replacement
712-33.00 1 lump sum Existing Diaphragm Connections to Flange
712-33.01 1 each Steel Intermediate Diaphragm for P/S Concrete Girders
712-35.00 1 linear foot Railing for Steps
712-36.10 1 each Slab Drain
712-36.11 1 each Slab Drain with Grate
712-36.20 1 lump sum Drainage System (On Structure)
712-51.00 1 lump sum Surface Preparation for Recoating Structural Steel
712-51.01 1 lump sum Surface Preparation for Overcoating Structural Steel (System G)
712-51.02 1 lump sum Surface Preparation for Applying Epoxy-Mastic Primer
712-51.09 1 lump sum Field Application of Organic Zinc Primer
712-51.10 1 lump sum Field Application of Inorganic Zinc Primer
712-51.11 1 lump sum Intermediate Field Coat (System G)
712-51.12 1 lump sum Finish Field Coat (System G)
712-51.13 1 lump sum Intermediate Field Coat (System H)
712-51.14 1 lump sum Finish Field Coat (System H)
712-51.15 1 lump sum Finish Field Coat (System I)
712-52.00 100 sq. foot Surface Preparation for Recoating Structural Steel
712-52.01 100 sq. foot Surface Preparation for Overcoating Structural Steel (System G)
712-52.02 100 sq. foot Chloride Remediation Surface Preparation
712-52.09 100 sq. foot Field Application of Organic Zinc Primer
712-52.10 100 sq. foot Field Application of Inorganic Zinc Primer
712-53.15A 0.1 ton Intermediate Field Coat (System G)
712-53.20A 0.1 ton Finish Field Coat (System G)
712-53.35A 0.1 ton Intermediate Field Coat (System H)
712-53.40A 0.1 ton Finish Field Coat (System H)
712-53.46 0.1 ton Finish Field Coat (System I)
712-53.65A 100 sq. foot Intermediate Field Coat (System G)
712-53.70A 100 sq. foot Finish Field Coat (System G)
712-53.85A 100 sq. foot Intermediate Field Coat (System H)
712-53.90A 100 sq. foot Finish Field Coat (System H)
712-53.96 100 sq. foot Finish Field Coat (System I)
712-59.60 1 lump sum Aluminum Epoxy-Mastic Primer
712-59.61 1 lump sum Gray Epoxy-Mastic Primer
712-60.00 1 linear foot Non-Destructive Testing
712-99.01 1 lump sum Galvanizing Structural Steel
712-99.02 1 each Misc.
712-99.03 1 linear foot Misc.
712-99.04 1 sq. foot Misc.
712-99.05 1 sq. yard Misc.
712-99.10 0.1 ton Misc.
712-99.11 10 pound Misc.
Sec 713 – Thrie Beam for Bridge Guardrail
713-30.00 1 linear foot Bridge Guardrail (W-Beam)
713-40.00 1 linear foot Bridge Guardrail (Thrie Beam)
713-99.03A 1 linear foot Misc.
Sec 715 – Vertical Drain at End Bents
715-10.01 1 each Vertical Drain at End Bents
715-99.02 1 each Misc.
Sec 716 – Neoprene Bearings
716-10.00 1 each Plain Neoprene Bearing Pad
716-10.01 1 linear foot Plain Neoprene Bearing Pad
716-10.02 1 each Laminated Neoprene Bearing Pad
716-10.03 1 each Laminated Neoprene Bearing Pad (Tapered)
716-20.00 1 each Laminated Neoprene Bearing Pad Assembly
716-30.00 1 each Type N PTFE Bearing
716-40.00 1 each POT Bearing
716-99.01 1 lump sum Misc.
716-99.02 1 each Misc.
716-99.03 1 linear foot Misc.
Sec 717 – Flexible Joint Systems
717-00.01 1 linear foot Alternate Expansion Joint System
717-10.01 1 linear foot Preformed Compression Seal Expansion Joint System
717-10.02 1 linear foot Preformed Compression Seal
Note: Use for seal only, no armor.
717-20.01 1 linear foot Strip Seal Expansion Joint System
717-20.02 1 linear foot Strip Seal
Note: Use for seal only, no armor.
717-20.53 1 linear foot Open Cell Foam Joint System
717-20.54 1 linear foot Open Cell Foam Joint Seal
Note: Use for seal only, no armor.
717-30.01 1 linear foot Silicone Expansion Joint Sealant System
Note: See EPG 751.13.1.5 Silicone Seal Expansion Joint System.
717-30.02 1 linear foot Silicone Expansion Joint Sealant
Note: See EPG 751.13.1.5 Silicone Seal Expansion Joint System.
Use for silicone sealant only, no armor.
717-40.01 1 linear foot Preformed Silicone or EPDM Expansion Joint System
717-40.02 1 linear foot Preformed Silicone or EPDM Expansion Joint Seal
Note: Use for seal only, no armor.
717-99.03 1 linear foot Misc.
Sec 718 – Temporary Bridge
718-10.10 1 lump sum Furnishing Superstructure
718-10.11 1 lump sum Partial Furnishing of Superstructure
718-10.20 1 lump sum Transporting and Erecting Superstructure
718-10.30 1 lump sum Removing and Storing Superstructure
718-99.01 1 lump sum Misc.
718-99.02 1 each Misc.
Sec 720 – Mechanically Stabilized Earth Wall Systems
720-10.00 1 sq. foot Mechanically Stabilized Earth Wall Systems
720-11.00 1 sq. yard Form Liners for MSE Wall Systems
720-12.00 1 cu. yard Select Granular Backfill for Structural Systems
720-13.00 1 each Pipe Pile Spacers
720-14.00 1 lump sum Temporary MSE Wall System
720-99.04 1 sq. foot Misc.
720-99.05 1 sq. yard Misc.
Sec 901 – Highway Lighting
901-93.00 1 lump sum Navigation Lighting System
901-93.01 1 lump sum Bridge Lighting

751.6.2 Computation of Estimated Quantities

All estimated quantities shall be carried to the degree of accuracy specified in the Index of Estimated Quantities. All quantities shall be listed on the plans in the order and worded exactly as shown in the Index of Estimated Quantities.

Two sets of quantity computations shall be independently performed and then agreed upon by the individuals performing the computations. Both sets of computations shall be bound together and submitted with the design plans.

In order to satisfy funding requirements on projects that add capacity to the Interstate System, the quantities that are attributed to the addition of capacity shall be reported separately from the remaining quantities in the submitted computations. Quantities shall not be shown separately on the bridge plans.

751.6.2.1 Weight of Bolts and Shear Connectors

Refer to AISC Manual of Steel Construction or ASTM F3125 for weight and dimensions of high strength bolts and washers. When calculating the weight of high strength bolts in structural connections, the following simplified weights may be used. These values include the weight of a regular hex head, one heavy hex nut, one washer, and the portion of the bolt projecting beyond the grip (washer thickness + nut thickness + 1/4“).


Weight of High Strength Bolts
Bolt Size
Diameter (inch)
Weight per
100 Bolts (pounds)
5/8 40
3/4 65
7/8 95
1 135
1-1/8 180
1-1/4 245
1-3/8 352
1-1/2 400


Weight of Shear Connectors
  Weight In Place Per 100 Studs
Stud Dia. 4" 5" 6" 7"
3/4" 63 75 88 100
7/8" 81 98 115 132

751.6.2.2 Piles

Estimated quantities for piles, steel or concrete, shall be compiled as the entire length of the piles used, including the length of pile embedded in the pile cap or footing, measured to the nearest foot for each pile.

751.6.2.3 Pre-bore for Piling

Pre-bore is required when fill exceeds five feet as described in Sec 702 or when specified on the Design Layout. Pre-bore is also required through earth plugs. Pre-bore is computed as the length of pile measured from the bottom of the pile cap or footing to the natural ground line or as directed on the Design Layout rounded to the nearest foot for each hole.

751.6.2.4 Drilled Shafts

Drilled shafts, rock sockets and reinforcing steel quantity will be measured in accordance with Sec 701. Video camera inspection quantity will be calculated one for each drilled shaft. Foundation inspection hole quantities will be from the top of rock socket to the greater of either 10 feet or twice the diameter of the rock socket below the anticipated bottom of rock socket for each rock socket. Sonic logging testing shall be performed on all drilled shafts and rock sockets. Drilled shafts for high mast lighting will not require sonic logging testing.

751.6.2.5 Concrete

The volume of concrete shall be calculated to the nearest 0.1 cubic yard, except where reported in the table of Estimated Quantities for Slab, where concrete is rounded to the nearest whole cubic yard (see EPG 751.50, Note B3.21). Do not deduct for volume of concrete displaced by reinforcing steel or HP piling. When CIP piles are used, the displaced concrete volume should be deducted.

751.6.2.6 Polymer Concrete

The volume of polymer concrete shall be calculated to the nearest 1.0 cubic foot. Do not deduct for volume of concrete displaced by reinforcing steel.

751.6.2.7 Non-Destructive Testing (NDT) for Cover Plates

NDT shall be required for all top cover plates when a bridge is to be redecked. Required NDT length shall be computed for pay and, if necessary for clarity, details can be shown on the plans (for example, to show unusual NDT locations not covered elsewhere). The length of weld to be tested and the base metal, 1” either side of the weld, shall be cleaned of all rust prior to the testing. On cover plates with square ends, the weld shall be tested 1” from each corner along the ends of the cover plate plus 6” back along the side from each corner of the plate. On cover plates with tapered ends, the weld shall be tested along the end of cover plate, along tapered edges and 6” back along cover plate from end of taper.

In the rare case that there are bottom flange cover plates, it is the responsibility of the SPM or SLE to coordinate with district bridge engineer or review visual records and field inspection notes and decide if these plates need to be tested. This should include only welded cover plate ends that terminate in a tension zone. If cover plates terminate at the inflection point or past it, there is a small chance that the bottom flange cover plate welds would need to be tested. (Rarely, other areas of cover plate welds could be tested based on deteriorated conditions as reported from the field on the Structural Rehabilitation Checklist.)

751.6.2.8 Temporary Shoring or Temporary MSE Wall System

When temporary shoring or temporary MSE wall is required, it shall be reported as a lump sum item on the bridge plans. In addition, the estimated area of temporary shoring or temporary MSE wall shall be computed to the nearest square foot and recorded only in the quantity folder. Embedment of temporary shoring shall be taken as one third of the exposed height of the shoring for the purpose of estimating the shoring area. The bottom of temporary MSE wall shall be taken as the lower of the top of permanent wall levelling pad or bottom of improved foundation. For temporary shoring use 206-55.00 pay item and for temporary MSE wall system use 720-14.00 pay item (EPG 751.6.1 Index of Quantities).

751.6.2.9 MSE Retaining Walls

Quantities for Mechanically Stabilized Earth Wall Systems are to be calculated based on the vertical face of the wall system as shown on the plans. The payment for furnishing and fabricating the concrete facing elements, excavation and installing the leveling pad, furnishing, and installing the soil reinforcement, furnishing, and placing select granular backfill for structural systems, furnishing other incidentals related to the wall system, and erecting the wall system complete-in-place, will be considered completely covered by the contract unit price for Mechanically Stabilized Earth Wall Systems per square foot. The use of the Select Granular Backfill for Structural Systems pay item will not be required. For permanent MSE wall systems use 720-10.00 pay item (EPG 751.6.1 Index of Quantities).

751.6.2.10 Bridge Slabs

The gross area of concrete slabs is used in the Estimated Quantities table and shall be estimated to the nearest square yard longitudinally from end of slab to end of slab and transversely from out to out of the bridge slab. This shall include all expansion gaps within these limits.

The actual volume of concrete is used in the table of slab quantities for the purpose of preparing the cost estimate and is given on the plans as an aid to the contractor. The concrete on top of the backwall at end bents for expansion joint systems shall be included in this volume (see Note B1.7). Concrete shall be estimated to the nearest cubic yard instead of 0.1 cubic yard due to variances and assumptions used in this estimate (see Note B3.21). Reinforcing steel shall be estimated to the nearest 10 pounds.

751.6.2.11 Structural Steel Protective Coatings (Non-weathering Steel)

The protective coating, as specified on the Design Layout, shall be System G, H or I with the color being gray or brown. The coating color shall be specified on the Design Layout. The following gives pay item guidelines for most bridges.

Coating New Multi-Girder/Beam Bridges

Intermediate Field Coat and Finish Field Coat (System G, H or I) (Gray or Brown) - The quantity shall be computed to the nearest one hundred square foot of structural steel to be field coated. The area computations do not include bearings, diaphragms, stiffeners and all other miscellaneous steel within the limits of the field coatings.

1. Bridges over Roadways (does not include over Railroads)

The intermediate field coat for beam and girder spans shall be applied to the surfaces of all structural steel except those surfaces to be in contact with concrete shall not receive the intermediate coat. The intermediate coat shall also be applied to the bearings, except where bearings will be encased in concrete.

The finish field coat for beam and girder spans shall include the facia girders or beams. The limits of the facia girders or beams shall include the bottom of the top exterior flanges, the top of the bottom exterior flanges, the exterior web area, the exterior face of the top and bottom flanges, and the bottom of the bottom flange. Areas of steel to be in contact with concrete shall not receive the finish coat. The finish coat shall also be applied to the exterior bearings, except where bearings will be encased in concrete.

The surfaces of all structural steel located under expansion joints of beam and girder spans shall be field coated with intermediate and finish coats for a distance of one and a half times the girder depth, but not less than 10 feet from the center line of the joint. Within this limit, the items to be field coated shall include all surfaces of beams, girders, bearings, diaphragms, stiffeners and miscellaneous structural steel items. Areas of steel to be in contact with concrete shall not receive the field coats. The limits of the field coatings shall be masked to provide crisp, straight lines and to prevent overspray on adjacent areas.

When System I finish field coat is specified on the plans with System G intermediate coat, System I finish field coat quantity will be figured the same as above for the finish field coat. System G intermediate coat with System I finish field coat will be as above for the intermediate field coat except that the area of the System I finish field coat will not be included in the System G intermediate field coat area. When the plans state System I finish field coat shall be substituted for System G intermediate coat, System I finish field coat quantity will be figured for all girder surfaces as discussed above for intermediate field coat area.

New Non-Weathering Bridge Over Roadway
751.6.2.11-Typical Roadway.jpg
751.6.2.11-Deck Joints Roadway.jpg
Typical Coating (System G) Coating Near Deck Joints (System G)

2. Bridges over Streams and Bridges over Railroads

The field coatings (including intermediate and finish coats) for beam and girder spans shall include the facia girders or beams. The limits of the facia girders or beams shall include the bottom of the top exterior flanges, the top of the bottom exterior flanges, the exterior web area, the exterior face of the top and bottom flanges, and the bottom of the bottom flange. Areas of steel to be in contact with concrete shall not receive the field coats. The field coatings shall also be applied to the exterior bearings, except where bearings will be encased in concrete. The interior beams or girders shall only have the prime coat applied with no other field coatings required.

The surfaces of all structural steel located under expansion joints of beam and girder spans shall be field coated with intermediate and finish coats for a distance of one and a half times the girder depth, but not less than 10 feet from the center line of the joint. Within the limit, the items to be field coated shall include all surfaces of beams, girders, bearings, diaphragms, stiffeners and miscellaneous structural steel items. Areas of steel to be in contact with concrete shall not receive the field coats. The limits of the field coatings shall be masked to provide crisp, straight lines and to prevent overspray on adjacent areas.

When System I is specified, the intermediate field coat will not be required.

New Non-Weathering Bridge Over Stream or Railroad
751.6.2.11-Typical Stream RR.jpg
751.6.2.11-Deck Joints Stream RR.jpg
Typical Coating (System G) Coating Near Deck Joints (System G)

Coating New Truss Bridges or Other Unusual Structures

Intermediate Field Coat and Finish Field Coat (System G, H or I) (Gray or brown) - The quantity shall be computed as a lump sum quantity.

All structural steel for truss or steel box girder spans shall be field coated with intermediate and finish coats, except the area of steel to be in contact with concrete and intermediate field coat is not required when System I is specified.

Recoating Existing Multi-Girder/Beam Bridges

Quantities shall be computed to the nearest one hundred square feet of structural steel to be prepared or coated. The area computations do not include bearings, diaphragms, stiffeners and all other misc. steel within the limits of surface preparation or field coatings.

1. Surface Preparation for Recoating Structural Steel - Preparation shall include the surfaces of all structural steel except areas to be in contact with concrete.

2. Field Application of Inorganic or Organic Zinc Primer - Coverage shall meet the same requirements of Surface Preparation for Recoating Structural Steel.

3. Intermediate Field Coat (System G or H) (Gray or Brown) - Coverage shall meet the same requirements as new multi-girder/beam bridges.

4. Finish Field Coat (System G, H or I) (Gray or Brown) - Coverage shall meet the same requirements as new multi-girder/beam bridges.

Existing Non-Weathering Bridge
751.6.2.11-Recoating Roadway.jpg
751.6.2.11-Recoating Stream RR.jpg
Typical Recoating Over Roadway (System G) Typical Recoating Over Stream or Railroad (System G)
751.6.2.11-Recoating Deck Joints.jpg
Recoating Near Deck Joints (System G)

Recoating Existing Truss Bridges or other Unusual Structures

Quantities shall be computed as lump sum quantities. The approximate weight of steel shall be shown to the nearest ton in the contract documents.

1. Surface Preparation for Recoating Structural Steel - Preparation shall include the surfaces of all structural steel except areas to be in contact with concrete.

2. Field Application of Inorganic or Organic Zinc Primer – Coverage shall meet the same requirements of Surface Preparation for Recoating Structural Steel.

3. Intermediate Field Coat (System G or H) (Gray or Brown) – Coverage shall meet the same requirements as new truss bridges.

4. Finish Field Coat (System G, H or I) (Gray or Brown) – Coverage shall meet the same requirements as new truss bridges.

Overcoating Existing Multi-Girder/Beam Bridges

Quantities shall be computed to the nearest one hundred square feet of structural steel to be prepared or overcoated except as noted below. The area computations do not include bearings, diaphragms, stiffeners and all other misc. steel within the limits of surface preparation or field coatings. Partial overcoating of steel structures is allowed and the areas of partial overcoating should be clearly indicated shown on the plans.

1. Surface Preparation for Overcoating Structural Steel (System G) - Preparation shall include the surfaces of all structural steel except areas to be in contact with concrete.

2. Intermediate Field Coat (System G) - Coverage shall meet the same requirements as Surface Preparation for Overcoating Structural Steel (System G).

3. Finish Field Coat (System G) - Coverage shall meet the same requirements as new bridges.

751.6.2.11-Overcoating Existing Bridge.jpg
Overcoating Existing Non-Weathering Bridge (System G)

Limits of Paint Overlap

Refer to EPG 751.50 Note A4a1.24. The figure below with note is available in a CADD cell.

Part Elev Paint Overlap 11-3-23.png

751.6.2.12 Structural Steel Protective Coatings (Weathering Steel)

Coating New Multi-Girder/Beam Bridges, Truss Bridges or other Unusual Structures

There will not be a quantity item for coating weathering steel. The cost of coating weathering steel structures will be considered completely covered by the contract unit price for the Fabricated Structural Steel.

Recoating Existing Multi-Girder/Beam Bridges, Truss Bridges or other Unusual Structures

Recoating weathering steel when performing joint repair/replacement may be included on the contract plans. Other areas may be recoated depending upon inspection of the condition of weathering steel and the future deterioration expectations of same by Bridge Maintenance. See Structural Project Manager or Structural Liaison Engineer.

For existing multi-girder/beam bridges, quantities shall be computed to the nearest one hundred square feet of structural steel to be prepared or recoated. The area computations do not include bearings, diaphragms, stiffeners and all other misc. steel within the limits of surface preparation or field coatings. For truss bridges or other unusual structures, quantities shall be computed as lump sum quantities.

1. Surface Preparation for Recoating Structural Steel - Preparation shall be on a case-by-case basis except areas to be in contact with concrete.

2. Field Application of Inorganic or Organic Zinc Primer - Coverage shall meet the same requirements of Surface Preparation for Recoating Structural Steel.

3. Intermediate Field Coat (System G) (Brown) - Coverage shall be on a case-by-case basis.

4. Finish Field Coat (System G or I) (Brown) - Coverage shall be on a case-by-case basis.

751.6.2.13 Protective Coatings for Concrete

When the use of a protective coating for concrete is required, it shall be reported as a lump sum item on the bridge plans. In addition, the estimated area to be coated shall be computed to the nearest square foot and recorded only in the quantity folder. The following guidelines shall apply to the calculations for these items.

Protective Coating - Concrete Bents and Piers (Urethane) or (Epoxy)
See Expansion Devices Section for details.
Protective Coating - Concrete Bents and Piers (Weathering Steel)
Concrete Abutments - Coat all surfaces above the ground line.
Concrete Intermediate Bents & Piers - Coat all surfaces above the ground line or above the low water elevation, whichever is the higher at that bent or pier.
Concrete and Masonry Protection System
Coat all surfaces above ground line of the concrete as specified on the Design Layout.
Sacrificial Graffiti Protection System
Coat all surfaces above ground line of the concrete as specified on the Design Layout.

751.6.2.14 Asphaltic Concrete Pavement

Seal coat or tack coat is required with the asphaltic concrete pavement. Unit weights will not be calculated.

751.6.2.15 Seal Coat

A seal coat shall be used when specified on the Bridge Memo.

The following unit weight will be used to calculate the estimated quantity reported on the bridge plans:

Seal Coat = 0.4 gal/sq. yd.

Grade B1 seal coat aggregate shall be used whenever a bridge deck is to receive an asphalt wearing surface. Grade A1 seal coat aggregate shall be used whenever the seal coat is to be the final riding surface. Unit weights will not be calculated for aggregate.

751.6.2.16 Tack Coat

A tack coat shall be used when specified on the Bridge Memo. The following unit weights will be used to calculate the estimated quantity reported on the bridge plans:

Tack Coat = 0.25 gal/sq. yd.

751.6.2.17 Excavation

Excavation shall be computed in accordance with Sec 206 and the limits shown in this section.

The Roadway and Drainage Excavation Line is the finish grade line after the bridge is completed in place. This may or may not correspond to the preliminary embankment line placed before the bridge is built.

The Excavation Datum is located at one foot above Low Water Elevation of the stream bed (round up to the next one foot). Use the low point of the streambed cross-section as Low Water Elevation, if a Low Water Elevation cannot be found. Everything above this datum is Class 1 Excavation while everything below it is Class 2 Excavation.

Excavation Limit Rules

Soil or other sub-strata shall be excavated to the limits of:

  • 18” around the perimeter at the bottom of footings, and vertically* to the finished Roadway and Drainage Excavation Line
  • 18” around the wings on end bents
  • The perimeter of seal courses
  • No excavation shall be figured for piles or bracing
  • If there is less than 10 cubic yards of total excavation, no excavation item needs to be listed in the Estimated Quantities. See EPG 751.50 Standard Detailing Notes for the appropriate notes.

Classes of Excavation**

Class 1, Class 2 Excavations shall be computed in accordance with Sec 206 and the limits shown in the figures below. Excavation for structures below Excavation Datum Elevation will be paid for as Class 2 Excavation. Excavation for structures above Excavation Datum Elevation will be paid for as Class 1 Excavation. Use a minimum of 10 cubic yards of Class 1 Excavation when there is Class 2.

Class 4 Excavation shall be used for culverts. Class 4 Excavation shall be computed in accordance with Sec 206 and the limits shown below. Culvert concrete removal for extensions will be paid for as Partial Removal of Culvert-Bridge Concrete. See the Design Layout for special cases.

Cases of Excavation

Case 1 is when the ground line survey is a higher elevation than the roadway and drainage excavation line.

Case 2 is when the ground line survey is a lower elevation than the roadway and drainage excavation line.

(* Soil shall be excavated vertically from the bottom of the footing for footing on pile, 6” above the bottom of the footing for footing on rock and 18” above the bottom of the footing for footing on shale.
(** Use Excavation in Rock if it is anticipated to be more than 10 cu. yard. The designer should check with the Structural Project Manager before calculating the quantity of Excavation in Rock. See EPG 751.6.1 Index of Quantities Bridge.

Excavation Limits: Bridges

The following figures graphically show the excavation limits for various substructure types. The effects of skew on the fill slope (H:V) should be considered in determining excavation quantities at end bents.

Hθ = H/cosθ

Where:

H:V = horizontal:vertical components of fill slope (Normal)
Hθ = horizontal component of the fill slope parallel to centerline of roadway with V = 1
H = horizontal component of the fill slope normal to centerline of bent with V = 1
θ = end bent skew angle
Excavation Limits: Integral End Bent (Case I)

751.6.2.17 int case 1 1.jpg

751.6.2.17 int case 1 2.jpg


Excavation Limits: Non-Integral End Bent (Case I)

751.6.2.17 non int case 1 1.jpg

751.6.2.17 non int case 1 2.jpg


Excavation Limits: Stub Bent (Case I)

751.6.2.17 stub.jpg


Excavation Limits: All Grade Separations

751.6.2.17 all.jpg


Excavation Limits: Stream Crossings (Typical)
751.6.2.17 stream typical.jpg

Excavation Limits: Stream Crossings (No Excavation Item)
751.6.2.17 stream no excavation.jpg

Excavation Limits: Retaining Walls

Note:

Excavation to be included in Estimated Quantity Table (Class 1 shall be calculated to the nearest 5 cubic yards).
Final limits of the roadway and bridge excavation to be coordinated with the bridge plans prior to estimating.
See EPG 751.50 Standard Detailing Notes for the appropriate notes.

Excavation Limits: Culverts

Excavation to be included in Estimated Quantity Table (Class 4 Excavation shall be carried to the nearest 5 cubic yards). Final limits of the roadway and bridge excavation to be coordinated with the bridge plans prior to estimating.

Excavation of 18" adjacent to the removal of culvert ends for purpose of extending the culvert will not be considered excavation and is considered part of removal. (Refer to Sec 206)

See EPG 751.50 Standard Detailing Notes for the appropriate notes.

Mechanically Stabilized Earth Walls (MSEW) Excavation and Fill

Excavation and Fill behind MSEW:

Excavation classes, quantities and pay items are determined and computed by districts for all MSEWs (Bridge Division walls and District Design Division walls) and are to be included on the roadway plans. Excavation before wall should be addressed same as excavation behind wall. Fill behind MSEWs is included in the cost of MSEWs and no separate quantity or pay item is required.

Excavation and Fill below MSEW (below top of leveling pad):

Excavation classes, quantities, replacement fill and pay items are determined and computed by districts for all MSEWs (Bridge Division walls and District Design Division walls) when required on the Foundation Investigation Geotechnical Report (FIGR), and are to be included on the roadway plans. When the FIGR gives excavation limits and type of replacement fill required for ground improvement, a detail is typically added to the MSEW plans showing the removal area and the removal locations along the wall (also referred to as “soil improvement”, “ground [or soil] mitigation”, “foundation replacement” or “foundation excavation”).

MSEW Excavation and Fill Guidelines
Excavation Std. Spec. Sec Fill Pay Item(s) on
Roadway Plans 2B
Quantities Sheet
Notes
Behind Wall 203 Compacted select
granular backfill
per Sec 720
Class A or Class C
Excavation
• Show on roadway plans
Below Wall
(Ground
Improvement)
203, 214 Compacted rock fill
or other per FIGR
Class A or Class C
Excavation,
Furnishing Rock
Fill,
Placing Rock Fill (or
other fill per FIGR)
• Show on MSEW
plans
Below Wall
(Incidental)
720 Suitable material
per District
Geotechnical
NA • Unanticipated and
Unsuitable per
engineer in field

Excavation Limits: Mechanically Stabilized Earth Walls (MSEW)

Excavation behind and below MSEWs are roadway pay items and based on information given in the Foundation Investigation Geotechnical Report (FIGR). Included may be a minimum soil reinforcement length, minimum embedment of the bottom of wall (top of leveling pad), global stability confirmation and angle of retained backfill which are used to estimate the excavation quantities. Use greatest of recommended minimum soil reinforcement length from

  • FIGR, or
  • the following table, or
  • 8 ft. minimum.

One additional foot must be added to the selected length to determine estimated excavation quantities.

Case MoDOT (USE) Table 2-1 (FHWA NHI-10-024)
(REFERENCE)
Minimum Length of Soil
Reinforcement, L
Minimum Length of Soil
Reinforcement, L
Static loading with or without
traffic surcharge
0.7H 0.7H
Sloping backfill surcharge 0.8H 0.8H
Seismic loading 0.95H1 0.8H to 1.1H

1 For a seismic design wall use 0.95H to estimate excavation quantities. For a seismic design wall minimum soil reinforcement length shall be ≥ 0.8H by design. For No-Seismic-Analysis provisions wall use minimum soil reinforcement length = 0.8H to estimate excavation quantities.

Where,

H = Height of the wall as measured from the top of the leveling pad to the top of the wall

Note: For seismic requirement upper two layers of soil reinforcement shall be extended 3 feet beyond the lower layers when wall height is greater than or equal to 10 feet. (FHWA NHI-10-024 section 4.4.3)

Minimum soil reinforcement length shall be greater than or equal to as required for a stable feature wall for strong/stable rock as shown in following cases 5 through 7.

Minimum Embedment Depth of MSEW - Minimum embedment is defined as the distance between the finished ground line and the top of the leveling pad. It is based on this table (FHWA-NHI-10-024, Table 2-1 and LRFD 11.10.2.2):

Slope in Front of Wall Minimum Embedment Depth to Top of Leveling Pad
All Geometries 2 ft minimum
Horizontal (walls) H/20
Horizontal (abutments) H/10
3H:1V H/10
2H:1V H/7
1.5H:1V H/5

Where,

H:V = Horizontal to vertical slope in front of the wall

H = Height of the wall as measured from the top of the leveling pad to the top of the wall

The absolute minimum embedment is 2 ft except when rock is found near surface. When the soundings are returned from the Geotechnical Director they will include a minimum embedment depth to the top of leveling pad, minimum soil reinforcement length necessary for global stability, bearing resistance and settlement requirements. If rock is encountered during excavation then the contractor shall immediately cease excavating and notify the engineer and contact Geotechnical Section to perform global stability and suggest a required minimum embedment depth to the top of leveling pad and required minimum soil reinforcement length.


TABLE OF EARTH WORK EXCAVATION QUANTITIES EXAMPLE IN ACCORDANCE WITH DISTRICT PROCEDURE
751.6.2.17 earth work.jpg

The excavation table example provides for identifying both Bridge Division MSE walls and District Design MSE walls.

For District Design MSE walls:

Ex. 1 shows that a wall can be laid out separate from the roadway and will have its own alignment where the wall earthwork can be quantified and shown independently in a table row.

Ex. 2 shows that a wall can be laid out along a roadway where it makes sense to include the wall earthwork with the roadway earthwork. This will be the case most of the time.

General Section thru MSEW In Cut
751.6.2.17.jpg

In Cut: (Cases 1 to 6)

θ can equal ɸƄ for computing excavation quantities. It may also be 1:1 (H:V) or 2:1 (H:V) at discretion of district.

In Fill: (Case 7)

Excavation shall be computed based on the wall and soil (and/or rock) parameters as given in the FIGR. Dimensions of ground improvements will be given in FIGR if required. This includes area elevation, length and locations along the wall and slope cuts*.

Rock fill in accordance with Sec 214 is typically used as replacement fill for ground improvement.

Case 1: In cut with soil excavation (behind wall)
751.6.2.17 case 1.jpg

Case 2: In cut with soil excavation (behind wall) and ground improvement (below wall)
751.6.2.17 case 2.jpg

Case 3: In cut with soil and rock excavation (behind wall)
751.6.2.17 case 3.jpg

Case 4: In cut with soil and rock excavation (behind wall) and ground improvement (below wall)
751.6.2.17 case 4.jpg

Case 5a Stable Feature MSE Wall: In cut with soil and partial rock excavation (behind wall)
751.6.2.17 case 5a.jpg

Case 5b Stable Feature MSE Wall: In cut with soil excavation (behind wall) and ground improvement (below wall)
751.6.2.17 case 5b.jpg

Case 6 Stable Feature MSE Wall: In cut with soil excavation
751.6.2.17 case 6.jpg

Case 7a: In fill with ground improvement (below wall)
751.6.2.17 case 7a.jpg

Case 7b Stable Feature MSE wall: In fill mostly with partial rock excavation (behind wall)
751.6.2.17 case 7b.jpg

Note: Include rock excavation in excavation quantities.