Difference between revisions of "LPA:136.9 Plans, Specs and Estimates (PSE)"

From Engineering_Policy_Guide
Jump to navigation Jump to search
m (→‎136.9.8 Work by Local Forces: minor clarification)
 
(134 intermediate revisions by 6 users not shown)
Line 1: Line 1:
According to Missouri State Statutes, plans, specifications, and cost estimates for public roadwork must be prepared by or under the immediate personal supervision of a registered professional engineer.
+
<div style="float: right; margin-top: 5px; margin-left: 5px; width:370px; background-color: #f5f5f5; padding: 0.3em; border: 1px solid #cccccc; text-align:left;">
 +
'''<u><center>Figures</center></u>'''
 +
* [https://epg.modot.org/forms/general_files/DE/RW-LPA/LPA_Final_PS&E_Submittal_Checklist.xlsx Fig. 136.9.1, Final PS&E Submittal Checklist]
 +
* [[media:136.9.2.doc|Fig. 136.9.2, Subcontractor Certification Regarding Affirmative Action]]
 +
* [https://epg.modot.org/forms/general_files/DE/RW-LPA/Federal_Project_Bid_Proposal_Boilerplate.docx Fig. 136.9.3, Federal Project Bid Proposal Boilerplate]
 +
* [https://epg.modot.org/forms/CM/ADA_Checklist.pdf ADA Checklist (PDF)]
 +
* [https://epg.modot.org/forms/CM/ADA_Checklist.docx ADA Checklist (MS Word)]
 +
* [[media:136.9.5 2020.docx|Fig. 136.9.5, LPA Certification of PS&E]]
 +
* [[media:136.9.6.docx|Fig. 136.9.6, Utility Status Letter]]
 +
* [http://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf Fig. 136.9.7, FHWA 1273]
 +
* [[media:136.9.8 2022.docx|Fig. 136.9.8, DBE Provisions]]
 +
* [[media:Fig. 136.9.9 2020.docx|Fig. 136.9.9, DBE Submittal Forms]]
 +
* [[media:136.9.10.pdf|Fig. 136.9.10, Example Itemized Bid Form]]
 +
* [[media:136.9.11.pdf|Fig. 136.9.11, Example Estimate (with categories)]]
 +
'''<u><center>Federal-Aid Essential Videos</center></u>'''
 +
* [http://www.fhwa.dot.gov/federal-aidessentials/catmod.cfm?category=develop Project Development]
 +
* [http://www.fhwa.dot.gov/federal-aidessentials/catmod.cfm?category=civilrig Civil Rights]
 +
</div>
  
Plans and specifications must be prepared in such a manner that payment in the contract will be
+
 
made on the basis of units of work and materials.
+
=136.9.1 Introduction=
{|style="padding: 0.3em; margin-left:1px; border:2px solid #a9a9a9; text-align:center; font-size: 95%; background:#f5f5f5" width="380px" align="right"  
+
 
 +
The preparation of the PS&E for local federally funded projects is the responsibility of the local public agency (LPA).  The LPA can either prepare the PS&E, or if they are not adequately staffed to do so, they can hire a consultant to prepare the PS&E.  In either case, if using federal funds, the LPA must ensure that Preliminary Engineering (PE) funds are obligated prior to beginning any work.  The LPA shall ensure that the PS&E complies with all applicable Federal and State Laws and they must certify that that each project complies by signing and submitting the LPA Certification of PS&E ([[media:136.9.5 2020.docx|Fig. 136.9.5]]).  The PS&E Submittal Checklist ([https://epg.modot.org/forms/general_files/DE/RW-LPA/LPA_Final_PS&E_Submittal_Checklist.xlsx Fig. 136.9.1]) references the Federal and State Laws that pertain to the PS&E submittal package.  Most Federal Laws pertaining to the PS&E submittal package can be found in, but not limited to, [http://www.ecfr.gov/cgi-bin/text-idx?tpl=/ecfrbrowse/Title23/23cfr635_main_02.tpl 23 CFR 635] (Code of Federal Regulations).
 +
 
 +
The PS&E package must be submitted to MoDOT for review and approval.  Any changes that need to be made to the PS&E package will be made by the LPA.  After all changes are incorporated, MoDOT will request construction funding obligation from the Federal Highway Administration (FHWA).  After FHWA approves the obligation of federal funds for construction, MoDOT will notify the LPA of the authority to advertise for bids.  This notification by MoDOT is officially the construction authorization.  No project shall be advertised for bids until construction authorization has been issued (23 CFR 635.112). 
 +
 
 +
Competitive bidding will be required except where work by local forces by the LPA (refer to [[136.3 Federal Aid Basics#136.3.12 Federal-aid Participation for Local Work|EPG 136.3.12]]) or work by utility companies has been authorized.    A minimum of 12 weeks is the typical timeframe from PS&E submittal to award of the construction contract.
 +
 
 +
=136.9.2 Required Submittals =
 +
 
 +
In order for the LPA to get Construction Authorization which allows advertisement for bids, the PS&E documents must be approved by MoDOT.  There are multiple items that should be considered and documented during the preparation of the PS&E.  Some of these items are applicable to all projects, while others may or may not be pertinent to a project depending upon the project characteristics.  The LPA must fill out the PS&E Submittal Checklist ([https://epg.modot.org/forms/general_files/DE/RW-LPA/LPA_Final_PS&E_Submittal_Checklist.xlsx Fig. 136.9.1]) by initialing each item in the checklist and identifying a location of each document the submittal.
 +
 
 +
==136.9.2.1 Environmental, Historical and Cultural Requirements==
 +
 
 +
There are multiple clearances, certifications and a classification that must be considered and/or obtained '''prior to bid advertisement.'''  [[136.6 Environmental and Cultural Requirements|EPG 136.6]] provides details regarding the environmental, historical and cultural requirements that must be met in conjunction with the development of the project.  The LPA should ensure all environmental mitigation commitments pertaining to the project are included in the contract provisions.  Failure to meet mitigation commitments may render the project ineligible for federal reimbursement. The LPA is also responsible for communicating permit conditions and restrictions in the final design.  All environmental permits applicable to the construction of the project should be included in the proposal.  A copy of the Corps of Engineers 404 Permit, Farmland Conversion Impact Statement, SHPO Section 106 concurrence, FEMA Floodplain Development Permit and <U>ALL</u> hazardous waste reports (lead paint and asbestos inspection reports) must be included in the bid proposal.  LPA’s should work closely with the permitting agency to ensure accurate interpretation and proper transfer of permit conditions and restrictions (as appropriate) into final design. 
 +
 
 +
==136.9.2.2 Right of Way Clearance ==
 +
 
 +
In accordance with [http://www.gpo.gov/fdsys/pkg/CFR-2010-title23-vol1/pdf/CFR-2010-title23-vol1-sec635-309.pdf 23CFR635.309], authorization to advertise for bids cannot be given until a statement is submitted indicating that all right-of-way clearances have been obtained or all necessary arrangements have been made for proper coordination with the physical construction schedule.  The right-of-way clearance statement may be made separately or in conjunction with the utility status and railroad statement.  Details regarding right-of-way acquisition and clearance can be found in [[136.8 Local Public Agency Land Acquisition|EPG 136.8]]. 
 +
 
 +
==136.9.2.3 Utility Status==
 +
 
 +
In accordance with [http://www.gpo.gov/fdsys/pkg/CFR-2010-title23-vol1/pdf/CFR-2010-title23-vol1-sec635-309.pdf 23CFR635.309], authorization to advertise for bids cannot be given until a statement regarding utility clearance is submitted.  Prior to authorization to advertise for bids, utility work must be completed or necessary arrangements must have been made for completion of the work for proper coordination with the contract construction schedules.  The utility status statement may be made separately or in conjunction with the right of way clearance and railroad statements.  Details regarding utilities are found in [[136.7 Design|EPG 136.7]].
 +
 
 +
The LPA shall prepare a Utility Status Letter ([[media:136.9.6.docx|Fig. 136.9.6]]) and provide it to MoDOT with the final plans submittal. Projects must be cleared prior to construction obligation and the MoDOT district contact must receive the status letter prior to the bid opening date. Utilities “status” is defined as:
 +
 
 +
:1. All utilities are physically adjusted on the projects, or
 +
 
 +
:2. Utility construction work is active and has been completed to such a point that no impact would be expected to the road contractor. The status of the work is given in the utility job special provisions, or
 +
 
 +
:3. Utilities are not expected to be adjusted by the notice to proceed date for the road project, but the utility work will have no impact on the progress of the road contractor’s work, or
 +
 
 +
:4. Utilities must be adjusted after the contractor completes stage construction. This information must be outlined in a job special provision, or
 +
 
 +
:5. Utility adjustments, plans and specifications, are included in the bid documents for the road project.
 +
Authorization will not be granted until any necessary utility agreements are executed.
 +
 
 +
==136.9.2.4 Railroads==
 +
 
 +
In accordance with [http://www.gpo.gov/fdsys/pkg/CFR-2010-title23-vol1/pdf/CFR-2010-title23-vol1-sec635-309.pdf 23CFR635.309], authorization to advertise cannot be given until a statement regarding any railroad involvement is submitted even when no railroads are affected by the project.  Projects on railroad right of way or crossing railroad right of way require the railway company’s written approval of the final plans prior to construction authorization.  This statement may be made separately or in conjunction with the right of way clearance and utility status statements. Details regarding Railroads are found in [[136.7 Design|EPG 136.7]] and [[643.4 Railroads|EPG 643.4 Railroads]].
 +
 
 +
Where construction of a federally funded project requires use of railroad properties or adjustments to railroad facilities, there shall be an agreement in writing between the LPA and the railroad company.
 +
 
 +
FHWA approval of railroad agreements is required for federal full oversight projects. A copy of the written agreement shall be transmitted to the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district contact] for FHWA review.
 +
 
 +
Authorization will not be granted until any necessary railroad agreements are executed.
 +
 
 +
==136.9.2.5 Bridge (Structure) Submittals==
 +
 
 +
The LPA is required to submit various deliverables on federally funded projects which include structures as defined in [[136.7 Design#136.7.2.2.2 General Types of Structures|EPG 136.7.2.2.2 General Types of Structures]].  The requirement for PS&E submittal deliverables is mandatory for structures that meet the definition for highway bridges and culverts as found in [[136.7 Design#136.7.2.2.1 Funding/Programs|EPG 136.7.2.2.1 Highway Bridges and Culverts]].  For structures that fit the definitions given in [[136.7 Design#136.7.2.2.2.2 Non-NBI Length Bridges and Culverts|EPG 136.7.2.2.2.2 Non-NBI Length Bridges and Culverts]], [[136.7 Design#136.7.2.2.2.3 Pedestrian Structures|EPG 136.7.2.2.2.3 Pedestrian Structures]], [[136.7 Design#137.7.2.2.2.4 Retaining Walls|EPG 136.7.2.2.2.4 Retaining Walls]] and [[136.7 Design#136.7.2.2.2.5 Structures on MoDOT Right of Way|EPG 136.7.2.2.2.5 Structures on MoDOT Right of Way]], the engineer of record shall review these sections to determine the appropriate PS&E deliverables that  are required and to determine the required input from MoDOT Bridge Division.
 +
 
 +
To aid in the determination of the various deliverables and the responsibilities for these deliverables, the tables in [[136.7 Design#136.7.2.2.7 Structure Submittal Requirements|EPG 136.7.2.2.7 Structure Submittal]] shall be reviewed by the engineer of record. For structures that will be NBI length, [https://epg.modot.org/forms/general_files/DE/RW-LPA/LPA_Final_PS&E_Submittal_Checklist.xlsx Fig. 136.9.1] may also be used for guidance on the deliverables required.
 +
 
 +
Renovation or demolition of structures requires hazardous waste reports (lead paint and asbestos inspection reports) and must be in the bid proposal.  Additionally, a notification of demolition 10 days prior to the start of structure work is required per [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=5 Sec 202.40.1.1].  For more guidance, refer to [[136.6 Environmental and Cultural Requirements#136.6.4.10.1 Renovation and Demolition of Structures|EPG 136.6.4.10.1 Renovation and Demolition of Structures]].
 +
 
 +
==136.9.2.6 Proprietary Items==
 +
 
 +
The use of proprietary items on federally funded projects is discouraged.  However, circumstances may exist that require specific products to meet the project need.  In these instances, in order for the proprietary item to be eligible for federal funds, three separate, competing products must be identified in the contract documents and an alternative product approval process must be indicated for each proprietary item included.  If certain conditions exist that cause this requirement to be unachievable a Public Interest Finding must be obtained.  Any proprietary item that does not meet one of the two previously described conditions, must be noted as non-participating on the estimate.  Prior to submitting the PS&E, the LPA should obtain a public interest finding for any proprietary items included in the project.  The proprietary item and the date the public interest finding was issued should be noted on the PS&E Submittal Checklist that accompanies the PS&E submittal.  See [[136.7 Design|EPG 136.7]] for details regarding proprietary items and public interest findings.
 +
 
 +
==136.9.2.7 Design Exceptions/Variances==
 +
 
 +
A registered Professional Engineer in the State of Missouri must sign the approval for design exceptions.  In addition, the LPA representative with approval authority shall sign approvals for design exceptions.  Additional procedures concerning documentation requirements can be found in [[136.7 Design|EPG 136.7]].
 +
 
 +
==136.9.2.8 Work By Local Forces==
 +
 
 +
When an LPA desires to use their own forces to construct a project financed with federal funds, a request must be submitted to MoDOT for approval.  See [[136.3 Federal Aid Basics#136.3.12 Federal-aid Participation for Local Work|EPG 136.3.12]] for details on work by local forces.
 +
 
 +
==136.9.2.9 Non-Infrastructure Projects==
 +
 
 +
Submittals for non-infrastructure projects will vary.  See [[136.5 Non-Infrastructure|EPG 136.5 Non-Infrastructure]] for details concerning various types of non-infrastructure projects and the required submittals.
 +
 
 +
==136.9.2.10 ADA Checklist==
 +
 
 +
The [https://epg.modot.org/forms/CM/ADA_Checklist.pdf ADA Checklist (PDF version of Fig. 136.9.4)] (or the [https://epg.modot.org/forms/CM/ADA_Checklist.docx MS Word version of the ADA Checklist, Fig. 136.9.4]), must also be submitted as supporting documentation to the PS&E.
 +
 
 +
==136.9.2.11 PS&E Certification==
 +
 
 +
The LPA certification of PS&E (Fig. 136.9.5) must be submitted with the PS&E when the LPA decides to use standard specifications other than ''Missouri Standard Specifications for Highway Construction''.  The LPA must certify that the specifications meet all state and federal laws and regulations.
 +
 
 +
=136.9.3 Plans =
 +
 
 +
The LPA must submit plans as a part of the PS&E submittal package.  For requirements on the content of the plans see [[136.7 Design|EPG 136.7]].  Before submitting plans, the LPA should ensure that all plan sheets are signed and sealed by the engineer of record and that the title sheet is signed by the LPA.
 +
 
 +
=136.9.4 Bid Documents=
 +
 
 +
Bid documents include the [[#136.9.4.1 Bid Proposal|bid proposal]], [[#136.9.4.2 Specifications|specifications]] and [[#136.9.4.3 Standard Plans|standard plans]].
 +
 
 +
EPG 136.9.4 includes a breakdown of required provisions and restrictions.  Many are included in the boilerplate ([https://epg.modot.org/forms/general_files/DE/RW-LPA/Federal_Project_Bid_Proposal_Boilerplate.docx Fig. 136.9.3]) and FHWA 1273 ([http://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf Fig. 136.9.7]).  Others should to be included in the specifications and job special provisions, as necessary.
 +
 
 +
==136.9.4.1 Bid Proposal ==
 +
 
 +
The LPA is required to use the Federal Project Bid Proposal Boilerplate ([https://epg.modot.org/forms/general_files/DE/RW-LPA/Federal_Project_Bid_Proposal_Boilerplate.docx Fig. 136.9.3]]) or an approved modified version of the boilerplate. For approval of a modified version of the boilerplate, the LPA must submit a proposed version to their [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district contact].The approval of the modified version must occur prior to submitting a project for review and approval.
 +
 
 +
The bid proposal must contain <u>The Notice to Contractors</u>. This notice is located in the front of the bid proposal and  provides prospective bidders with the bid opening date, time and location where bids will be received and opened; a brief description of the project; and the time and location of any pre-bid meetings. 
 +
 
 +
The bid proposal must also contain a List of items required in order for the bids to be considered responsive:  Federal regulations state that any requirements the bidder must comply with to be considered responsive should be clearly identified in the bidding documents. (Refer to [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=ad83a0198b1b37c4c10512d1b769e803&rgn=div8&view=text&node=23:1.0.1.7.23.1.1.12&idno=23 Title 23 CFR, Sections 635.112]).
 +
 
 +
The [https://epg.modot.org/forms/general_files/DE/RW-LPA/LPA_Final_PS&E_Submittal_Checklist.xlsx Final PS&E Submittal Checklist Fig.136.9.1] includes a list of required federal provisions.
 +
 
 +
===136.9.4.1.1 Bid Proposal – Required Provisions===
 +
 
 +
====136.9.4.1.1.1 Contract Time====
 +
Contract Time must be specified in the bid proposal and must be monitored by the LPA.  Contract time is defined as the maximum time allowed in the contract for completion of all work contained in the contract documents. This time can be established in the specifications by either a specific completion date or a fixed number of calendar days or working days. The definition of calendar days and workings days must be included in the bid proposal if the LPA is not using MoDOT specifications. Contract time often becomes an issue when the traveling public is inconvenienced without any apparent reason. While there may be several reasons for a project to appear dormant, frequently the cause can be traced to excessive contract time or poor contractor scheduling.
 +
 
 +
Insufficient contract time can result in higher bid prices, increased time overruns and claims, inefficiencies and safety problems. On the other hand, excess contract time can result in increased inefficiencies, unnecessary delays and inconvenience to the public.
 +
 
 +
There are several different techniques used to determine contract time.  See [[237.8 Contract Time|EPG 237.8]] for more information.
 +
 
 +
The LPA should strive for the shortest practical duration of traffic interruptions during highway construction. Innovative contracting methods including incentive/disincentive (I/D), lane rental, A+B contracts or other contract provisions for early completion are available to minimize traffic inconvenience and delay. The FHWA Technical Advisory 5080.10, Incentive/Disincentive for Early Completion, describes this technique in detail, and is available in the appendix of FHWA's [http://www.fhwa.dot.gov/programadmin/contracts/coretoc.cfm ''Contract Administration Core Curriculum''].
 +
 
 +
====136.9.4.1.1.2 Liquidated Damages ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1127&rgn=div8 23 CFR 635.127])====
 +
 
 +
A provision for liquidated damages must be included in the bid proposal and must be administered by the LPA.  The term liquidated damages means the daily amount set forth in the contract to be deducted from the contract price to cover additional costs incurred by the LPA because of the contractor’s failure to complete the contract work within the number of calendar days or work days specified.
 +
 
 +
The actual liquidated damage rate must be specified in the bid proposal.  The amount of project costs that will be eligible for federal participation will be reduced by the amount of any liquidated damages assessed against the contractor.  In determining the amount eligible for participation, the amount of liquidated damages will first be deducted from the amount of construction engineering claimed and then from construction costs if the amount of liquidated damages exceeds the amount of construction engineering.  The liquidated  damages should be, at a minimum,  the amount  shown in the following table corresponding to the original contract amount to minimize the risk of losing full federal participation.
 +
<center>
 +
{| border="1" class="wikitable" style="margin: 1em auto 1em auto" style="text-align:center"
 +
|+
 +
!style="background:#BEBEBE" colspan="3"|Schedule of Deductions for Each Day of Overrun in Contract Time, <br> Original Contract Amount (or the Engineer's Estimate of the Total Construction Cost)
 +
|-
 +
! style="background:#BEBEBE" |From ($)!!style="background:#BEBEBE" | To, and including ($)!! style="background:#BEBEBE" |Assessment, per Day ($)
 +
|-
 +
| 0|| 25,000|| 475
 +
|-
 +
|25,001|| 50,000|| 475
 +
|-
 +
|50,001|| 100,000|| 500
 +
|-
 +
|100,001|| 500,000|| 700
 +
|-
 +
|500,001|| 1,000,000|| 950
 +
|-
 +
|1,000,001|| 2,000,000|| 1,100
 +
|-
 +
|2,000,001|| 3,000,000|| 1,225
 +
|-
 +
|3,000,001|| 4,000,000|| 1,625
 +
|-
 +
|4,000,001|| 5,000,000|| 2,025
 +
|-
 +
|5,000,001|| 6,000,000|| 2,425
 +
|-
 +
|6,000,001|| 7,000,000|| 2,825
 +
|-
 +
|7,000,001|| 8,000,000|| 3,225
 +
|-
 +
|8,000,001|| 9,000,000|| 3,625
 
|-
 
|-
|colspan="2"|<center>'''Additional Information'''</center>
+
|9,000,001|| 10,000,000|| 4,025
 
|-
 
|-
|[[media:136.9.1 Work by Local Forces Proposal (Fig. 9-1).doc|Fig. 136.9.1 Work by Local Forces Proposal]]||[[media:136.9.2 Utility.jpg|Utility Depth and Encasement Requirements]]
+
|10,000,001|| 70,000,000|| 4,300
 
|}
 
|}
Plans and specifications prepared by the engineer may be reviewed by MoDOT on a cursory basis
+
</center>
for an individual project basis only and should not necessarily be assumed to apply to other similar projects. Design computations do not need to be submitted to MoDOT unless requested, with the exception of vehicle load rating computations that meet the requirements described in this article.
 
  
===136.9.1 Roadway===
+
====136.9.4.1.1.3 Bid Guaranty ([http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&rgn=div8&view=text&node=49:1.0.1.1.12.3.5.14&idno=49 49 CFR 18.36])====
[[image:136.9.1.jpg|right|125px]]
+
The bid proposal must include criteria requiring a bid guarantee of at least 5% of the bid amount. The bid proposal may include bid bond requirements over 5%, although the LPA should consider excessive burdens put on the contractor where higher percentage bid bonds are required on large projects. Bid bond requirements expressed as a dollar amount are not allowed. The bid guaranty can be in the form of a cashier’s check, certified check or bid bond.  Bid bonds must be guaranteed by a surety company authorized by the director of the department of insurance, financial institutions and professional registration to conduct surety business in the state of Missouri.  More detail regarding bid guaranty can be found in [https://revisor.mo.gov/main/OneSection.aspx?section=227.100 RSMO 227.100] and [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=4 Sec 102.9]. MoDOT has included an example bid bond in the Federal Project Bid Proposal Boilerplate [https://epg.modot.org/forms/general_files/DE/RW-LPA/Federal_Project_Bid_Proposal_Boilerplate.docx Fig. 136.9.3].
There is no set standard for the order of sheets within the roadway portion of the plans. Items that must be included are typical sections, plan, profile, or plan and profile sheets, special sheets, erosion control plans, traffic control plans, and cross section sheets or data. Other sheets to be included if applicable include culvert sheets, lighting, signals, signing, utility sheets if part of the roadway contract and standard plans.
 
  
The plan, profile, or plan and profile sheets should include a north arrow, graphic scale, description of the project’s beginning and ending points, construction details, alignment and profile data, bench marks, and any construction notes. Construction notes should not be placed in the cross section sheets.
+
====136.9.4.1.1.4 Certifications Regarding Affirmative Action and Equal Opportunity ====
 +
The LPA shall include requirements for certification pursuant to 41 CFR Parts 60-2, 60.1, 60.1.4 and Executive Order No. 11246 regarding affirmative action and equal opportunity in the bidding documents. [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=4 Sec 102.18.1] details the compliance requirements.  The Federal Project Bid Proposal Boilerplate ([https://epg.modot.org/forms/general_files/DE/RW-LPA/Federal_Project_Bid_Proposal_Boilerplate.docx Fig. 136.9.3]) addresses this in (6) <u>CERTIFICATIONS FOR FEDERAL JOBS</u> for the prime contractor. .  If the bid proposal boilerplate is modified, Section 102.18.1 of the Missouri Standard Specification for Highway Construction cannot be waived.  A certification regarding affirmative action and equal opportunity for the subcontractor ([[media:136.9.2.doc|Fig. 136.9.2]]) must be submitted for all subcontractors prior to the notice to proceed for construction.
  
===136.9.2 Water Quality Impacts/Land Disturbance===
+
====136.9.4.1.1.5 Suspension and Debarment Certification ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1112&rgn=div8 23 CFR 635.112])====
 +
On all federal-aid construction contracts and all related subcontracts, the contractor and lower tier participants must certify they are in compliance with this provision. This includes subcontractors, material suppliers and vendors.
  
The National Pollutant Discharge Elimination Systems (NPDES) program regulates construction activities where 1 acre or more of land is disturbed. If the project proponent has a general NPDES permit for all of their construction activities, this is adequate. If the project proponent does not have a valid general permit and will disturb 1 acre or more of land, a project-specific NPDES permit is required. If the project is entirely within MoDOT right of way, the sponsor may use MoDOT’s general permit. In either case, the sponsor will need to develop a site-specific stormwater pollution prevention plan for the project. The sponsor shall contact the Missouri Department of Natural Resources (DNR) NPDES Storm Water Program office at (573) 751-1300 or (800) 361-4827 for further directions. A few cities (Kansas City, Columbia, and others) and counties have obtained their own land disturbance permits from DNR for generic land disturbance purposes; see additional discussion on stormwater and erosion control in [[136.4 Environmental and Cultural Requirements|EPG 136.4 Environmental and Cultural Requirements]].
+
Each participant in the contract must certify “that it is not presently debarred, suspended, proposed for debarment, declared ineligible or voluntarily excluded from covered transactions by any federal agency and they have not been convicted or had civil judgment rendered within the past 3 years for certain types of offenses”. It is the LPA’s responsibility to assure that the contractor is not suspended or debarred from federal contracts. The [https://sam.gov/content/home System for Award Management] website is helpful.  
  
===136.9.3 [[616.1 Preparation of Traffic Control Plan (TCP)|Traffic Control]]===
+
The LPA shall include the lobbying certification requirement 49 CFR Part 29 regarding suspension and debarment certification in the bidding documents. The Federal Project Bid Proposal Boilerplate, covers this requirement in Section (6) <u>CERTIFICATIONS FOR FEDERAL JOBS</u>. If the bid proposal boilerplate is modified, [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=4 Sec 102.18.1] cannot be waived.
  
The local agency shall develop and implement a Transportation Management Plan (TMP) in sustained consultation with all stakeholders for each project. The TMP shall consist of strategies to manage work zone impacts and provide for the safe and efficient movement of motorized and non-motorized traffic through or around the construction. The TMP shall include a Temporary Traffic Control (TTC) plan for non-significant projects and TTC, Transportation Operation (TO) and Public Information (PI) plans for projects determined to have significant impact on the public. A significant project is one that, alone or in combination with other concurrent projects nearby, is anticipated to cause sustained work zone impacts greater than what is considered tolerable.
+
====136.9.4.1.1.6 Anti-collusion Provision ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1112&rgn=div8 23 CFR 635.112])====
 +
The bidding documents shall include a non-collusion provision to the following effect: Each bidder shall file a statement executed by, or on behalf of the person, firm, association, or corporation submitting the bid certifying that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action, in restraint of free competitive bidding in connection with the submitted bid.
  
The TTC plan describes measures to be used to facilitate the movement of system users through or around the construction and shall conform to the guidelines set forth in Chapter 6 of the [http://mutcd.fhwa.dot.gov/pdfs/2003r1/pdf-index.htm ''Manual on Uniform Traffic Control Devices'' (MUTCD)]. [[:Category:616 Temporary Traffic Control|EPG 616 Temporary Traffic Control]] and [[616.23 Traffic Control for Field Operations|EPG 616.23 Traffic Control for Field Operations]] may be used as references in the development of the TTC plan. The scope of the traffic control plan should match the complexity of the project.
+
The Federal Bid Proposal Boilerplate ([https://epg.modot.org/forms/general_files/DE/RW-LPA/Federal_Project_Bid_Proposal_Boilerplate.docx Figure 136.9.3]), includes the anti-collusion certification requirements in Section (6) <u>CERTIFICATIONS FOR FEDERAL JOBS</u> and Section (14) <u>SIGNATURE AND IDENTITY OF BIDDER</u>. If the bid proposal boilerplate is modified, [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=4 Sec 102.18.3] cannot be waived.
  
The TO plan identifies strategies to be used to mitigate impacts of the work zone on the operation and management of the transportation system within the work zone impact area.
+
====136.9.4.1.1.7 Lobbying Certification ([http://www.fhwa.dot.gov/hep/49cfr20.htm 49 CFR part 20])====
The PI plan prescribes the communication strategies to be used to inform affected road users, the general public, area residents and businesses, and appropriate public and transportation entities about the project, the expected impacts of the work, and changing conditions.
+
On all federally funded construction contracts and all related subcontracts of $100,000 or more, federal funds may not be used to provide financial gain to a member of congress or a federal agency. Awarding a federal-aid contract to a constituent would be an example of financial gain. This applies to contractors as well as subcontractors. A certification by the contractor indicating they have not and will not use federal funds to make any payments for lobbying must be included in the contract proposal.
The plans and specifications should include the TMP and pay item for implementing the TMP, including providing, installing, moving, replacing, maintaining, cleaning, and removing traffic control devices required by the TTC plan.
 
  
The local agency shall designate a trained person on each project who has the primary responsibility, with sufficient authority, for implementing the TMP and other safety and mobility aspects of the project.
+
The LPA shall include the lobbying certification requirement pursuant to 49 CFR part 20 in the bidding documents.  The Federal Project Bid Proposal Boilerplate ([https://epg.modot.org/forms/general_files/DE/RW-LPA/Federal_Project_Bid_Proposal_Boilerplate.docx Figure 136.9.3]) includes the lobbying certification requirements in Section (6) <u>CERTIFICATIONS FOR FEDERAL JOBS</u>.  If the bid proposal boilerplate is modified, [http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=4 Sec 102.18.4] cannot be waived.
  
===136.9.4 Railroad Crossings===
+
====136.9.4.1.1.8 Title VI Civil Rights Assurances ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1112&rgn=div8 23 CFR 635.112(d)])====
 +
The following Title VI Civil Rights Assurances notification must be included in the invitation to bidders in the front of all bid proposals and in any bid advertisements and invitations for bids:
  
If the proposed improvements are on or cross railroad right of way, the railway company must be
+
:“The County/City/Organization of _______________________ hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, businesses owned and controlled by socially and economically disadvantaged individuals will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, religion, creed, sex, age, ancestry, or national origin in consideration for an award.
contacted. Railway company approval will be necessary to receive construction authorization. The
 
local agency must contact the affected railway company directly.
 
  
===136.9.5 Utilities===
+
====136.9.4.1.1.9 Inspection by MoDOT and FHWA ([http://www.modot.org/business/standards_and_specs/SpecbookEPG.pdf#page=4 Sec 105.10])====
 +
The project Bid Proposal shall stipulate that MoDOT and FHWA may make inspections of the work at any time and that the contractor shall grant them access to all parts of the work.
  
All existing and proposed utility facilities must be shown on the plan sheets. The [[media:136.9.2 Utility.jpg|minimum depth locations and encasement requirements]] for the utilities located on MHTC right of way are available.
+
====136.9.4.1.1.10 Wage Rates ([https://revisor.mo.gov/main/OneSection.aspx?section=290.263 RsMO 290.263])====
 +
A statement is required in the Bid Proposal  indicating that when state and federal wage rates are both required the higher of the two for each job classification should be used.
  
The local agency shall prepare a [http://www.modot.mo.gov/business/manuals/documents/UtilityStatusLetter.pdf Utility Status Letter] and provide it to MoDOT with the final plans submittal. Projects must be cleared for bid opening and MoDOT district personnel must receive the status letter, prior to the bid opening date. Utilities “status” is defined as:
+
=====136.9.4.1.1.10.1 Federal Wage Rates ([http://us-code.vlex.com/vid/sec-prevailing-rate-wage-19205135 23 USC 113] and [http://www.rurdev.usda.gov/mi/cp/Davis%20Bacon%20Labor%20Standards%20Contract%20Document.pdf 29 CFR 5])=====
 +
The payment of predetermined minimum wages on federal-aid contracts is derived from the Davis-Bacon Act of 1931 and is prescribed by 23 USC 113. These wage rates must be physically inserted in the Bid Proposal on all federal-aid highway construction projects exceeding $2,000 and to all related subcontracts.
  
'''1.''' All utilities are physically adjusted on the projects, or
+
The federal minimum wage rates are available from the [https://www.dol.gov/agencies/whd Department of Labor’s Wage and Hour Division website] (click on “Wage Determinations” at the bottom of the page and then click on “Public Building or Works” or directly from the [https://sam.gov/content/wage-determinations SAM.gov website].  Once at the search location, select all appropriate information, including “Missouri” and the county in which the work is taking place.  For LPAs in Missouri to be in conformance with the federal “10-day rule”, LPAs are to access the “Federal Wage Rates” ten days prior to bid opening to see if updated federal wage rates have been posted. The applicable wage rates will be posted 10 days prior to the bid opening. When the wage rates change within the 10-day window, the LPA will not update the wage rates since doing so will not provide contractors with sufficient time to accommodate the revised wage order. If the updated wage rates have been posted, LPAs are required to issue an addendum to insert the updated wage rates in their final contract package.
  
'''2.''' Utility construction work is active and has been completed to such a point that no impact would be expected to the road contractor. The status of the work is given in the utility job special provisions, or
+
Federal wage rates are not required to be physically included in the contract advertising package provided they are referenced to an Internet web site address where they can be found or they can be posted at a referenced location that is readily accessible by all bidders. The final contract package signed by the LPA and the contractor must physically contain the federal wage rates, including updates if applicable.
  
'''3.''' Utilities are not expected to be adjusted by the notice to proceed date for the road project, but the utility work will have no impact on the progress of the road contractor’s work, or
+
=====136.9.4.1.1.10.2 State Wage Rates ([http://www.sos.mo.gov/adrules/csr/current/8csr/8c30-3.pdf 8 CSR 30-3])=====
[[image:136.9.6.jpg|right|105px]]
+
The LPA must request an Annual State Wage Determination for each contract from the Industrial Commission, Missouri Department of Labor and Industrial Relations (DOLIR), Box 449, Jefferson City, Missouri 65102 or by calling (573) 751-3403. The LPA will receive a password from the Missouri DOLIR which is required to access the official Annual Wage Order and incremental increases on the [http://labor.mo.gov/ Missouri DOLIR webpage]. Contracts must be awarded within one year of the issuance of the official Annual Wage Order or the LPA will be required to request a new Annual Wage Order determination. '''The Annual Wage Order must be included in the proposal and must be part of the contract.'''
'''4.''' Utilities must be adjusted after the contractor completes stage construction. This
 
information must be outlined in a job special provision, or
 
  
'''5.''' Utility adjustments, plans and specifications, are included in the bid documents for the road project.
+
====136.9.4.1.1.11 E-Verify Affidavit & MOU ([https://revisor.mo.gov/main/OneSection.aspx?section=285.530 RsMO 285.530])====
 +
The bid proposal must state that requirements regarding the Federal Work Authorization Program and list the Federal website for E-Verify.  The bid proposal must state that the E-verify affidavit and MOU must be submitted prior to award of the contract.
  
===136.9.6 Projects with Bridges===
+
====136.9.4.1.1.12 OSHA 10-Hour Training ([https://revisor.mo.gov/main/OneSection.aspx?section=292.675 RsMO 292.675])====
 +
The bid proposal must state that the bidders must adhere to the OSHA 10-Hour Training requirements.
  
====136.9.6.1 Bridge Drawings and Contract Documents====
+
====136.9.4.1.1.13 Buy America ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1410&rgn=div8 CFR 635.410])====
Structural drawings, specifications and special provisions for bridges or culverts must provide
+
On all federal-aid construction projects, 23 CFR 635.410 requires that steel and iron used be made in the United States. The “Buy America” provision is applicable to all steel and iron materials, except as noted below, regardless of the percentage of steel in the manufactured product.  All manufacturing processes involved in steel or iron products must occur within the United States. These processes include rolling, extruding, machining, bending, grinding, drilling, coating, welding and smelting. Domestically produced steel billets or iron ingots shipped overseas for any process and returned to the United States do not conform to this requirement.
sufficient detail that will clearly identify all dimensional and materials requirements, and will allow the construction of all structural components in accordance with the engineer’s design.
+
Buy America provisions do not apply to:
  
The drawings shall provide appropriate general notes to identify all pertinent design criteria for the project; such as identification of all design loads, design unit stresses for the structural components, bearing pad and joint filler requirements, hydraulic data, geotechnical information, reinforcing steel clearances, etc. The notes should identify the usage of the appropriate AASHTO Design Standard Specification for Highway Bridges along with a listing of significant exceptions. Also, plans should note the applicable construction specifications.
+
:* Minimal use of all foreign material in which the total delivery cost to the project site is less than $2500 or 0.1 percent of the contract amount, whichever is greater.  
  
Drawings shall include a summary of estimated quantities, a reinforcing steel bar list and bending diagrams and a pile data table and footing design bearing table, where applicable.
+
:* Raw materials; scrap temporary steel items such as sheet pilings, bridges, steel scaffolding and false work.  
  
'''1.''' If useful as an aid and/or reference, [[:Category:751 LRFD Bridge Design Guidelines|751 LRFD Bridge Design Guidelines]] covering design and detail of prestress double tee, prestress I-beam and other type structures, including steel is available.  
+
:* Materials that remain in place at the contractor’s convenience such as sheet pilings and forms.  
  
'''2.''' [http://www.modot.mo.gov/business/consultant_resources/bridgestandards.htm Detail sheets are also available for many superstructure details and substructure units].  
+
:* Pig iron manufactured outside the United States.  
  
'''3.''' If a concrete box culvert structure is appropriate, [http://www.modot.mo.gov/business/standards_and_specs/currentsec700.htm Standard Plans are readily available for single, double, or triple box culverts]. These may be used in conjunction with an additional front sheet for the double and triple box culverts to be completed with information from the standard plans.
+
An LPA shall not list an ineligible iron or steel product as “nonparticipating” in order to circumvent the Buy America requirements.
  
====136.9.6.2 Structural Inventory and Appraisal Sheet====
+
A waiver of the Buy America requirements by the FHWA Division Administrator is permitted for specific projects, specific products, specific geographical areas or combinations if:
  
The engineer must complete the Structural Inventory & Appraisal (SI&A) Sheet and provide it with the PS&E by the engineer for any replacement structure (or rehabilitated structure) that will meet the National Bridge Inventory definition of a “bridge”. The SI&A Sheet must be completed in accordance with the [http://www.fhwa.dot.gov/bridge/mtguide.pdf ''Recording and Coding Guide for the Structure Inventory and Appraisal of the Nation's Bridges''], by [http://www.fhwa.dot.gov/ FHWA].
+
:* Buy America is inconsistent with the public interest, or
  
A blank form for the [http://www.modot.mo.gov/business/manuals/documents/siaform.pdf Structural Inventory and Appraisal Sheet] is provided under “Commonly Used
+
:* There is not a sufficient supply of domestic materials of satisfactory quality.  
Forms”. This form can be filled out electronically and printed.
 
  
====136.9.6.3 Load Rating Calculations and Load Rating Summary Sheet====
+
Failure to comply with the Buy America Policy can result in loss of federal funding, not just for the item, but for the entire project. Approval for waiver of Buy America requirements must be obtained from FHWA.
  
Load rating calculations are required for all structures that will be classified as a "bridge" on the National Bridge Inventory (as defined [http://www.fhwa.dot.gov/bridge/mtguide.pdf ''Recording and Coding Guide for the Structure Inventory and Appraisal of the Nation's Bridges''].  Inventory and Operating Load Ratings shall be provided compared to the AASHTO HS20 design loading. Load rating calculations for any NBI structure carrying vehicular traffic shall also account for all MoDOT standard load posting vehicles (the H20 and 3S2 vehicles) used to represent truck legal loads in the state. For bridges or culverts located within the limits of commercial zones, an additional load posting recommendation for the commercial loading shall be included, utilizing the MO5 vehicle. (For example, when the operating rating for the MO5 vehicle is less than 70T, a S-C3 posting is required). For information and details regarding MoDOT’s rating vehicles, refer to [http://epg.modot.org/files/5/5d/Bridgesection_4.pdf Section Four of MoDOT’s Bridge Inspection Rating].
+
'''Buy America should not be confused with Buy American.'''
  
All load ratings are to be calculated using the Load Factor Rating Method in accordance with the
+
====136.9.4.1.1.14 Contractor Requirements====
AASHTO ''Manual for Condition Evaluation of Bridges''. A Load Rating Summary Sheet, signed
 
and sealed by a Missouri Registered Professional Engineer, shall clearly list all of the determined controlling load ratings, indicated in tons. The Load Rating Summary Sheet shall indicate all information needed for the completion of the Load Rating and Posting portion of the SI&A Sheet and the load rating calculations shall provide the information necessary to support the data indicated on the Load Rating Summary Sheet.
 
  
Load rating calculations and the load rating summary sheet will generally not be required with the PS&E submittals for projects which will utilize structural systems that are essentially proprietary based such as CMP or concrete arch culvert structures, since identification of a single proprietary manufacturer is generally not allowed in the contract documents. Unless informed otherwise by the local agency or engineer of record at the time of the PS&E submittal, MoDOT will in the interim assume that the presumptive values for the inventory and operating ratings are being achieved through the manufacturer’s conformance with the design loading indicated by the local agency’s consultant in the contract documents. However, the contract specifications should include the requirement that the actual load ratings, signed and sealed by a professional engineer licensed in Missouri be provided by the awarded manufacturer. MoDOT districts should secure this information along with an updated SI&A form and forward to the MoDOT Bridge division prior to project closeout. Upon receipt of the additional information from the local agency, MoDOT Bridge division will update the National Bridge Inventory to indicate the actual ratings.
+
=====136.9.4.1.1.14.1 Work completed by the Prime Contractor ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1116&rgn=div8 23 CFR 635.116])=====
 +
The bid proposal shall stipulate that the prime contractor on a project must perform, with its own staff, contract work amounting to not less than 30% of the total original contract price.
  
===136.9.7 Estimates===
+
=====136.9.4.1.1.14.2 Pre-qualification of Prime Contractors=====
 +
Prequalification of contractors may be required as a condition of submission of a bid or award of contract only if the period between the date of issuing a request for bids and the date of opening of bids affords sufficient time to enable a bidder to obtain the required prequalification rating or approval. All prequalification criteria must be submitted to MoDOT for approval in advance of the date of issuing a request for bids.  The intent of the pre-qualification of contractors is not to intentionally disqualify contractor but to qualify contractors based on a set criteria.
  
An engineer's estimate, showing estimated quantities, unit prices and extended totals shall be
+
Depending upon the project type and the LPA’s preference, one of the following scenarios will apply to a project: 
submitted to MoDOT with the detailed plans. Subtotals shall be shown for roadway items, bridge, signing/striping/signals, landscaping/streetscaping, utilities (reimbursable with federal participation) and bicycle/pedestrian facilities . The bid proposal will also need to include an itemized listing of all pay items included in the project, quantities of each individual pay item and blanks for the contractor to submit a unit price (and extension) for each pay item. Non-participating work (work that is not eligible for federal participation) shall be identified in the submitted estimate prepared by engineer of record. Any non-reimbursable utility work shall be separated from utility work that is eligible for participation. The use of lump sum contract will not be allowed.
 
  
The engineer's estimate should be treated as a confidential document. Any knowledge of the
+
:* LPA shall require MoDOT Pre-Qualification
estimate may cause unbalanced bids or provide a contractor who has knowledge of the engineer's
 
estimate an advantage.
 
  
===136.9.8 Work by Local Forces===
+
:* LPA shall waive MoDOT Pre-Qualification and use no pre-qualification requirement
  
As required by federal regulations, [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&rgn=div5&view=text&node=23:1.0.1.7.23&idno=23#23:1.0.1.7.23.2 23 CFR Subpart B, Section 635.201-205], the contract method based on competitive bidding shall be used for performance of highway work financed with the aid of federal funds unless it can be demonstrated that some other method is more cost effective. Force Account, or [[media:136.9.1 Work by Local Forces Proposal (Fig. 9-1).doc|work by local forces]] is considered to be the direct performance of work by the contracting agency or its designee utilizing labor, equipment, materials and supplies furnished by the agency and used under its direct control. When the local agency desires to construct any portion of the project with its own forces, it must be in the public interest that this is the most cost effective way to construct the project (the efficient use of labor, equipment, materials and supplies to assure the lowest overall cost). Local agencies must demonstrate to MoDOT that they have the equipment and experience to perform the items of work specified. MoDOT shall determine that the organization to undertake the work is so staffed and equipped as to perform such work satisfactorily and cost effectively. When a local agency desires that highway construction work financed with the aid of federal funds be undertaken by local forces, a request must be submitted identifying and describing the following:
+
:*  LPA shall waive MoDOT Pre-Qualification and use their own pre-qualification process i.e. LPA pre-qualification
  
'''1.''' The project and the kind of work to be performed,
+
'''136.9.4.1.1.14.2.1 Required MoDOT Pre-qualification '''
  
'''2.''' The estimated costs,
+
In accordance with Section 102.2 of the Missouri Standard Specifications for Highway Construction, a prime contractor must have a fully responsive contractor questionnaire on file with the Missouri Highways and Transportation Commission (MHTC) at least seven (7) days prior to the bid opening date if this project involves roadway or bridge work. To get on the approved contractor listing prior to letting, click here.  A statement regarding this pre-qualification of a prime contractor must be included in the bid proposal.   For projects involving a roadway or bridge construction, the MoDOT pre-qualification process is required unless the LPA has their own pre-qualification process that had been approved by MoDOT in advance of the project being advertised for bids.  For LPA pre-qualification see EPG 136.9.4.1.1.14.2.3.
  
'''3.''' The estimated federal funds to be provided and
+
'''136.9.4.1.1.14.2.2 Waiving MoDOT Pre-qualification '''
  
'''4.''' The reason or reasons that force account for such project is considered cost effective.
+
If the LPA elects to waive MoDOT’s prequalification process, the following sentence must be inserted into the bid proposal in order to allow contractors not on the listing to submit a bid for the project. “Sec 102.2 of the Missouri Standard Specifications for Highway Construction will be waived for this project.” This statement may only be used on proposed improvements that do not contain roadway or bridge construction (i.e., landscaping, sidewalks, bicycle path, etc.).   
  
There are two methods by which the local agency can be reimbursed for this type of work, and the
+
'''136.9.4.1.1.14.2.3 LPA Pre-qualification'''
estimate should be prepared accordingly. The first method is actual cost. Payment will be made for labor, materials and equipment rental rates. Estimated hours and rates should be included and final reimbursement will be made based on an audit of actual costs.
 
  
The other method is agreed to unit prices. This method requires more extensive justification at the PS&E stage, but reimbursement will be made based on the number of units constructed. This
+
An LPA may wish to use a pre-qualification other than MoDOT’s for proposed improvements. A statement regarding the pre-qualification of a prime contractor must be included in the bid advertisement. The statement should include information for how the contractor can become pre-qualified or indicate where the information can be found. The LPA pre-qualification process must be approved by MoDOT prior to the advertisement for bids for the project.   Requests for approval of qualification criteria must be submitted to MoDOT at least 60 calendar days in advance of the advertisement for bids.  
eliminates some record keeping and detailed audit. The agreed unit prices must be developed using quantities, man-hours, pay rates, material costs and equipment rental rates. The local agency by agreeing to these unit prices also agrees that no construction change order can be made to adjust the unit prices, but a construction change order is allowable for quantity changes. If the local agency and MoDOT can't come to an agreement on the unit price, the local agency can still perform the work by using the actual cost method described above.
 
  
MoDOT will not approve work by the local agency's forces unless it can be demonstrated that it can be accomplished at lower cost than if performed by contract. If the local agency determines they do not want to perform an item and the work is within the scope of the construction contract, they can negotiate a change order with the contractor to perform the work and execute a construction change order. The local agency will need to execute a [[media:136.9.1 Work by Local Forces Proposal (Fig. 9-1).doc|work by local forces proposal]] that must be submitted with the construction estimate.
+
While developing qualification criteria, the LPA should keep in mind that any requirements for the pre-qualification must be based upon a full and appropriate evaluation of the contractor’s capability to perform the work. For further discussion on prequalification of bidders see AASHTO’s [http://www.fhwa.dot.gov/programadmin/contracts/ashtobid.cfm ''Suggested Guidelines for Strengthening Bidding and Contract Procedures''].  This publication contains useful information for consideration when developing pre-qualification criteria.
  
===136.9.9 Specifications and Job Special Provisions===
+
====136.9.4.1.1.15 Disadvantaged Business Enterprise (DBE) ([http://www.fhwa.dot.gov/hep/49cfr26.htm 49 CFR Part 26])====
 +
All federal-aid projects are subject to the legislative and regulatory DBE requirements in order to ensure that DBE firms have an opportunity to participate in federally funded projects.
  
It is recommended that the engineer shall refer to [http://www.modot.mo.gov/business/standards_and_specs/highwayspecs.htm the Missouri Standard Specifications for Highway Construction and Supplemental Specification Revisions]. The engineer
+
The Disadvantaged Business Enterprise (DBE) Contract Provisions are found in [[media:136.9.8 2022.docx|Fig. 136.9.8]]. All bidding documents must refer to 49 CFR Part 26. For each project, the LPA shall submit a request to the MoDOT district representative to establish a DBE goal. The MoDOT district representative must request a DBE goal from MoDOT’s External Civil Rights Division by emailing LPADBEGoal@modot.mo.gov. The DBE goal request must include the engineer’s estimate for the project, preferably in Excel format.  
may modify these specifications, where appropriate for job-specific requirements or conditions, by creating job special provisions. Also, the engineer of record and/or local agency may write their own custom set of specifications. The specification used shall be referenced on both the drawings and the specifications package as the basic standard for materials and construction - except as modified or superseded by job special provisions or other specifications included in the specifications package. When the Missouri Standard Specifications for Highway Construction are supplemented by job special provisions or substituted by other specifications, the cover sheet of the supplementary or substituting specifications package is to be signed and sealed by the engineer.
 
  
MoDOT specifications can be made available to local agencies as either a reference or for actual
+
Since federal funds are used, the DBE goal will apply to the entire project (to include line items which may be funded by other sources). The bid proposal shall require that upon letting the project, the ([[media:Fig. 136.9.9 2020.docx|DBE Submittal Forms, Fig. 136.9.9]]) must be completed and submitted with the bid proposal or delivered by all bidders within three working days after the bid opening date. DBE Identification Submittal Form (Page 2 of the DBE Submittal Forms, Fig. 136.9.9) must be submitted for each DBE to be utilized on the project. DBE requirements are also covered in [[:Category:146 Disadvantaged Business Enterprise (DBE)|EPG 146 Disadvantaged Business Enterprise (DBE)]].
use in contracts. Certain job special provisions are available from MoDOT for a nominal fee;
 
however, [http://www.modot.mo.gov/business/standards_and_specs/jobspecialprovisions.htm MoDOT Job Special Provisions] are available at MoDOT's website. Local agencies are urged to prepare the specifications and special provisions carefully to ensure that the inspection, testing and sampling procedures are adequately covered.
 
  
'''When the local agency decides not to inspect at the fabricators shop, the following specifications regarding acceptance of fabricated structural members shall be included in the specification documents (as Job Special Provisions), as applicable to the following categories
+
Any provision setting a DBE/MBE/WBE goal cannot be allowed unless that program meets the requirements of 49 CFR Part 26. Specifically, Part 26 does not permit separate goals for minorities and females without a specific authorization and waiver. Therefore, no project funded by federal money, whether administered by MoDOT or any other entity receiving federal funds, can contain an MBE or WBE goal, even if mandated by city ordinance. Any project submitted with such a goal will not be approved for federal funds.
of structural members:'''
 
  
====136.9.9.1 Acceptance of Precast Double Tee, I-Girder, Box-Girder and Slab Panels====
+
====136.9.4.1.1.16 On the Job Training (OJT) ([http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&tpl=/ecfrbrowse/Title23/23cfr230_main_02.tpl 23 CFR Section 230])====
The following procedures have been established for the acceptance of precast double tee, I-girder, box-girder and slab panels. Shop drawings shall be submitted to the local agency’s engineer for review and approval. The approval is expected to cover only the general design features, and in no case shall this approval be considered to cover errors or omissions in the shop drawings. The local agency or their consultant has the option of inspecting the precast units during fabrication or requiring the fabricator to furnish a certification of contract compliance and substantiating test reports. In addition, the following reports will be required:
+
The intent of the OJT program, based on 23 CFR Section 230, is to recruit entry-level individuals and provide them with meaningful training with the intent of leading to journey-level employment. It is the policy of the program to require full use of all available training and skill-improvement opportunities to assure the increased participation of minority groups, disadvantaged persons and women in all phases of the highway construction industry.  A request to establish an OJT goal must be submitted to the [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT district contact] for all projects.
  
'''1.''' Certified mill test reports, including results of physical tests on the prestressed strands and reinforcement as required.
+
When a project receives a goal, the [[media:136.9.4.1.1.16_Training.docx|Training Provision]] (contract version) shall be included in the bid proposal.  
  
'''2.''' Test reports on concrete cylinder breaks.
+
For further information and guidance about the OJT program and the submittal forms, you may access the [https://www.modot.org/job-trainingcontract-compliance ECR website] or call (573) 526-2978.
  
The local agency or consultant must verify and document that dimensions of the units were checked at the job and found to be in compliance with the shop drawings.
+
====136.9.4.1.1.17 Acknowledgement of Addenda ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1112&rgn=div8 23 CFR 635.112])====
 +
The bid proposal shall require the acknowledgement and the incorporation of all addenda issued for the project.  Failure of the contractor to do so shall make the bid nonresponsive and not eligible for award consideration.  Verification that bidders received and incorporated any/all addenda issued for the project must be evident in the submitted bidding documents.
  
====136.9.9.2 Acceptance of Structural Steel====
+
====136.9.4.1.1.18 Other submittals required by the LPA====
 +
Federal regulations state that any requirement the bidder must comply with to be considered responsive shall be clearly identified in the bidding documents (Title 23 CFR, Sections 635.112).  Should the LPA choose to require any additional documentation as a condition of responsiveness, the requirement should be pre-approved by MoDOT and then noted in the bidding documents.  Per Title 23 & 29 CFR federal-aid contracts cannot include any provisions that do not meet federal law.
  
The following procedures have been established for the acceptance of structural steel. Shop
+
====136.9.4.1.1.19 Award Language ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1114&rgn=div8 23 CFR 635.114(a)])====
drawings shall be submitted to the local agency’s engineer for review and approval. The approval is expected to cover only the general design features, and in no case shall this approval be considered to cover errors or omissions in the shop drawings. It is recommended that the contract documents contain provisions that the contractor shall utilize a fabricator that meets the appropriate American Institute of Steel Construction (AISC) certification provisions as outlined in [http://www.modot.mo.gov/business/standards_and_specs/Sec1080.pdf Sec 1080.3.1.6]. All welding operations, including material and personnel, shall meet the
+
Federal-aid contracts must be awarded based on the lowest responsible and responsive bid. Responsible is determined <u>prior to award</u> and therefore is referred to as pre-qualified. Responsive means that a bidder has submitted all required documents as outlined in the bid proposal. See [[136.10 Advertisement for Bid and Project Award|EPG 136.10]] for more information on awarding a contract. If using innovative contracting such as add alternates, the bid proposal must have award language stating how the alternates will be considered and how the job will be awarded.  See [[136.7 Design#136.7.5 Innovative Contracting|EPG 136.7.5]] for more information on innovative contracting.
American Welding Society (AWS) specifications. The local agency or their consultant has the
 
option of inspecting the steel units during fabrication or requiring the fabricator to furnish a certification of contract compliance and substantiating test reports. In addition, the following reports will be required:
 
  
'''1.''' Certified mill test reports, including results of chemical and physical tests on all structural steel as furnished; and
+
====136.9.4.1.1.20 Itemized Bid Form====
 +
The bid proposal must include an itemized listing of all pay items included in the project, quantities of each individual pay item and blanks for the contractor to submit a unit price (and extension) for each pay item.  Additionally, the itemized bid form should include pay item categories for roadway, bridge, signing/striping/signal, landscaping/streetscaping, utilities (if completed by contractor), and bicycle/pedestrian facilities so that the bid tabulations can be easily categorized as required in [[media:136.10.2.doc|Fig. 136.10.2]].  [[media:136.9.10.pdf|Fig. 136.9.10]] is an example of a completed itemized bid form.
  
'''2.''' Non-destructive testing reports.
+
====136.9.4.1.1.21 Form FHWA 1273 - Required Federal Contract Provisions ([http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&tpl=/ecfrbrowse/Title23/23cfr633_main_02.tpl 23 CFR 633])====
 +
Form FHWA 1273 ([http://www.fhwa.dot.gov/programadmin/contracts/1273/1273.pdf Fig. 136.9.7]) is a package of federally required contract provisions that must be physically included as special provisions for all federal-aid projects.  These provisions may not be incorporated by reference.
  
The local agency or consultant must verify and document that dimensions of the units were checked at the job and found to be in compliance with the shop drawings.
+
The provisions apply to all work performed on the contract including work performed by subcontract. ''The Form FHWA 1273 is required to be physically incorporated into each contract and subcontract.'' Failure of the LPA to incorporate the Form FHWA 1273 in the contract shall make the construction phase of the project ineligible for federal reimbursement.
  
(Additional information regarding the AISC Certification provisions may be found at the AISC website address, www.aisc.org.)
+
====136.9.4.1.1.22 Changed Condition Clauses====
 +
Standardized changed condition clauses are required to be included in all contracts. The Missouri Standard Specifications and the ''Standard Specifications for Public Works Construction'' (Green Book) contain standard changed condition clauses. If a LPA choses not to use MoDOT's standard specifications, the LPA must still comply with the federal regulations. (Refer to [http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1109&rgn=div8 CFR 635.109].)
  
====136.9.9.3 Preparation of Contract Documents Involving Proporietary Products or System====
+
This regulation requires the use of three different clauses:
  
Generally, on federal aid projects, the use of trade names in plans and specifications is not allowed except as outlined below. The practice of utilizing essentially proprietary products or systems is acceptable if it can be assured that three or more companies can provide an acceptable product. Overall, there are three basic approaches which are available to provide construction plans and specifications that can accommodate the use of proprietary based products or systems.
+
=====136.9.4.1.1.22.1 Differing Site Conditions Clause=====
 +
This clause provides for the adjustment of the contract terms if the contractor encounters:
  
'''1.''' If the product or system will be specified by using trade names, the contract documents need to be prepared so that at least three different brand names of viable producers are specified in conjunction with appropriate contract requirements and also that acceptable equivalents are allowed. If structures are involved, the requirements for final plans and shop
+
:* Subsurface or latent physical conditions that differ materially from those indicated in the contract, or
drawings in item no. 2, below, will apply.
+
:* Unknown physical conditions of an unusual nature that differ materially from those ordinarily encountered and generally recognized as inherent to the work.  
  
'''2.''' The engineer can prepare generic or performance based contract documents which can be
+
=====136.9.4.1.1.22.2 Suspensions of Work Ordered by the Engineer=====
met by at least three viable producers or vendors that are identified by the engineer when
+
This clause provides for the adjustment of the contract terms if the performance of all or a portion of the work is suspended or delayed by the engineer of record for the LPA, in writing, for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry). The contractor is required to submit a request for adjustment, in writing, to the engineer of record for the LPA  within 7 calendar days of receipt of the notice to resume work. Recovery of profit on costs resulting from suspensions of work is not allowed.
the PS&E is submitted. Contracts set up to permit alternate bidding of different types or
 
products providing the same function may also be used provided three vendors are available
 
for each type. For structures, the engineer will prepare complete plans and specifications
 
which will include sufficient key parameters to define the scope of the project such as
 
structure and opening size, important geometrics, loading, hydraulics and foundation
 
information. Using this approach the successful fabricator will provide design computations
 
and shop drawings which are signed and sealed by a professional engineer for review and
 
approval by the local agency’s engineer. Approved final plans for bridge structures should
 
be secured by the MoDOT districts and forwarded to the MoDOT Bridge division for inventory purposes as part of the project closeout.
 
  
'''3.''' Fewer than three (3) specified materials or products may be approved if MoDOT concurs in a finding that it is in the public interest. For instance, a local agency may find it desirable to limit traffic signal controllers to one brand for ease of maintenance and the stocking of repair parts. If the local agency wishes to use fewer than three trade names, the following justification will need to be provided to MoDOT for review/approval:
+
This clause does not preclude the recognition of construction suspensions or delays resulting from the contracting agency’s actions, without written notification. The LPAs may address constructive delays and suspensions, as they chose, in their standard specifications and contract administration procedures.
  
:a. Show how the item(s) is essential for synchronization with the existing roadway facility or that no equally suitable alternative exists.
+
Suspensions must be for unreasonable periods and do not include brief, customary suspensions for reasons inherent to highway construction (i.e., material sampling and testing; approval of shop drawings, material sources, etc.; and other reasonable and customary suspensions necessary for the supervision of construction by the contracting agency). In addition, an adjustment under this clause is not allowed if the work is suspended for other reasons or if an adjustment is provided for, or excluded, under other terms or conditions of the contract.
  
:b. Show how the use of the product(s) will prove to be cost-effective. This should include historical data supporting the cost effectiveness of the products.
+
=====136.9.4.1.1.22.3 Material Changes in the Scope of the Work=====
 +
This clause provides for the adjustment of the contract terms if the engineer of record for the LPA orders, in writing, an alteration in the work or in the quantities that significantly change the character of work. The term “significant change” shall apply only to the following circumstances:
  
:c. Show how using the product(s) will provide ease of maintenance.
+
:* The altered character of the work differs materially from that of the original contract, or
 +
:* A major item of work, as defined in the contract, is increased or decreased by more than 25 percent of the original contract quantity (adjustments shall apply only to that portion in excess of 125 percent of original contract quantity, or in case of a decrease, to the actual quantity performed).
 +
 +
This clause provides for adjustments resulting from formal change orders by the engineer of record for the LPA, in writing, to the extent that the impacted work is part of the contract. Either party may initiate an adjustment and both must be in agreement before the work is performed. As with the suspension of work provision, this clause does not preclude the recognition of construction suspensions or delays.
  
:d. Provide more detail on its spare parts inventory on what impact using the trade name products(s) will have on this inventory (where applicable).
+
===136.9.4.1.2 Bid Proposal – Restricted Provisions ===
  
:e. Provide more detail on standardization. That is, provide estimated quantity of product that was implemented in areas surrounding the product. Also include the date when the trade name product was implemented, where applicable.
+
In accordance with [http://ecfr.gpoaccess.gov/cgi/t/text/text-idx?c=ecfr&sid=5eef70b643d18bbd1698859321364bcb&rgn=div8&view=text&node=23:1.0.1.7.23.1.1.12&idno=23 Title 23 CFR, Section 635.112], nondiscriminatory bidding procedures shall be afforded to all qualified bidders regardless of National, State or local boundaries and without regard to race, color, religion, sex, national origin, age, or handicap. If any provisions of State laws, specifications, regulations, or policies may operate in any manner contrary to Federal requirements, including Title VI of the Civil Rights Act of 1964, to prevent submission of a bid, or prohibit consideration of a bid submitted by any responsible bidder appropriately qualified in accordance with §635.110, such provisions shall not be applicable to Federal-aid projects.
  
If MoDOT concurs, we will forward to [http://www.fhwa.dot.gov/ FHWA] for their approval as may be required.
+
Care should be taken to ensure that the Bid Proposal do not contain any of the restricted provisions listed below.  
  
If the single source material cannot be justified, the item will be non-participating unless bidding procedures are used that establish the unit price of each acceptable alternative, in which case participation will be based on the lowest price established.
+
====136.9.4.1.2.1 Retainage ([https://revisor.mo.gov/main/OneSection.aspx?section=8.960 RsMO 8.960])====
 +
Retainage of contractor payment is not allowed to be automatically applied to projects as a matter of course and shall not be included in the bid proposal. However, the PS&E can state that in accordance with the Missouri Prompt Pay Act (8.960 RSMo), the owner may withhold payment for any of the following reasons, or as determined by the engineer.
  
====136.9.9.4 Shop Drawings====
 
Shop drawings which are prepared in conformance with the engineer’s detailed plans and
 
specifications are not typically required to be signed and sealed by a professional
 
engineer. However, this is not applicable for projects where the contractor may be responsible for the design at the shop drawing stage, e.g., MSE walls, precast culverts, and steel trusses.
 
 
====136.9.9.5 Retainage====
 
Retainage of contractor payment is not to be automatically applied to projects as a matter of course.  However, the PS&E should clearly state that in accordance with the Missouri Prompt Pay Act (34.057 RSMo), the owner may withhold payment for any of the following reasons, or as determined by the engineer.
 
 
:* liquidated damages
 
:* liquidated damages
 
:* unsatisfactory job progress
 
:* unsatisfactory job progress
Line 208: Line 356:
 
:* citation by the enforcing authority for acts of the contractor or subcontractor which do not comply with any material provision of the contract and which result in a violation of any federal, state or local law, regulation or ordinance applicable to that project causing additional costs or damages to the owner.
 
:* citation by the enforcing authority for acts of the contractor or subcontractor which do not comply with any material provision of the contract and which result in a violation of any federal, state or local law, regulation or ordinance applicable to that project causing additional costs or damages to the owner.
  
===136.9.10 Inspection by MoDOT and FHWA===
+
====136.9.4.1.2.2 Warranties ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1413&rgn=div8 23 CFR 635.413])====
 +
The LPA may include warranty provisions in construction contracts in accordance with the following:
 +
 
 +
:1. Warranty provisions shall be for a specific construction product or feature. Items of maintenance not eligible for federal participation shall not be covered.
 +
 
 +
:2. All warranty requirements and subsequent revisions shall be submitted to MoDOT for advance approval.
 +
 
 +
:3. No warranty requirement shall be approved which in the judgment of MoDOT, may place an undue obligation on the contractor for items over which the contractor has no control.
 +
 
 +
Routine warranties or guarantees provided by a manufacturer are valid. Contractors’ warranties or guarantees providing for satisfactory in-service operation of mechanical and electrical equipment and related components for a period not to exceed 6 months following project acceptance are permissible.
 +
 
 +
====136.9.4.1.2.3 Professional Licensure, Certification, Business Licensure and Work Permits====
 +
Any permitting or licensing criteria for contractors, subcontractors, and suppliers must be submitted to MoDOT for advanced approval. MoDOT must review all submissions for approval.  Permitting and licensing criteria that unduly restrict or limit any firm’s ability to bid on and receive award of federal-aid projects will not be approved. If modifications are made to an approved permitting and licensing criteria, the revised criteria must be resubmitted for approval prior to use.
 +
 
 +
====136.9.4.1.2.4 Bidder Qualification Language====
 +
All qualifying or other criteria to determine the responsibility of contractors, subcontractors, and suppliers must be submitted to MoDOT for advanced approval.  Therefore, the notice to bidders (i.e. the bid advertisement) should contain the pre-qualification requirements, not the bid proposal itself.  The bidder qualification language can reside in the bid proposal as long as the bidders are informed PRIOR to bid opening in the notice to contractors.  In short, the pre-qualification language can be in both the notice/advertisement and the bid proposal but the language is required to be in the notice and is optional for the bid proposal.  See [[#136.9.4.1.1.14.2 Pre-qualification of Prime Contractors|EPG 136.9.4.1.1.14.2]] for pre-qualification information.
 +
 
 +
====136.9.4.1.2.5 Project Labor Agreements ====
 +
A Project Labor Agreement (PLA), also called a union agreement, is a contract between labor unions, contractors and governmental agencies. Presidential Executive Order 13202 (signed February 17, 2001) was issued to limit executive branch agencies from using PLAs. Essentially, executive agencies may not require or prohibit contractors to enter into PLAs. Agencies also may not discriminate against contractors based on PLAs. In addition, despite the limits on executive agencies, contractors are not barred from freely agreeing to PLAs.
 +
 
 +
Executive Order 13202 was amended to settle concerns about existing PLAs on projects with multiple contracts. Amendments in Executive Order 13208 allow an agency to request an exemption to the use of PLAs, only if the PLA was in effect before February 17, 2001.
 +
 
 +
Requests for exemption must be written and must include the PLA, specific bid information, and the reason why the agency believes the exemption should be granted. PLAs are allowed only if the FHWA Administrator exempts a project. Requests for exemption should be referred to [http://www.modot.org/business/manuals/LPAContacts.htm MoDOT’s district contact].
 +
 
 +
[http://www.whitehouse.gov/news/releases/2001/02/20010221.html Executive Orders 13202] and [http://www.whitehouse.gov/news/releases/2001/04/20010406-1.html 13208] are available online.
 +
 
 +
====136.9.4.1.2.6 LPA Preferences ([https://www.ecfr.gov/current/title-23/chapter-I/subchapter-G/part-635/subpart-D/section-635.409 CFR 635.409])====
 +
On all federally funded construction projects, materials produced within the state or local area shall not be favored over comparable materials produced outside of the state or local area. Also, in-state material sources cannot be given preference over foreign materials or actions taken against materials of foreign origin unless permitted by federal law. State or local preference provisions are not allowed on federally funded project contracts.
 +
 
 +
====136.9.4.1.2.7 Contract Documents Involving Proprietary Products or System  ([http://www.ecfr.gov/cgi-bin/text-idx?SID=d55e4f29583a8177baf0aa23e2919235&mc=true&node=se23.1.635_1411&rgn=div8 23 CFR 635.411])====
 +
Generally, on federal aid projects, the use of trade names in plans and specifications is not allowed except as outlined in [[136.7 Design#136.7.2.8 Proprietary Items|EPG 136.7.2.8]]. The practice of specifying proprietary products or systems is only acceptable if it can be assured that three or more companies can provide an acceptable product.  See EPG 136.7.2.8 and [[#136.9.2.6 Proprietary Items|EPG 136.9.2.6]] for more information.
 +
 
 +
====136.9.4.1.2.8 Signing Restriction ====
 +
The FHWA Division Administrator has determined that the PS&E provide for the erection of only those information signs and traffic control devices that conform to the standards developed by the Secretary of Transportation or mandates of Federal law and shall not include promotional or other informational signs regarding such matters as identification of public officials, contractors, organizational affiliations, and related logos and symbols.
 +
 
 +
The FHWA Division Administrator has determined that, where applicable, provisions shall be included in the PS&E that require the erection of funding source signs, for the life of the construction project, in accordance with section 154 of the Surface Transportation and Uniform Relocation Assistance Act of 1987.
 +
 
 +
====136.9.4.1.2.9 Employ Missouri ([https://revisor.mo.gov/main/OneSection.aspx?section=290.570 RsMO 290.570])====
 +
A provision stating that when employment is greater than 5% then the entity must employ Missouri citizens can only be used on State Funded projects.
 +
 
 +
==136.9.4.2 Specifications==
 +
 
 +
For information on specification requirements, see [[136.7 Design#136.7.3 Specifications and Standards|EPG 136.7.3 Specifications and Standards]].  The Bid Proposal '''must''' contain all specifications requirements and job special provisions.
 +
 
 +
===136.9.4.2.1 Standard Specifications ===
 +
The bid proposal must clearly indicate the standard specifications which are in effect.  In addition, If more than one is referenced, the order of precedence must be stipulated.  For more information on what Standard Specifications are acceptable on a federally funded project, see [[136.7 Design#136.7.3 Specifications and Standards|EPG 136.7.3 Specifications and Standards]].
 +
 
 +
===136.9.4.2.2 Job Special Provisions===
 +
All Job Special Provisions (JSPs) must be included in the Bid Proposal.  For more information on required JSPs, see [[136.7 Design#136.7.3 Specifications and Standards|EPG 136.7.3 Specifications and Standards]].
 +
 
 +
==136.9.4.3 Standard Plans==
 +
 
 +
The bid proposal must clearly indicate that standard plans which are in effect.  In addition, if more than one is referenced, the order of precedence must be stipulated.  For more information on what standard plans are acceptable on a federally funded project, see [[136.7 Design#136.7.3 Specifications and Standards|EPG 136.7.3 Specifications and Standards]].
 +
 
 +
=136.9.5 Estimate =
 +
 
 +
An engineer's estimate, showing estimated pay item quantities, unit prices and extended totals shall be submitted to MoDOT with the detailed plans prior to bid advertisement.  The engineer's estimate should be treated as a confidential document. Any knowledge of the estimate may cause unbalanced bids or provide a contractor who has knowledge of the engineer's estimate an advantage. For more information on Engineer’s Estimate,  see [[136.7 Design#136.7.4 Engineer’s Estimate|EPG 136.7.4 Engineer’s Estimate]].
 +
 
 +
 
 +
 
  
The project [http://www.modot.mo.gov/business/standards_and_specs/jobspecialprovisions.htm Job Special Provisions] or drawings shall stipulate that MoDOT and FHWA may make inspections of the work and that the contractor shall grant them access to all parts of the work.
+
 +
 +
 +
 +
 +
 +
 +
  
[http://www.modot.mo.gov/ Representatives of MoDOT] will make a final inspection on all projects, preferably at the same time as the local agency makes final inspection.
 
  
===136.9.11 Plans, Specifications and Estimate (PS&E) Submittal===
 
When the plans, specifications and the engineer's estimate of project cost and construction
 
engineering have been completed, the local agency shall submit the "PS&E" documents to
 
MoDOT for review.
 
  
The project sponsor must contact their district office representative to determine how many sets of plans, specifications and estimate of project cost and construction engineering need to be submitted to MoDOT and if these should be submitted by hard copy or electronic PDF. If the project contains a bridge, the completed Structure Inventory and Appraisal Sheet, the vehicle Load Rating Summary Sheet (signed and sealed by the engineer) and load rating calculations must also be submitted at this time. The title sheet of the drawings must be signed by the local agency and all plan sheets signed and sealed by the appropriate professional before MoDOT will provide approval of the submittals. '''Submitted drawings shall be 11 in. x 17 in.'''  When the [http://www.modot.mo.gov/business/standards_and_specs/BEGIN.pdf 2004 Missouri Standard Specifications for Highway Construction] are supplemented by job special provisions or substituted by other MoDOT-approved specifications, the cover sheet of the supplementary or substituting specifications package is to be signed and sealed by the engineer.
 
  
  
 
[[Category:136 Local Public Agency (LPA) Policy|136.09]]
 
[[Category:136 Local Public Agency (LPA) Policy|136.09]]

Latest revision as of 08:47, 3 September 2024

Figures
Federal-Aid Essential Videos


Contents

136.9.1 Introduction

The preparation of the PS&E for local federally funded projects is the responsibility of the local public agency (LPA). The LPA can either prepare the PS&E, or if they are not adequately staffed to do so, they can hire a consultant to prepare the PS&E. In either case, if using federal funds, the LPA must ensure that Preliminary Engineering (PE) funds are obligated prior to beginning any work. The LPA shall ensure that the PS&E complies with all applicable Federal and State Laws and they must certify that that each project complies by signing and submitting the LPA Certification of PS&E (Fig. 136.9.5). The PS&E Submittal Checklist (Fig. 136.9.1) references the Federal and State Laws that pertain to the PS&E submittal package. Most Federal Laws pertaining to the PS&E submittal package can be found in, but not limited to, 23 CFR 635 (Code of Federal Regulations).

The PS&E package must be submitted to MoDOT for review and approval. Any changes that need to be made to the PS&E package will be made by the LPA. After all changes are incorporated, MoDOT will request construction funding obligation from the Federal Highway Administration (FHWA). After FHWA approves the obligation of federal funds for construction, MoDOT will notify the LPA of the authority to advertise for bids. This notification by MoDOT is officially the construction authorization. No project shall be advertised for bids until construction authorization has been issued (23 CFR 635.112).

Competitive bidding will be required except where work by local forces by the LPA (refer to EPG 136.3.12) or work by utility companies has been authorized. A minimum of 12 weeks is the typical timeframe from PS&E submittal to award of the construction contract.

136.9.2 Required Submittals

In order for the LPA to get Construction Authorization which allows advertisement for bids, the PS&E documents must be approved by MoDOT. There are multiple items that should be considered and documented during the preparation of the PS&E. Some of these items are applicable to all projects, while others may or may not be pertinent to a project depending upon the project characteristics. The LPA must fill out the PS&E Submittal Checklist (Fig. 136.9.1) by initialing each item in the checklist and identifying a location of each document the submittal.

136.9.2.1 Environmental, Historical and Cultural Requirements

There are multiple clearances, certifications and a classification that must be considered and/or obtained prior to bid advertisement. EPG 136.6 provides details regarding the environmental, historical and cultural requirements that must be met in conjunction with the development of the project. The LPA should ensure all environmental mitigation commitments pertaining to the project are included in the contract provisions. Failure to meet mitigation commitments may render the project ineligible for federal reimbursement. The LPA is also responsible for communicating permit conditions and restrictions in the final design. All environmental permits applicable to the construction of the project should be included in the proposal. A copy of the Corps of Engineers 404 Permit, Farmland Conversion Impact Statement, SHPO Section 106 concurrence, FEMA Floodplain Development Permit and ALL hazardous waste reports (lead paint and asbestos inspection reports) must be included in the bid proposal. LPA’s should work closely with the permitting agency to ensure accurate interpretation and proper transfer of permit conditions and restrictions (as appropriate) into final design.

136.9.2.2 Right of Way Clearance

In accordance with 23CFR635.309, authorization to advertise for bids cannot be given until a statement is submitted indicating that all right-of-way clearances have been obtained or all necessary arrangements have been made for proper coordination with the physical construction schedule. The right-of-way clearance statement may be made separately or in conjunction with the utility status and railroad statement. Details regarding right-of-way acquisition and clearance can be found in EPG 136.8.

136.9.2.3 Utility Status

In accordance with 23CFR635.309, authorization to advertise for bids cannot be given until a statement regarding utility clearance is submitted. Prior to authorization to advertise for bids, utility work must be completed or necessary arrangements must have been made for completion of the work for proper coordination with the contract construction schedules. The utility status statement may be made separately or in conjunction with the right of way clearance and railroad statements. Details regarding utilities are found in EPG 136.7.

The LPA shall prepare a Utility Status Letter (Fig. 136.9.6) and provide it to MoDOT with the final plans submittal. Projects must be cleared prior to construction obligation and the MoDOT district contact must receive the status letter prior to the bid opening date. Utilities “status” is defined as:

1. All utilities are physically adjusted on the projects, or
2. Utility construction work is active and has been completed to such a point that no impact would be expected to the road contractor. The status of the work is given in the utility job special provisions, or
3. Utilities are not expected to be adjusted by the notice to proceed date for the road project, but the utility work will have no impact on the progress of the road contractor’s work, or
4. Utilities must be adjusted after the contractor completes stage construction. This information must be outlined in a job special provision, or
5. Utility adjustments, plans and specifications, are included in the bid documents for the road project.

Authorization will not be granted until any necessary utility agreements are executed.

136.9.2.4 Railroads

In accordance with 23CFR635.309, authorization to advertise cannot be given until a statement regarding any railroad involvement is submitted even when no railroads are affected by the project. Projects on railroad right of way or crossing railroad right of way require the railway company’s written approval of the final plans prior to construction authorization. This statement may be made separately or in conjunction with the right of way clearance and utility status statements. Details regarding Railroads are found in EPG 136.7 and EPG 643.4 Railroads.

Where construction of a federally funded project requires use of railroad properties or adjustments to railroad facilities, there shall be an agreement in writing between the LPA and the railroad company.

FHWA approval of railroad agreements is required for federal full oversight projects. A copy of the written agreement shall be transmitted to the MoDOT district contact for FHWA review.

Authorization will not be granted until any necessary railroad agreements are executed.

136.9.2.5 Bridge (Structure) Submittals

The LPA is required to submit various deliverables on federally funded projects which include structures as defined in EPG 136.7.2.2.2 General Types of Structures. The requirement for PS&E submittal deliverables is mandatory for structures that meet the definition for highway bridges and culverts as found in EPG 136.7.2.2.1 Highway Bridges and Culverts. For structures that fit the definitions given in EPG 136.7.2.2.2.2 Non-NBI Length Bridges and Culverts, EPG 136.7.2.2.2.3 Pedestrian Structures, EPG 136.7.2.2.2.4 Retaining Walls and EPG 136.7.2.2.2.5 Structures on MoDOT Right of Way, the engineer of record shall review these sections to determine the appropriate PS&E deliverables that are required and to determine the required input from MoDOT Bridge Division.

To aid in the determination of the various deliverables and the responsibilities for these deliverables, the tables in EPG 136.7.2.2.7 Structure Submittal shall be reviewed by the engineer of record. For structures that will be NBI length, Fig. 136.9.1 may also be used for guidance on the deliverables required.

Renovation or demolition of structures requires hazardous waste reports (lead paint and asbestos inspection reports) and must be in the bid proposal. Additionally, a notification of demolition 10 days prior to the start of structure work is required per Sec 202.40.1.1. For more guidance, refer to EPG 136.6.4.10.1 Renovation and Demolition of Structures.

136.9.2.6 Proprietary Items

The use of proprietary items on federally funded projects is discouraged. However, circumstances may exist that require specific products to meet the project need. In these instances, in order for the proprietary item to be eligible for federal funds, three separate, competing products must be identified in the contract documents and an alternative product approval process must be indicated for each proprietary item included. If certain conditions exist that cause this requirement to be unachievable a Public Interest Finding must be obtained. Any proprietary item that does not meet one of the two previously described conditions, must be noted as non-participating on the estimate. Prior to submitting the PS&E, the LPA should obtain a public interest finding for any proprietary items included in the project. The proprietary item and the date the public interest finding was issued should be noted on the PS&E Submittal Checklist that accompanies the PS&E submittal. See EPG 136.7 for details regarding proprietary items and public interest findings.

136.9.2.7 Design Exceptions/Variances

A registered Professional Engineer in the State of Missouri must sign the approval for design exceptions. In addition, the LPA representative with approval authority shall sign approvals for design exceptions. Additional procedures concerning documentation requirements can be found in EPG 136.7.

136.9.2.8 Work By Local Forces

When an LPA desires to use their own forces to construct a project financed with federal funds, a request must be submitted to MoDOT for approval. See EPG 136.3.12 for details on work by local forces.

136.9.2.9 Non-Infrastructure Projects

Submittals for non-infrastructure projects will vary. See EPG 136.5 Non-Infrastructure for details concerning various types of non-infrastructure projects and the required submittals.

136.9.2.10 ADA Checklist

The ADA Checklist (PDF version of Fig. 136.9.4) (or the MS Word version of the ADA Checklist, Fig. 136.9.4), must also be submitted as supporting documentation to the PS&E.

136.9.2.11 PS&E Certification

The LPA certification of PS&E (Fig. 136.9.5) must be submitted with the PS&E when the LPA decides to use standard specifications other than Missouri Standard Specifications for Highway Construction. The LPA must certify that the specifications meet all state and federal laws and regulations.

136.9.3 Plans

The LPA must submit plans as a part of the PS&E submittal package. For requirements on the content of the plans see EPG 136.7. Before submitting plans, the LPA should ensure that all plan sheets are signed and sealed by the engineer of record and that the title sheet is signed by the LPA.

136.9.4 Bid Documents

Bid documents include the bid proposal, specifications and standard plans.

EPG 136.9.4 includes a breakdown of required provisions and restrictions. Many are included in the boilerplate (Fig. 136.9.3) and FHWA 1273 (Fig. 136.9.7). Others should to be included in the specifications and job special provisions, as necessary.

136.9.4.1 Bid Proposal

The LPA is required to use the Federal Project Bid Proposal Boilerplate (Fig. 136.9.3]) or an approved modified version of the boilerplate. For approval of a modified version of the boilerplate, the LPA must submit a proposed version to their MoDOT district contact.The approval of the modified version must occur prior to submitting a project for review and approval.

The bid proposal must contain The Notice to Contractors. This notice is located in the front of the bid proposal and provides prospective bidders with the bid opening date, time and location where bids will be received and opened; a brief description of the project; and the time and location of any pre-bid meetings.

The bid proposal must also contain a List of items required in order for the bids to be considered responsive: Federal regulations state that any requirements the bidder must comply with to be considered responsive should be clearly identified in the bidding documents. (Refer to Title 23 CFR, Sections 635.112).

The Final PS&E Submittal Checklist Fig.136.9.1 includes a list of required federal provisions.

136.9.4.1.1 Bid Proposal – Required Provisions

136.9.4.1.1.1 Contract Time

Contract Time must be specified in the bid proposal and must be monitored by the LPA. Contract time is defined as the maximum time allowed in the contract for completion of all work contained in the contract documents. This time can be established in the specifications by either a specific completion date or a fixed number of calendar days or working days. The definition of calendar days and workings days must be included in the bid proposal if the LPA is not using MoDOT specifications. Contract time often becomes an issue when the traveling public is inconvenienced without any apparent reason. While there may be several reasons for a project to appear dormant, frequently the cause can be traced to excessive contract time or poor contractor scheduling.

Insufficient contract time can result in higher bid prices, increased time overruns and claims, inefficiencies and safety problems. On the other hand, excess contract time can result in increased inefficiencies, unnecessary delays and inconvenience to the public.

There are several different techniques used to determine contract time. See EPG 237.8 for more information.

The LPA should strive for the shortest practical duration of traffic interruptions during highway construction. Innovative contracting methods including incentive/disincentive (I/D), lane rental, A+B contracts or other contract provisions for early completion are available to minimize traffic inconvenience and delay. The FHWA Technical Advisory 5080.10, Incentive/Disincentive for Early Completion, describes this technique in detail, and is available in the appendix of FHWA's Contract Administration Core Curriculum.

136.9.4.1.1.2 Liquidated Damages (23 CFR 635.127)

A provision for liquidated damages must be included in the bid proposal and must be administered by the LPA. The term liquidated damages means the daily amount set forth in the contract to be deducted from the contract price to cover additional costs incurred by the LPA because of the contractor’s failure to complete the contract work within the number of calendar days or work days specified.

The actual liquidated damage rate must be specified in the bid proposal. The amount of project costs that will be eligible for federal participation will be reduced by the amount of any liquidated damages assessed against the contractor. In determining the amount eligible for participation, the amount of liquidated damages will first be deducted from the amount of construction engineering claimed and then from construction costs if the amount of liquidated damages exceeds the amount of construction engineering. The liquidated damages should be, at a minimum, the amount shown in the following table corresponding to the original contract amount to minimize the risk of losing full federal participation.

Schedule of Deductions for Each Day of Overrun in Contract Time,
Original Contract Amount (or the Engineer's Estimate of the Total Construction Cost)
From ($) To, and including ($) Assessment, per Day ($)
0 25,000 475
25,001 50,000 475
50,001 100,000 500
100,001 500,000 700
500,001 1,000,000 950
1,000,001 2,000,000 1,100
2,000,001 3,000,000 1,225
3,000,001 4,000,000 1,625
4,000,001 5,000,000 2,025
5,000,001 6,000,000 2,425
6,000,001 7,000,000 2,825
7,000,001 8,000,000 3,225
8,000,001 9,000,000 3,625
9,000,001 10,000,000 4,025
10,000,001 70,000,000 4,300

136.9.4.1.1.3 Bid Guaranty (49 CFR 18.36)

The bid proposal must include criteria requiring a bid guarantee of at least 5% of the bid amount. The bid proposal may include bid bond requirements over 5%, although the LPA should consider excessive burdens put on the contractor where higher percentage bid bonds are required on large projects. Bid bond requirements expressed as a dollar amount are not allowed. The bid guaranty can be in the form of a cashier’s check, certified check or bid bond. Bid bonds must be guaranteed by a surety company authorized by the director of the department of insurance, financial institutions and professional registration to conduct surety business in the state of Missouri. More detail regarding bid guaranty can be found in RSMO 227.100 and Sec 102.9. MoDOT has included an example bid bond in the Federal Project Bid Proposal Boilerplate Fig. 136.9.3.

136.9.4.1.1.4 Certifications Regarding Affirmative Action and Equal Opportunity

The LPA shall include requirements for certification pursuant to 41 CFR Parts 60-2, 60.1, 60.1.4 and Executive Order No. 11246 regarding affirmative action and equal opportunity in the bidding documents. Sec 102.18.1 details the compliance requirements. The Federal Project Bid Proposal Boilerplate (Fig. 136.9.3) addresses this in (6) CERTIFICATIONS FOR FEDERAL JOBS for the prime contractor. . If the bid proposal boilerplate is modified, Section 102.18.1 of the Missouri Standard Specification for Highway Construction cannot be waived. A certification regarding affirmative action and equal opportunity for the subcontractor (Fig. 136.9.2) must be submitted for all subcontractors prior to the notice to proceed for construction.

136.9.4.1.1.5 Suspension and Debarment Certification (23 CFR 635.112)

On all federal-aid construction contracts and all related subcontracts, the contractor and lower tier participants must certify they are in compliance with this provision. This includes subcontractors, material suppliers and vendors.

Each participant in the contract must certify “that it is not presently debarred, suspended, proposed for debarment, declared ineligible or voluntarily excluded from covered transactions by any federal agency and they have not been convicted or had civil judgment rendered within the past 3 years for certain types of offenses”. It is the LPA’s responsibility to assure that the contractor is not suspended or debarred from federal contracts. The System for Award Management website is helpful.

The LPA shall include the lobbying certification requirement 49 CFR Part 29 regarding suspension and debarment certification in the bidding documents. The Federal Project Bid Proposal Boilerplate, covers this requirement in Section (6) CERTIFICATIONS FOR FEDERAL JOBS. If the bid proposal boilerplate is modified, Sec 102.18.1 cannot be waived.

136.9.4.1.1.6 Anti-collusion Provision (23 CFR 635.112)

The bidding documents shall include a non-collusion provision to the following effect: Each bidder shall file a statement executed by, or on behalf of the person, firm, association, or corporation submitting the bid certifying that such person, firm, association, or corporation has not, either directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken any action, in restraint of free competitive bidding in connection with the submitted bid.

The Federal Bid Proposal Boilerplate (Figure 136.9.3), includes the anti-collusion certification requirements in Section (6) CERTIFICATIONS FOR FEDERAL JOBS and Section (14) SIGNATURE AND IDENTITY OF BIDDER. If the bid proposal boilerplate is modified, Sec 102.18.3 cannot be waived.

136.9.4.1.1.7 Lobbying Certification (49 CFR part 20)

On all federally funded construction contracts and all related subcontracts of $100,000 or more, federal funds may not be used to provide financial gain to a member of congress or a federal agency. Awarding a federal-aid contract to a constituent would be an example of financial gain. This applies to contractors as well as subcontractors. A certification by the contractor indicating they have not and will not use federal funds to make any payments for lobbying must be included in the contract proposal.

The LPA shall include the lobbying certification requirement pursuant to 49 CFR part 20 in the bidding documents. The Federal Project Bid Proposal Boilerplate (Figure 136.9.3) includes the lobbying certification requirements in Section (6) CERTIFICATIONS FOR FEDERAL JOBS. If the bid proposal boilerplate is modified, Sec 102.18.4 cannot be waived.

136.9.4.1.1.8 Title VI Civil Rights Assurances (23 CFR 635.112(d))

The following Title VI Civil Rights Assurances notification must be included in the invitation to bidders in the front of all bid proposals and in any bid advertisements and invitations for bids:

“The County/City/Organization of _______________________ hereby notifies all bidders that it will affirmatively ensure that in any contract entered into pursuant to this advertisement, businesses owned and controlled by socially and economically disadvantaged individuals will be afforded full opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, religion, creed, sex, age, ancestry, or national origin in consideration for an award.”

136.9.4.1.1.9 Inspection by MoDOT and FHWA (Sec 105.10)

The project Bid Proposal shall stipulate that MoDOT and FHWA may make inspections of the work at any time and that the contractor shall grant them access to all parts of the work.

136.9.4.1.1.10 Wage Rates (RsMO 290.263)

A statement is required in the Bid Proposal indicating that when state and federal wage rates are both required the higher of the two for each job classification should be used.

136.9.4.1.1.10.1 Federal Wage Rates (23 USC 113 and 29 CFR 5)

The payment of predetermined minimum wages on federal-aid contracts is derived from the Davis-Bacon Act of 1931 and is prescribed by 23 USC 113. These wage rates must be physically inserted in the Bid Proposal on all federal-aid highway construction projects exceeding $2,000 and to all related subcontracts.

The federal minimum wage rates are available from the Department of Labor’s Wage and Hour Division website (click on “Wage Determinations” at the bottom of the page and then click on “Public Building or Works” or directly from the SAM.gov website. Once at the search location, select all appropriate information, including “Missouri” and the county in which the work is taking place. For LPAs in Missouri to be in conformance with the federal “10-day rule”, LPAs are to access the “Federal Wage Rates” ten days prior to bid opening to see if updated federal wage rates have been posted. The applicable wage rates will be posted 10 days prior to the bid opening. When the wage rates change within the 10-day window, the LPA will not update the wage rates since doing so will not provide contractors with sufficient time to accommodate the revised wage order. If the updated wage rates have been posted, LPAs are required to issue an addendum to insert the updated wage rates in their final contract package.

Federal wage rates are not required to be physically included in the contract advertising package provided they are referenced to an Internet web site address where they can be found or they can be posted at a referenced location that is readily accessible by all bidders. The final contract package signed by the LPA and the contractor must physically contain the federal wage rates, including updates if applicable.

136.9.4.1.1.10.2 State Wage Rates (8 CSR 30-3)

The LPA must request an Annual State Wage Determination for each contract from the Industrial Commission, Missouri Department of Labor and Industrial Relations (DOLIR), Box 449, Jefferson City, Missouri 65102 or by calling (573) 751-3403. The LPA will receive a password from the Missouri DOLIR which is required to access the official Annual Wage Order and incremental increases on the Missouri DOLIR webpage. Contracts must be awarded within one year of the issuance of the official Annual Wage Order or the LPA will be required to request a new Annual Wage Order determination. The Annual Wage Order must be included in the proposal and must be part of the contract.

136.9.4.1.1.11 E-Verify Affidavit & MOU (RsMO 285.530)

The bid proposal must state that requirements regarding the Federal Work Authorization Program and list the Federal website for E-Verify. The bid proposal must state that the E-verify affidavit and MOU must be submitted prior to award of the contract.

136.9.4.1.1.12 OSHA 10-Hour Training (RsMO 292.675)

The bid proposal must state that the bidders must adhere to the OSHA 10-Hour Training requirements.

136.9.4.1.1.13 Buy America (CFR 635.410)

On all federal-aid construction projects, 23 CFR 635.410 requires that steel and iron used be made in the United States. The “Buy America” provision is applicable to all steel and iron materials, except as noted below, regardless of the percentage of steel in the manufactured product. All manufacturing processes involved in steel or iron products must occur within the United States. These processes include rolling, extruding, machining, bending, grinding, drilling, coating, welding and smelting. Domestically produced steel billets or iron ingots shipped overseas for any process and returned to the United States do not conform to this requirement. Buy America provisions do not apply to:

  • Minimal use of all foreign material in which the total delivery cost to the project site is less than $2500 or 0.1 percent of the contract amount, whichever is greater.
  • Raw materials; scrap temporary steel items such as sheet pilings, bridges, steel scaffolding and false work.
  • Materials that remain in place at the contractor’s convenience such as sheet pilings and forms.
  • Pig iron manufactured outside the United States.

An LPA shall not list an ineligible iron or steel product as “nonparticipating” in order to circumvent the Buy America requirements.

A waiver of the Buy America requirements by the FHWA Division Administrator is permitted for specific projects, specific products, specific geographical areas or combinations if:

  • Buy America is inconsistent with the public interest, or
  • There is not a sufficient supply of domestic materials of satisfactory quality.

Failure to comply with the Buy America Policy can result in loss of federal funding, not just for the item, but for the entire project. Approval for waiver of Buy America requirements must be obtained from FHWA.

Buy America should not be confused with Buy American.

136.9.4.1.1.14 Contractor Requirements

136.9.4.1.1.14.1 Work completed by the Prime Contractor (23 CFR 635.116)

The bid proposal shall stipulate that the prime contractor on a project must perform, with its own staff, contract work amounting to not less than 30% of the total original contract price.

136.9.4.1.1.14.2 Pre-qualification of Prime Contractors

Prequalification of contractors may be required as a condition of submission of a bid or award of contract only if the period between the date of issuing a request for bids and the date of opening of bids affords sufficient time to enable a bidder to obtain the required prequalification rating or approval. All prequalification criteria must be submitted to MoDOT for approval in advance of the date of issuing a request for bids. The intent of the pre-qualification of contractors is not to intentionally disqualify contractor but to qualify contractors based on a set criteria.

Depending upon the project type and the LPA’s preference, one of the following scenarios will apply to a project:

  • LPA shall require MoDOT Pre-Qualification
  • LPA shall waive MoDOT Pre-Qualification and use no pre-qualification requirement
  • LPA shall waive MoDOT Pre-Qualification and use their own pre-qualification process i.e. LPA pre-qualification

136.9.4.1.1.14.2.1 Required MoDOT Pre-qualification

In accordance with Section 102.2 of the Missouri Standard Specifications for Highway Construction, a prime contractor must have a fully responsive contractor questionnaire on file with the Missouri Highways and Transportation Commission (MHTC) at least seven (7) days prior to the bid opening date if this project involves roadway or bridge work. To get on the approved contractor listing prior to letting, click here. A statement regarding this pre-qualification of a prime contractor must be included in the bid proposal. For projects involving a roadway or bridge construction, the MoDOT pre-qualification process is required unless the LPA has their own pre-qualification process that had been approved by MoDOT in advance of the project being advertised for bids. For LPA pre-qualification see EPG 136.9.4.1.1.14.2.3.

136.9.4.1.1.14.2.2 Waiving MoDOT Pre-qualification

If the LPA elects to waive MoDOT’s prequalification process, the following sentence must be inserted into the bid proposal in order to allow contractors not on the listing to submit a bid for the project. “Sec 102.2 of the Missouri Standard Specifications for Highway Construction will be waived for this project.” This statement may only be used on proposed improvements that do not contain roadway or bridge construction (i.e., landscaping, sidewalks, bicycle path, etc.).

136.9.4.1.1.14.2.3 LPA Pre-qualification

An LPA may wish to use a pre-qualification other than MoDOT’s for proposed improvements. A statement regarding the pre-qualification of a prime contractor must be included in the bid advertisement. The statement should include information for how the contractor can become pre-qualified or indicate where the information can be found. The LPA pre-qualification process must be approved by MoDOT prior to the advertisement for bids for the project. Requests for approval of qualification criteria must be submitted to MoDOT at least 60 calendar days in advance of the advertisement for bids.

While developing qualification criteria, the LPA should keep in mind that any requirements for the pre-qualification must be based upon a full and appropriate evaluation of the contractor’s capability to perform the work. For further discussion on prequalification of bidders see AASHTO’s Suggested Guidelines for Strengthening Bidding and Contract Procedures. This publication contains useful information for consideration when developing pre-qualification criteria.

136.9.4.1.1.15 Disadvantaged Business Enterprise (DBE) (49 CFR Part 26)

All federal-aid projects are subject to the legislative and regulatory DBE requirements in order to ensure that DBE firms have an opportunity to participate in federally funded projects.

The Disadvantaged Business Enterprise (DBE) Contract Provisions are found in Fig. 136.9.8. All bidding documents must refer to 49 CFR Part 26. For each project, the LPA shall submit a request to the MoDOT district representative to establish a DBE goal. The MoDOT district representative must request a DBE goal from MoDOT’s External Civil Rights Division by emailing LPADBEGoal@modot.mo.gov. The DBE goal request must include the engineer’s estimate for the project, preferably in Excel format.

Since federal funds are used, the DBE goal will apply to the entire project (to include line items which may be funded by other sources). The bid proposal shall require that upon letting the project, the (DBE Submittal Forms, Fig. 136.9.9) must be completed and submitted with the bid proposal or delivered by all bidders within three working days after the bid opening date. DBE Identification Submittal Form (Page 2 of the DBE Submittal Forms, Fig. 136.9.9) must be submitted for each DBE to be utilized on the project. DBE requirements are also covered in EPG 146 Disadvantaged Business Enterprise (DBE).

Any provision setting a DBE/MBE/WBE goal cannot be allowed unless that program meets the requirements of 49 CFR Part 26. Specifically, Part 26 does not permit separate goals for minorities and females without a specific authorization and waiver. Therefore, no project funded by federal money, whether administered by MoDOT or any other entity receiving federal funds, can contain an MBE or WBE goal, even if mandated by city ordinance. Any project submitted with such a goal will not be approved for federal funds.

136.9.4.1.1.16 On the Job Training (OJT) (23 CFR Section 230)

The intent of the OJT program, based on 23 CFR Section 230, is to recruit entry-level individuals and provide them with meaningful training with the intent of leading to journey-level employment. It is the policy of the program to require full use of all available training and skill-improvement opportunities to assure the increased participation of minority groups, disadvantaged persons and women in all phases of the highway construction industry. A request to establish an OJT goal must be submitted to the MoDOT district contact for all projects.

When a project receives a goal, the Training Provision (contract version) shall be included in the bid proposal.

For further information and guidance about the OJT program and the submittal forms, you may access the ECR website or call (573) 526-2978.

136.9.4.1.1.17 Acknowledgement of Addenda (23 CFR 635.112)

The bid proposal shall require the acknowledgement and the incorporation of all addenda issued for the project. Failure of the contractor to do so shall make the bid nonresponsive and not eligible for award consideration. Verification that bidders received and incorporated any/all addenda issued for the project must be evident in the submitted bidding documents.

136.9.4.1.1.18 Other submittals required by the LPA

Federal regulations state that any requirement the bidder must comply with to be considered responsive shall be clearly identified in the bidding documents (Title 23 CFR, Sections 635.112). Should the LPA choose to require any additional documentation as a condition of responsiveness, the requirement should be pre-approved by MoDOT and then noted in the bidding documents. Per Title 23 & 29 CFR federal-aid contracts cannot include any provisions that do not meet federal law.

136.9.4.1.1.19 Award Language (23 CFR 635.114(a))

Federal-aid contracts must be awarded based on the lowest responsible and responsive bid. Responsible is determined prior to award and therefore is referred to as pre-qualified. Responsive means that a bidder has submitted all required documents as outlined in the bid proposal. See EPG 136.10 for more information on awarding a contract. If using innovative contracting such as add alternates, the bid proposal must have award language stating how the alternates will be considered and how the job will be awarded. See EPG 136.7.5 for more information on innovative contracting.

136.9.4.1.1.20 Itemized Bid Form

The bid proposal must include an itemized listing of all pay items included in the project, quantities of each individual pay item and blanks for the contractor to submit a unit price (and extension) for each pay item. Additionally, the itemized bid form should include pay item categories for roadway, bridge, signing/striping/signal, landscaping/streetscaping, utilities (if completed by contractor), and bicycle/pedestrian facilities so that the bid tabulations can be easily categorized as required in Fig. 136.10.2. Fig. 136.9.10 is an example of a completed itemized bid form.

136.9.4.1.1.21 Form FHWA 1273 - Required Federal Contract Provisions (23 CFR 633)

Form FHWA 1273 (Fig. 136.9.7) is a package of federally required contract provisions that must be physically included as special provisions for all federal-aid projects. These provisions may not be incorporated by reference.

The provisions apply to all work performed on the contract including work performed by subcontract. The Form FHWA 1273 is required to be physically incorporated into each contract and subcontract. Failure of the LPA to incorporate the Form FHWA 1273 in the contract shall make the construction phase of the project ineligible for federal reimbursement.

136.9.4.1.1.22 Changed Condition Clauses

Standardized changed condition clauses are required to be included in all contracts. The Missouri Standard Specifications and the Standard Specifications for Public Works Construction (Green Book) contain standard changed condition clauses. If a LPA choses not to use MoDOT's standard specifications, the LPA must still comply with the federal regulations. (Refer to CFR 635.109.)

This regulation requires the use of three different clauses:

136.9.4.1.1.22.1 Differing Site Conditions Clause

This clause provides for the adjustment of the contract terms if the contractor encounters:

  • Subsurface or latent physical conditions that differ materially from those indicated in the contract, or
  • Unknown physical conditions of an unusual nature that differ materially from those ordinarily encountered and generally recognized as inherent to the work.
136.9.4.1.1.22.2 Suspensions of Work Ordered by the Engineer

This clause provides for the adjustment of the contract terms if the performance of all or a portion of the work is suspended or delayed by the engineer of record for the LPA, in writing, for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry). The contractor is required to submit a request for adjustment, in writing, to the engineer of record for the LPA within 7 calendar days of receipt of the notice to resume work. Recovery of profit on costs resulting from suspensions of work is not allowed.

This clause does not preclude the recognition of construction suspensions or delays resulting from the contracting agency’s actions, without written notification. The LPAs may address constructive delays and suspensions, as they chose, in their standard specifications and contract administration procedures.

Suspensions must be for unreasonable periods and do not include brief, customary suspensions for reasons inherent to highway construction (i.e., material sampling and testing; approval of shop drawings, material sources, etc.; and other reasonable and customary suspensions necessary for the supervision of construction by the contracting agency). In addition, an adjustment under this clause is not allowed if the work is suspended for other reasons or if an adjustment is provided for, or excluded, under other terms or conditions of the contract.

136.9.4.1.1.22.3 Material Changes in the Scope of the Work

This clause provides for the adjustment of the contract terms if the engineer of record for the LPA orders, in writing, an alteration in the work or in the quantities that significantly change the character of work. The term “significant change” shall apply only to the following circumstances:

  • The altered character of the work differs materially from that of the original contract, or
  • A major item of work, as defined in the contract, is increased or decreased by more than 25 percent of the original contract quantity (adjustments shall apply only to that portion in excess of 125 percent of original contract quantity, or in case of a decrease, to the actual quantity performed).

This clause provides for adjustments resulting from formal change orders by the engineer of record for the LPA, in writing, to the extent that the impacted work is part of the contract. Either party may initiate an adjustment and both must be in agreement before the work is performed. As with the suspension of work provision, this clause does not preclude the recognition of construction suspensions or delays.

136.9.4.1.2 Bid Proposal – Restricted Provisions

In accordance with Title 23 CFR, Section 635.112, nondiscriminatory bidding procedures shall be afforded to all qualified bidders regardless of National, State or local boundaries and without regard to race, color, religion, sex, national origin, age, or handicap. If any provisions of State laws, specifications, regulations, or policies may operate in any manner contrary to Federal requirements, including Title VI of the Civil Rights Act of 1964, to prevent submission of a bid, or prohibit consideration of a bid submitted by any responsible bidder appropriately qualified in accordance with §635.110, such provisions shall not be applicable to Federal-aid projects.

Care should be taken to ensure that the Bid Proposal do not contain any of the restricted provisions listed below.

136.9.4.1.2.1 Retainage (RsMO 8.960)

Retainage of contractor payment is not allowed to be automatically applied to projects as a matter of course and shall not be included in the bid proposal. However, the PS&E can state that in accordance with the Missouri Prompt Pay Act (8.960 RSMo), the owner may withhold payment for any of the following reasons, or as determined by the engineer.

  • liquidated damages
  • unsatisfactory job progress
  • defective construction work or material not remedied
  • disputed work
  • failure to comply with any material provision of the contract
  • third party claims filed or reasonable evidence that a claim will be filed
  • failure to make timely payments for labor, equipment or materials
  • damage to a contractor, subcontractor or material supplier
  • reasonable evidence that a subcontractor or material supplier cannot be fully compensated under its contract with the contractor for the unpaid balance of the contract sum
  • citation by the enforcing authority for acts of the contractor or subcontractor which do not comply with any material provision of the contract and which result in a violation of any federal, state or local law, regulation or ordinance applicable to that project causing additional costs or damages to the owner.

136.9.4.1.2.2 Warranties (23 CFR 635.413)

The LPA may include warranty provisions in construction contracts in accordance with the following:

1. Warranty provisions shall be for a specific construction product or feature. Items of maintenance not eligible for federal participation shall not be covered.
2. All warranty requirements and subsequent revisions shall be submitted to MoDOT for advance approval.
3. No warranty requirement shall be approved which in the judgment of MoDOT, may place an undue obligation on the contractor for items over which the contractor has no control.

Routine warranties or guarantees provided by a manufacturer are valid. Contractors’ warranties or guarantees providing for satisfactory in-service operation of mechanical and electrical equipment and related components for a period not to exceed 6 months following project acceptance are permissible.

136.9.4.1.2.3 Professional Licensure, Certification, Business Licensure and Work Permits

Any permitting or licensing criteria for contractors, subcontractors, and suppliers must be submitted to MoDOT for advanced approval. MoDOT must review all submissions for approval. Permitting and licensing criteria that unduly restrict or limit any firm’s ability to bid on and receive award of federal-aid projects will not be approved. If modifications are made to an approved permitting and licensing criteria, the revised criteria must be resubmitted for approval prior to use.

136.9.4.1.2.4 Bidder Qualification Language

All qualifying or other criteria to determine the responsibility of contractors, subcontractors, and suppliers must be submitted to MoDOT for advanced approval. Therefore, the notice to bidders (i.e. the bid advertisement) should contain the pre-qualification requirements, not the bid proposal itself. The bidder qualification language can reside in the bid proposal as long as the bidders are informed PRIOR to bid opening in the notice to contractors. In short, the pre-qualification language can be in both the notice/advertisement and the bid proposal but the language is required to be in the notice and is optional for the bid proposal. See EPG 136.9.4.1.1.14.2 for pre-qualification information.

136.9.4.1.2.5 Project Labor Agreements

A Project Labor Agreement (PLA), also called a union agreement, is a contract between labor unions, contractors and governmental agencies. Presidential Executive Order 13202 (signed February 17, 2001) was issued to limit executive branch agencies from using PLAs. Essentially, executive agencies may not require or prohibit contractors to enter into PLAs. Agencies also may not discriminate against contractors based on PLAs. In addition, despite the limits on executive agencies, contractors are not barred from freely agreeing to PLAs.

Executive Order 13202 was amended to settle concerns about existing PLAs on projects with multiple contracts. Amendments in Executive Order 13208 allow an agency to request an exemption to the use of PLAs, only if the PLA was in effect before February 17, 2001.

Requests for exemption must be written and must include the PLA, specific bid information, and the reason why the agency believes the exemption should be granted. PLAs are allowed only if the FHWA Administrator exempts a project. Requests for exemption should be referred to MoDOT’s district contact.

Executive Orders 13202 and 13208 are available online.

136.9.4.1.2.6 LPA Preferences (CFR 635.409)

On all federally funded construction projects, materials produced within the state or local area shall not be favored over comparable materials produced outside of the state or local area. Also, in-state material sources cannot be given preference over foreign materials or actions taken against materials of foreign origin unless permitted by federal law. State or local preference provisions are not allowed on federally funded project contracts.

136.9.4.1.2.7 Contract Documents Involving Proprietary Products or System (23 CFR 635.411)

Generally, on federal aid projects, the use of trade names in plans and specifications is not allowed except as outlined in EPG 136.7.2.8. The practice of specifying proprietary products or systems is only acceptable if it can be assured that three or more companies can provide an acceptable product. See EPG 136.7.2.8 and EPG 136.9.2.6 for more information.

136.9.4.1.2.8 Signing Restriction

The FHWA Division Administrator has determined that the PS&E provide for the erection of only those information signs and traffic control devices that conform to the standards developed by the Secretary of Transportation or mandates of Federal law and shall not include promotional or other informational signs regarding such matters as identification of public officials, contractors, organizational affiliations, and related logos and symbols.

The FHWA Division Administrator has determined that, where applicable, provisions shall be included in the PS&E that require the erection of funding source signs, for the life of the construction project, in accordance with section 154 of the Surface Transportation and Uniform Relocation Assistance Act of 1987.

136.9.4.1.2.9 Employ Missouri (RsMO 290.570)

A provision stating that when employment is greater than 5% then the entity must employ Missouri citizens can only be used on State Funded projects.

136.9.4.2 Specifications

For information on specification requirements, see EPG 136.7.3 Specifications and Standards. The Bid Proposal must contain all specifications requirements and job special provisions.

136.9.4.2.1 Standard Specifications

The bid proposal must clearly indicate the standard specifications which are in effect. In addition, If more than one is referenced, the order of precedence must be stipulated. For more information on what Standard Specifications are acceptable on a federally funded project, see EPG 136.7.3 Specifications and Standards.

136.9.4.2.2 Job Special Provisions

All Job Special Provisions (JSPs) must be included in the Bid Proposal. For more information on required JSPs, see EPG 136.7.3 Specifications and Standards.

136.9.4.3 Standard Plans

The bid proposal must clearly indicate that standard plans which are in effect. In addition, if more than one is referenced, the order of precedence must be stipulated. For more information on what standard plans are acceptable on a federally funded project, see EPG 136.7.3 Specifications and Standards.

136.9.5 Estimate

An engineer's estimate, showing estimated pay item quantities, unit prices and extended totals shall be submitted to MoDOT with the detailed plans prior to bid advertisement. The engineer's estimate should be treated as a confidential document. Any knowledge of the estimate may cause unbalanced bids or provide a contractor who has knowledge of the engineer's estimate an advantage. For more information on Engineer’s Estimate, see EPG 136.7.4 Engineer’s Estimate.