Difference between revisions of "Category:503 Bridge Approach Slabs"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (→‎503.1 Major Roads: updated link)
m (Per Transportation Planning, updated Major Highways map)
Line 19: Line 19:
 
|}
 
|}
 
===503.1 Major Roads===
 
===503.1 Major Roads===
In site-specific circumstances, the project core team may decide a bridge approach slab is not needed on a [[media:Major Highways.pdf|major road]].  In those cases, a [[131.1 Design Exception Process|design exception]] is required and the minor road guidance, shown below, is followed.  When the decision is made to include a bridge approach slab in the project plans, construction personnel will not underrun the item nor will the contractor be allowed to remove it by a [[:Category:130 Value Engineering|Value Engineering]] proposal.
+
In site-specific circumstances, the project core team may decide a bridge approach slab is not needed on a [http://wwwi/intranet/tp/documents/Major_Highway_System.pdf major road].  In those cases, a [[131.1 Design Exception Process|design exception]] is required and the minor road guidance, shown below, is followed.  When the decision is made to include a bridge approach slab in the project plans, construction personnel will not underrun the item nor will the contractor be allowed to remove it by a [[:Category:130 Value Engineering|Value Engineering]] proposal.
  
 
===503.2 Minor Roads===
 
===503.2 Minor Roads===

Revision as of 09:19, 7 September 2012

A bridge approach slab is used to provide a smooth and structurally sound transition from the pavement to the bridge. The area between the roadway embankment and the bridge end bent frequently receives inadequate compaction or a different degree of compaction than the roadway fill. Another cause of differential settlement between roadway pavement and the bridge structure is subsidence of compressible original soil layers under the new approach roadway fill's weight, while the bridge is normally founded on more unyielding foundation of solid rock or piling. In order to prevent pavement failure, an unacceptable differential elevation between the pavement and the bridge pavement, and excessive loading on the end bent, a bridge approach slab is constructed to span from the end bent over the roadway embankment.

Bridge approach slabs are included in the bridge plans prepared by the Bridge Division. Payment for bridge approach slab is included in bridge estimated quantities.

Bridge Approach Slabs, Performance and Design
Report 2004
Summary 2004
Bridge Approach Slabs, Alternative and Cost Efficient Approaches
Report, 2010
See also: Innovation Library

503.1 Major Roads

In site-specific circumstances, the project core team may decide a bridge approach slab is not needed on a major road. In those cases, a design exception is required and the minor road guidance, shown below, is followed. When the decision is made to include a bridge approach slab in the project plans, construction personnel will not underrun the item nor will the contractor be allowed to remove it by a Value Engineering proposal.

503.2 Minor Roads

Bridge approach slabs, as shown on Standard Plan 504.00, are not used on minor roads because of their expense. Bridges on minor roads, with asphatic pavement, will be constructed without any bridge approach slabs. In order to maintain an acceptably smooth pavement, maintenance forces may need to fill or patch asphatic pavement adjacent to the bridge end as settlement occurs.

Bridges on minor roads with concrete pavement will be constructed with a modified bridge approach slab in accordance with the plans. The modified bridge approach slab is considered a roadway item as part of the alternate pavement option.

This guidance shall be used for new bridge construction or bridge replacement.

503.3 Drainage

When a bridge approach slab is included in the plans, the roadway items of curb and drain basin as shown on Standard Plan 609.40 are also specified. When the bridge approach slab is not needed, a method of moving drainage away from the bridge end will be necessary. In most cases, Type A curb and drain basin will be sufficient. The project core team is to make recommendations for handling drainage as necessary.

503.4 Construction Inspection Guidance for Sec 503

Material (for Sec 503.2) The concrete mix for bridge approach slabs shall be in accordance with Sec 501 of the Standard Specifications. The bridge approach slab shall be constructed of pavement concrete or an approved Class B-1.

Construction Requirements (for Sec 503.3) This item is not subject to the Quality Control/Quality Assurance (QC/QA) requirements of Sec 502 of the Standard Specifications. Particular attention must be given to the grade of the side forms to obtain the desired riding quality. Hand finish methods, as defined by Sec 502.4.8.6, may be used for the bridge approach slab. The bridge approach slab shall be cured and sealed in accordance with Sec 703 of the Standard Specifications for bridge decks.

503.5 Maintenance Activities

See Mud Jacking Bridge Approach for additional information.

This category currently contains no pages or media.